Asset Management Update

Decided Executive 6 papers

AI summaryMerthyr Tydfil County Borough Council Cabinet received the asset management update for information [D]; the report listed a £43,090,628 maintenance backlog for 25/26, not yet complete [3.4].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedRefreshed AMP, action plan, KPIs and policies attached [1.2] [1.3] [1.4] [1.5] [1.6]
Money£43,090,628 backlog for 25/26 [3.4]Historical figure, not yet complete [3.4]
What happens nextDevelop Corporate Property business case [6.0]Address capacity, budgets and maintenance backlog [6.0]
Who it affectsCouncil buildings and maintenance [4.5]Health and safety, service and cost risks [4.5]

What was decided

Merthyr Tydfil County Borough Council Cabinet received the Asset Management Update for information.

Why

Good asset management supports the Corporate Wellbeing Plan and the Council’s corporate objectives, and supports better long term use of property assets. Report P4

Backlog maintenance requires corporate prioritisation and adequate resourcing of the Maintenance and Compliance Team to reverse the decline in building condition. Report 3.3

A single Corporate Property team is needed to support effective asset management and long term financial resilience. Report 4.5, 5.2, 5.3

What happens next

Develop a business case to reinstate Corporate Property, address maintenance capacity and budget issues, and reduce the backlog. Report 6.0

Continue addressing Property Services capacity and bring Property Services and Estates together as Corporate Property. Report 4.5

Update the website links when the refreshed AMP replaces the original version.

The money

  • £43,090,628 25/26 historical backlog, not yet complete Report 3.4
  • £42,773,159 24/25 historical backlog Report 3.4
  • £35,958,523 23/24 historical backlog Report 3.4
  • £9,090,658 12/13 historical backlog Report 3.4
  • £490k Projected savings from new solar PV systems at 3 schools Report P21
  • £254k Leaks identified by water data loggers at 24 sites Report P20
  • £147k Investment in the completed Salix Energy Scheme Report P20
  • £30k Annual savings from the Salix Energy Scheme Report P20

Options considered

  • Chosen: Receive the Asset Management Update for information

Implications

  • Risk: Extensive backlog and insufficient capacity create health and safety risks, operational risks and increased long term costs. Report 4.5
  • Staffing: The Maintenance and Compliance Team needs adequate resourcing to support building managers, planned maintenance programmes and condition survey work. Report 3.3
  • Financial: Reinstating Corporate Property and increasing maintenance capacity are likely to have financial implications, which the business case will specify. Report 7.0
  • Financial: Disposals can raise capital receipts and reduce ongoing maintenance liabilities, with residential land disposals supporting good quality affordable housing objectives. Report 4.6
  • Climate: Renewable energy generation has improved, but carbon dioxide emissions from local authority buildings have risen after the return of the former Leisure Trust properties. Report 4.3
  • Legal: Statutory compliance continues to improve, and a new asset management system includes a module for managing asbestos. Report 4.3, 4.4
  • Risk: 40 buildings are linked to the Building Management System, but there is no current funding for expansion. Report P20
  • Risk: Whole life costing is considered in major projects but is not consistently documented because of capacity issues. Report P21

Who and where

  • Council property portfolio Report P4
  • Property Services and Estates teams Report 4.5, 5.3
  • Maintenance and Compliance Team Report 3.3
  • Building managers Report 3.3
  • All council service areas
  • Technical departments
  • Community organisations with Community Asset Transfer leases Report 4.7

Timeline

  • June 2023: The Council adopted the Corporate Asset Management Plan Report P4
  • 2024: An annual update was presented to Scrutiny Committee and Cabinet Report P4
  • June 2024: The Salix Energy Scheme was completed Report P20
  • September 2025: The Action Plan summary was prepared Report 4.2
  • Oct 2025: Completion was expected for energy schemes funded by Salix across 6 sites Report P21
  • 21st October 2025: The update went to Scrutiny Committee, with backlog cost details also sent separately to members Report 1.8
  • 3rd December 2025: The Asset Management Update was scheduled for Cabinet Report P3
  • Q1 2026: The Tregenna Hotel redevelopment was due to deliver 19 units Report P21

Plain English for the jargon

  • AMP: Strategic framework for managing the Council’s property portfolio [P4]
  • Backlog maintenance: Accumulated maintenance work and costs requiring prioritisation [3.3] [3.4]
  • Corporate Property: A single team formed by bringing Property Services and Estates together [4.5] [5.3]
  • KPI: Updated measure used to track asset management performance [1.4] [4.3]
  • Whole life costing: Considered for major projects but not consistently documented because of capacity issues [P21]
  • Statutory compliance: Compliance reported as continuing to improve across the estate [4.3]
  • Building Management System: Central system for linking and managing Council buildings [P20]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item53

Resolved

RESOLVED that: The report for information be received.
Word for word from the decision Merthyr Tydfil published for this meeting. Source: democracy.merthyr.gov.uk

Follow this further

Built from Merthyr Tydfil's papers

What the report saysPro

Report to Cabinet, 5 pages

Civic Centre, Castle Street, Merthyr Tydfil CF47 8AN Main Tel: 01685 725000 www.merthyr.gov.uk

CABINET - INFORMATION REPORT

Date Written 30th October 2025 Report Author Lisa Emerson Service Area Corporate Property Exempt/Non Exempt Non Exempt Committee Date 3rd December 2025

Asset Management Update

1.0SUMMARY OF THE REPORT 1.1 Good asset management is a critical component in delivering the Corporate Wellbeing Plan and supports the Council’s corporate objectives. Reviewing and planning how we make better use of our property assets efficiently and effectively for the long term is essential. The Corporate Asset Management Plan (AMP), adopted in June 2023, provides a strategic framework for supporting good asset management principles across the Council’s property portfolio.

