Resolved
That the contents of the report be noted.
South London Waste Partnership Joint Committee noted this item on Tuesday 9 June 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
That the contents of the report be noted.
Joint Waste Committee is asked to note the contents of this report, and comment on any aspects of the performance of the Partnership’s Phase A contracts.
Background Documents:
Contract Performance Monitoring updates have been presented to the Joint Waste Committee since 22 July 2010. The most recent reports were presented at the meeting on 31st March 2015 by the Contract Manager.
Page 5 1. BACKGROUND
1.1Contract 1 is operated by Viridor Waste Management Ltd and includes the haulage of all materials requiring transfer and the management of residual waste.
1.2The Partnership’s HRRC site service is currently managed by the Royal Borough of Kingston, pending re-procurement of the service.
1.3Contract 3 is operated by Viridor and includes the marketing of recyclates and the treatment of green and food waste.
2. PERFORMANCE DETAIL
2.1Contract 1: Transport and Residual waste management (Viridor Waste Management Limited)
2.1.1. Under Contract 1, during the reporting period 1st April 2014 and the 31st March 2015, the Partnership managed 233,526 tonnes of residual waste. Please see Appendix A section 1 for further detail.
2.1.2. The Royal Borough of Kingston deliver residual waste to the Authority owned waste transfer station (WTS), also referred to as Villiers WTS. The Villiers WTS is operated by Viridor, who are responsible for the onward transfer of residual waste for disposal. The London Boroughs of Merton, Croydon and Sutton direct deliver residual waste to the Viridor Beddington Lane site.
2.1.3. Viridor continue to divert a proportion of the Contract 1 residual waste to their Lakeside energy recovery facility (ERF) when capacity is available. Partnership waste sent to the Lakeside ERF is thermally treated at the same price as the residual waste landfill Gate fee. Viridor have direction on which Borough waste is diverted from l;andfill, largely determined by the location and capacity at the facility receiving the waste.
2.1.4. During this reporting period 47,074 tonnes of SLWP residual waste was diverted from landfill via the Lakeside ERF. This equates to approximately 20% of our residual waste. Please see Appendix A section 3 for further tonnage data.
2.1.5. Residual waste diversion from landfill has increased with each period reported; quarter one saw an 8% diversion, quarter two 15% diversion, quarter three 17% and at end of year quarter four we can report a 20% diversion rate. Viridor has confirmed that capacity will be available in Lakeside for the financial year 2015/16.
Page 6 2.1.6. The Contract is operating effectively. There were no major operational or performance issues and no formal complaints reported under Contract 1.
2.2Contract 2: Management of the Household Reuse and Recycling Centres (Royal Borough of Kingston)
2.2.1. Contract management - The Royal Borough of Kingston continues to manage the HRRC services across the four boroughs on behalf of the Partnership.
2.2.2. Recycling performance – The HRRC service is achieving good recycling rates across all sites. Individually the end of year average recycling rate at each site is broadly comparable to the 12 month average for the previous year. See Appendix 5 for more details.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
01_Phase A Contract management Report Appendix A June 2015V2Appendix | 336 KB | Download |
PDF |
Phase A Contract Management ReportReport | 55 KB | DownloadRead as text |
Follow South London Waste Partnership Joint Committee at Merton and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Jun 2023 | Minutes of the Previous MeetingThat minutes of the meeting held on 25 April 2023 were agreed and signed as an accurate record. | Agreed | Open |
| 15 Jun 2023 | Contract Performance ReportThat the Joint Committee; · noted the contents of the report, and · commented on any aspects of the performance of th... | Noted | Open |
| 15 Jun 2023 | Partnership Budget Update 22/23 - Final Out-turnThat the report was noted. | Noted | Open |
| 25 Apr 2023 | Minutes of the Previous MeetingThat the minutes of the meeting held on 12 January were agreed as an accurate record. Item 8 on the agenda would be b... | Agreed | Open |
| 25 Apr 2023 | Partnership Budget Update - Month 11That the Committee noted the contents of the report. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.