Quarter 2 - Performance, Risk and Finance Report 2025/26
ApprovedExecutive7 papers
AI summaryMerthyr Tydfil County Borough Council Cabinet approved risk and performance progress, budget virements and budget amendments for projects funded from core funding. It noted revenue and capital monitoring, a £556,000 projected net revenue deficit, and asked managers to address service area deficits. [D] [P21]
Written from the decision and the officer reportPDF Pro
OutcomeApprovedRisk, performance, revenue, virements and capital items [D]
Money£556,000Projected net revenue deficit for 2025/26 [P21]
What happens nextManagers address service deficits [D]Asked to identify all possible offset measures [D]
Who it affectsResidents and council services [P9]Delivery plans aim to improve services and resident outcomes [P9]
What was decided
Cabinet approved progress in managing the Council's Corporate Risks and the Corporate Risk Register at the end of quarter 2.
Cabinet approved progress against the Annual Delivery Plan for quarter 2 and key performance indicators for the Corporate Wellbeing Plan for quarters 1 and 2.
Cabinet noted the Revenue Budget Monitoring report based on quarter 2 projections and the Quarter 2 Capital Monitoring Report for 2025/26. It approved budget virements in Appendix 5 and budget amendments for projects funded from core funding in Appendix 6, and noted budget variances in Appendix 6.
Why
The Annual Delivery Plan sets the Council's intentions for the year ahead and is based on service evaluation and service planning. Quarterly monitoring is intended to support challenge, reporting and improvement. Performance data will also feed the Corporate Self-Assessment Report for 2025/26. Report P3, P4, P12
The Corporate Risk Register had 12 corporate risks at the end of quarter 2 and had been reviewed by the Corporate Management Team on 5th November 2025. Internal Audit was due to examine corporate risk management arrangements during 2025/26, with most work envisaged for quarter 3. Report P18
A £556,000 net revenue deficit was projected for 2025/26. Service budget shortfalls were £360,000 in Social Services, £73,000 in Education, £23,000 in Neighbourhood Services and £152,000 in Finance, partly offset by projected budgeted surpluses of £182,000 in Regeneration, Investment and Housing and £35,000 within Governance and Resources. There was also a further £645,000 projected overspend within Corporate Cost and a £480,000 saving in Contributions and Recharges. Report P21
What happens next
Managers were asked to address projected budget deficits within their service areas by identifying all possible measures to offset them.
Continue quarterly monitoring, challenge and reporting, and consider how performance can improve. Report P12
Continue monitoring corporate risk, scan for emerging risks, place greater emphasis on mitigation plans and integrate corporate risk with performance. Report P19
The money
£556,000 Projected net revenue deficit for 2025/26 Report P21
£645,000 Further projected overspend within Corporate Cost Report P21
£360,000 Projected deficit in Social Services Report P21
£182,000 Projected budgeted surplus in Regeneration, Investment and Housing Report P21
£152,000 Projected deficit in Finance Report P21
£480,000 Projected saving in Contributions and Recharges Report P21
£73,000 Projected deficit in Education Report P21
£23,000 Projected deficit in Neighbourhood Services Report P21
Implications
Financial: The forecast shows a £556,000 net revenue deficit, and managers were asked to identify measures to offset projected service area deficits. Report P21
Financial: Budget virements and budget amendments for projects funded from core funding were approved, while budget variances were noted.
Financial: Budget monitoring arrangements are to be continually reviewed and enhanced to maintain effective challenge and scrutiny. Report P22
Risk: The Corporate Risk Register contained 12 corporate risks, with one proposed change to increase a risk score at quarter 2. Report P18
Risk: The Council will continue monitoring corporate risk, scan for emerging risks, place greater emphasis on mitigation plans and integrate risk with performance. Report P19
Other: Quarterly reporting brings performance, corporate risk and finance together in connected reports for Cabinet. Report P3, P6
Other: Complaints fell from 227 in quarter 1 to 195 in quarter 2. The data can be used to inform service level improvements. Report P15
Staffing: Workforce data was taken in quarter 2 of 2025/26 to show how employees' skills and experience support service delivery. Report P24
Who and where
Residents Report P9, P15
Council employees Report P24
Managers in service areas
Service areas with projected deficits: Social Services, Education, Neighbourhood Services and Finance Report P21
Service areas with projected surpluses: Regeneration, Investment and Housing and Governance and Resources Report P21
Corporate Cost Report P21
Timeline
June 2025: The Annual Delivery Plan was approved. Report P3
September 2025: More detail for the Annual Delivery Plan was approved. Report P3
30 th September 2025: The projected revenue outturn for 2025/26 was reported as at this date. Report P21
4th November 2025: The report was written.
