Detailed Findings Appendix A Previous Report Recommendations Appendix B Control Evaluation Appendix C Action Plan Appendix D 1.0 Introduction
1.1As part of the audit plan for 2010-11 a system review was undertaken of the Budgetary Control system.
1.2The system was examined using a CIPFA matrix to test the controls that should be in place within the Authority.
1.3Sample testing was conducted for the 2010/11 financial year.
1.4Acknowledgement is given to the staff concerned for their help and assistance during the course of the audit.
1.5Copies of this report have been sent to the Group Accountant and the Chief Finance Officer. A copy may also be passed to the Audit Committee for them to monitor/comment upon recommendations made and accepted.
1.6The report is addressed to appropriate Councillors and Officers and may contain confidential and/or privileged material. Any review, reproduction, external distribution, dissemination or other use of, or taking of any action in reliance upon, this information by persons or entities other than the Authority is prohibited.
2.1The Accountancy Service prepares a revenue budget annually that is approved by Cabinet and Full Council. Budgets are compiled for each service area based on previous estimates uplifted for known factors e.g. inflation, pay awards.
2.2The Authority utilises the Agresso financial management system to record income and expenditure against cost centres and account codes and prepare monthly budget monitoring statements for budget holders that shows spend to date and projected spend against revenue estimates.
2.3Variances are monitored and reported on to ensure that action is taken on any significant overspends identified on agreed budgets.
3.0Scope and Objectives
3.1The objective of the audit was to evaluate the system of internal control with a view to delivering reasonable assurance to the Authority over the adequacy of the internal control environment. This is defined as the whole system of controls, established by management, which help to ensure the achievement of objectives, economy and efficiency, compliance with policies and procedures, safeguarding of assets and the integrity and reliability of information.
Merthyr Tydfil County Borough Council 13/05/2011 Internal Audit Service 1 of 4 Budgetary Control 2010-11 3.2 The system has been evaluated against the following control objectives:
• Budgets should be controlled in accordance with financial procedure rules. • There should be documentary evidence to support the approval of the budget. • All relevant records should be updated with the amount of the budget set. • FIS should provide an effective management tool, to enable senior management and the managing body to be kept fully informed of whether the organisation will meet its required spending levels. • The budgets should be calculated and valued correctly. • FIS should provide information to management which is up to date and should be in a format which can be understood easily. • The budgets should be initiated and recorded promptly. • Variations in the budget should be reported and acted upon.
4.0Methodology
4.1The audit was undertaken using a risk-based auditing methodology. Actual controls were evaluated against the expected controls within each control objective. A risk assessment of the individual controls under each control objective was undertaken and the level of testing decided upon. The system evaluation and the results of compliance testing were then used as the basis on which to draw conclusions and to form an opinion on the overall effectiveness and adequacy of the internal control environment.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Budgetary Control System Internal Audit Report 2010/11.Report | 13 pages | DownloadRead as text |
Follow Governance and Audit Committee at Merthyr Tydfil and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 Sep 2026 | Peer Panel Performance Assessment - Response and Action PlanResolved that the report and draft action plan be noted and recommended to Council for approval. | Noted | Open |
| 28 Sep 2026 | Terms of ReferenceResolved that the Governance and Audit Committee be approved and reviewed annually. | Approved | Open |
| 28 Sep 2026 | Governance and Audit Committee Annual Report 2025/26Resolved that the Annual Report be noted, amended as appropriate in relation to the attendance record, and recommende... | Noted | Open |
| 22 Jun 2026 | Appointment of Chair and Vice ChairResolved; That Martin Veale continue as Chair and Colin Prosser continue as Vice-Chair of the Governance and Audit Co... | Decided | Open |
| 1 Sep 2025 | Time of Future MeetingsIt was agreed that future meetings would be moved to 5pm and if there was an issue with officer availability for any ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.