1.2A refreshed version of the AMP is attached at Appendix 1

1.3An updated Action Plan is attached at Appendix 2

1.4Updated Key Performance Indicators are attached at Appendix 3.

1.5The Disposal Strategy is attached at Appendix 4.

1.6The updated Community Organisation Rental Policy is attached at Appendix 5.

1.7Key issues raised are in relation to the continued insufficient capacity to manage property maintenance effectively, together with the allocation of insufficient maintenance budgets to deal with backlog maintenance.

1.8This Asset Management Update Report was also provided to Scrutiny Committee on 21st October 2025. Following a request made at that meeting, details of the increase in backlog maintenance costs over time have also been included in this report and provided separately to Scrutiny Committee Members. 2.0 INTRODUCTION AND BACKGROUND 2.1 Good asset management is a critical component in delivering the Corporate Wellbeing Plan and supports the Council’s corporate objectives. Reviewing and planning how we make better use of our property assets efficiently and effectively for the long term is essential. The Corporate Asset Management Plan (AMP), adopted in June 2023, provides a strategic framework for supporting good asset management principles across the Council’s property portfolio.

2.2The AMP includes an Action Plan and Key Performance Indicators which support the delivery of good asset management and continued improvement.

3.0WHERE WE WERE 3.1 In June 2023 Council adopted the Corporate Asset Management Plan (AMP) and an annual update report was presented to Scrutiny Committee and Cabinet in 2024. This report highlighted the lack of maintenance budgets and a lack of capacity within the Property Services team, resulting in the inability to consider centralising maintenance budgets and a significant increase in the floor area of property within condition rating C and D.

3.2Progress had been made in addressing full statutory compliance overall, but investment was required on an asbestos management software system.

3.3Investment in addressing the backlog maintenance needed prioritisation corporately to reverse the decline in building condition. To achieve this, the Maintenance/Compliance Team needed to be adequately resourced to support building managers with planned maintenance programmes and completion of maintenance work highlighted in condition surveys.

3.4Historical Backlog Maintenance: 12/13 - £9,090,658 23/24 - £35,958,523 24/25 - £42,773,159 25/26 - £43,090,628 (not yet complete)

4.0WHERE WE ARE NOW 4.1 An updated version of the AMP is attached at Appendix 1 and will replace the original version following this Cabinet Report. The links on the Council’s website will also be updated as appropriate.

4.2The updated Action Plan is attached at Appendix 2, showing progress against each action where actions are ongoing. Completed actions previously reported have been removed. A summary of completed and ongoing actions are as follows: 4.2.1 Action Plan Summary - September 2025

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Asset Management UpdateReport 5 pages DownloadRead as text
PDF
Enc. 2 for CF: Asset Management UpdateReport 36 pages Download
PDF
Enc. 3 for CF: Asset Management UpdateReport 8 pages Download
PDF
Enc. 4 for CF: Asset Management UpdateReport 1 pages Download
PDF
Enc. 5 for CF: Asset Management UpdateReport 5 pages Download
PDF
Enc. 6 for CF: Asset Management UpdateReport 2 pages Download

At this meeting

Whole meeting

Who was there

5 of 13 attended
BC
Councillor Brent CarterChair, present
DJ
Councillor David JonesVice-Chair, present
GL
Councillor Gareth LewisCommittee Member, apologies
LM
Councillor Louise Minett-VokesCommittee Member, apologies
DS
Councillor Declan SammonCommittee Member, present
JS
Councillor Jamie ScrivenCommittee Member, present
AW
Councillor Anna Williams- PriceCommittee Member, present
GM
Geraint MorganOfficer, in attendance
RB
Rebecka BowOfficer, in attendance
AM
Andrew MogfordOfficer, in attendance
BL
Beki Lee-Burrowes Corporate CommunicationsOfficer, in attendance
KR
Katy Roberts Corporate CommunicationsOfficer, in attendance

All 13 on the meeting page

On this subject at Merthyr Tydfil

Search all
  1. Asset Management UpdateThis decision
  2. Options for the Future Management of Leisure Services and Assets in Merthyr TydfilApproved
  3. Corporate Asset Management Plan 2023-2038Approved
  4. Asset Management PlanNoted
  5. Corporate Asset Management Plan 2014-2019 – UpdateDecided
  6. Corporate Asset Management PlanDecided

More from Merthyr Tydfil Cabinet

All decisions
MeetingDecisionOutcome
22 Oct 2026 The Tobacco and Vapes Act 2026 - Scheme of DelegationResolved that: 2.1 Approve the inclusion of the Tobacco and Vapes Act 2026 within the Council's Scheme of Delegation.... Approved Open
22 Oct 2026 Annual Equality Report 2025-2026Resolved that: 2.1 The Council’s Annual Equality Report for 2025-2026 be approved for publishing. Approved Open
22 Oct 2026 Bright Futures Education Strategy 2026 - 2030Resolved that: 2.1 The Bright Futures Education Strategy 2026-2030 (Appendix 1) be discussed and noted prior to Full ... Noted Open
22 Oct 2026 Greenfield Special School - Satellite ProvisionResolved that: 2.1 The use of the vacated former St Mary’s Primary School site as an interim solution for Greenfield ... Approved Open
22 Oct 2026 Provisional Capital Outturn Report 2025/26Resolved that: 2.1 The provisional Capital Outturn position for the 2025/26 financial year be noted. 2.2 The budget a... Noted Open