5th November 2025: The Corporate Management Team reviewed the Corporate Risk Register. Report P18
3rd December 2025: Cabinet considered and decided the report.
quarter 3: Most Internal Audit work on corporate risk management arrangements was envisaged to take place. Report P18
Plain English for the jargon
Annual Delivery Plan (ADP): Sets the Council's intentions for the year ahead, based on service evaluation and service planning. [P3]
Corporate Risk Register (CRR): Holds the Council's corporate risks at the end of quarter 2. [P17] [P18]
Corporate Wellbeing Plan: Sets wellbeing objectives and the key performance indicators used for quarterly monitoring. [P4] [P8]
Key performance indicators (KPIs): Measures set against the Corporate Wellbeing Plan. [P4]
Service evaluation (SSE): Service evaluation used with service planning to develop the Annual Delivery Plan. [P3]
Performance Management Framework: Uses Plan, Do, Monitor and Improve to support consistent performance management. [P3]
Budget monitoring: Regular review of the projected revenue outturn and major budget variances. [P6] [P22]
Revenue outturn: The projected final revenue position for the financial year. [P6] [P21]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item50
Resolved
Resolved that: 2.1 Progress on the management of the Council’s Corporate Risks and the Corporate Risk Register (as at the end of quarter 2), be approved. 2.2 Progress against the Council’s Annual Delivery Plan (quarter 2) and key performance indicators of the Council’s Corporate Wellbeing Plan (quarters 1 & 2), be approved. 2.3 The Revenue Budget Monitoring report for the 2025/26 financial year based on Quarter 2 projections be noted. Date Written 4th November 2025 *** Report Author A Mogford, J Hopwood & L Ballinger Service Area Policy and Performance Committee Division Strategic Exempt/Non Exempt Non-Exempt Committee Date 3rd December 2025 Page 149 Agenda Item 5 2.4 Budget Virements outlined in Appendix 5, be approved. 2.5 Managers are being asked to address projected budget deficits within their respective service areas (by identifying all possible measures to offset the deficits), be noted. 2.6 The Quarter 2 Capital Monitoring Report for 2025/26 (appendix 6), be noted. 2.7 The budget amendments for core-funded projects (appendix 6), be approved. 2.8 Variances to the budgets (appendix 6), be noted.
Word for word from the decision Merthyr Tydfil published for this meeting.Source: democracy.merthyr.gov.uk
Merthyr Tydfil County Borough Council Performance, Risk & Finance Report - Quarter 2 2025-2026
Improving our Services for a Better Tomorrow Contents What is the Performance, Risk and Finance (PRF) Quarterly Report? ............................................................................................................................................... 2 Part 1: Performance ...................................................................................................................................................................................................................... 3 Part 2: Corporate Risk ................................................................................................................................................................................................................... 5 Part 3: Finance ............................................................................................................................................................................................................................. 6 What is our workforce position? ................................................................................................................................................................................................... 7
1|P a g e What is the Performance, Risk and Finance (PRF) Quarterly Report? The Council is continuing to strengthen its governance and is reintroducing quarterly reporting. In this second iteration, we will consider Performance, Corporate Risk and Finance. Our joined-up approach will enable us to provide regular integrated reports to Cabinet providing a more connected position with data being provided to our decision makers. Throughout our reporting we are using the principles set out in our recently approved Performance Management Framework. As part of that work, we developed a new service self-evaluation and service planning framework using lessons learned from previous work and learning from and working with neighbouring Councils. This includes the ‘Plan → Do → Monitor → Improve’ process. This has allowed us to develop a consistent approach to performance management across the Council and in turn enabled us to work towards our first Annual Delivery Plan (ADP) which was approved in June 2025 with more detail approved in September 2025. The ADP sets out our intentions for the year ahead and is based on the findings from our service self-evaluation (SSE) and service planning.
The Performance section of this report will monitor the delivery of the ADP and the measures we have put in place for it. It also considers the key performance indicators (KPIs) set against our Corporate Wellbeing Plan. This report provides data which will also feed into our Corporate Self-Assessment Report for 2025/26.
In the Corporate Risk section, we will consider the Corporate Risk Register (CRR) as at the end of quarter 2 (2025/26). It also builds on actions implemented to address recommendations of an internal audit, as reported to the Governance and Audit Committee (GAC) previously.
In the Finance section, details of the projected revenue outturn for 2025/26 as at the end of the quarter 2 and capital monitoring for quarters 1 and 2 for 2025/26. This is to be considered at Corporate Leadership Team. The report advises Cabinet (and other decision makers) of the projected outturn position for the 2025/26 financial year with a focus on projected major budget variances.
2|P a g e Part 1: Performance What is included in this report?
In this section we will consider four aspects of our performance, namely progress against of Annual Delivery Plan (ADP), performance data for the measures set for our Corporate Wellbeing Plan and Wellbeing Objectives, complaints data at quarter 2 and elements of staffing data.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.