Resolved
Resolved That the report be received and noted.
Governance and Audit Committee noted this item on Monday 23 May 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved That the report be received and noted.
Detailed Findings Appendix A Control Evaluation Appendix B Action Plan Appendix C 1.0 Introduction
1.1As part of the audit plan for 2010/11 a system review was undertaken on the Control of ICT Equipment Systems and Procedures.
1.2The system was examined using a CIPFA matrix modified by Internal Audit to test the controls that should be in place within the Authority.
1.3As the audit was conducted early in the 2010/2011 financial year sample testing was conducted for the 2009/2010 financial year.
1.4Acknowledgement is given to the staff concerned for their help and assistance during the course of the audit.
1.5Copies of this report have been sent to the Executive Director of Customer Services, the Assistant Director ICT, Business Services, Service Support and Procurement and the ICT Operations Manager. A copy may also be passed to the Audit Committee for them to monitor/comment upon recommendations made and accepted.
1.6The report is addressed to appropriate Councillors and Officers and may contain confidential and/or privileged material. Any review, reproduction, external distribution, dissemination or other use of, or taking of any action in reliance upon, this information by persons or entities other than the Authority is prohibited.
2.1All ICT hardware and software procured by the Authority should be procured by the ICT Department. Failure to procure items in this way could lead to compatibility and information security issues and may result in the equipment not being supported by the ICT Department.
2.2Before any ICT equipment is procured the requesting department must first complete and submit a standard project request form to the ICT Department. The ‘Request for ICT Services’ form needs to be fully completed and appropriately authorised.
2.3The ICT Department utilises a computerised management information system to record and monitor items ordered, received and installed.
2.4A computerised asset register exists and is linked to the management information system. The asset register contains project number, order number, specification, manufacturer, serial number, location and cost centre for each item maintained by the Authority.
2.5It is the ICT Department’s responsibility to install all new ICT equipment and move items between offices when requested.
Merthyr Tydfil County Borough Council 13/05/2011 Internal Audit Service 1 of 4 Control of Equipment Systems and Procedures 2.6 The ICT Department maintains a large stock of consumables and various ICT peripherals including printer carriages, USB pens, cables etc. All stock items are held in a storage cupboard in the ICT Department to which only ICT Department staff have access.
3.0Scope and Objectives
3.1The objective of the audit was to evaluate the system with a view to delivering reasonable assurance to the Authority over the adequacy of the internal control environment. This is defined as the whole system of controls, established by management, which help to ensure the achievement of objectives, economy and efficiency, compliance with policies and procedures, safeguarding of assets and the integrity and reliability of information.
3.2The system has been evaluated against the following control objectives:
• Policy • Requisition forms • Ordering • Delivery & Receipt of items • Asset Register • Physical Control • Departmental Inventories • Installation • Insurance
4.0Methodology
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Control of ICT Equipment Internal Audit Report 2010/11Report | 12 pages | DownloadRead as text |
Follow Governance and Audit Committee at Merthyr Tydfil and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 Sep 2026 | Peer Panel Performance Assessment - Response and Action PlanResolved that the report and draft action plan be noted and recommended to Council for approval. | Noted | Open |
| 28 Sep 2026 | Terms of ReferenceResolved that the Governance and Audit Committee be approved and reviewed annually. | Approved | Open |
| 28 Sep 2026 | Governance and Audit Committee Annual Report 2025/26Resolved that the Annual Report be noted, amended as appropriate in relation to the attendance record, and recommende... | Noted | Open |
| 22 Jun 2026 | Appointment of Chair and Vice ChairResolved; That Martin Veale continue as Chair and Colin Prosser continue as Vice-Chair of the Governance and Audit Co... | Decided | Open |
| 1 Sep 2025 | Time of Future MeetingsIt was agreed that future meetings would be moved to 5pm and if there was an issue with officer availability for any ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.