Budget Monitoring 2016/17 and Revenue Estimates 2017/18
NotedCommittee1 paper
Merton and Sutton Joint Cemetery Board noted this item on Wednesday 22 February 2017. Below is the council's own wording, with the papers it was decided on.
RESOLVED The Board 1. That the current budgetary position for 2016/17 based on the third quarters monitoring be noted. 2. The Revenue Estimates for 2017/18 as submitted be approved. 3. That the precepts for the financial year ended 31 March 2018 be set at zero. 4. That the Board establishes it’s next meeting for Monday 12 June 2017 at 2.30pm to ensure that information is despatched to Merton’s External Auditors by 30 th June 2017. 5. That the Board review and approve the Risk Management Strategy and Risk Register (as at February 2017)attached as Appendix G The Chair thanked Officers for their work on this report Board members asked to record a vote of thanks to Councillor Nick Emmerson for his Chairing in the last year. Patrick Phillips and Tony Race from idverde attended the meeting and introduced the work of idverde to the. Board. Members noted the work already being done by idverde and requested that they be provided with regular updates from idverde on their work at the Cemetery.
Word for word from the decision Merton published for this meeting.Source: democracy.merton.gov.uk
1. That the current budgetary position for 2016/17 based on the third quarters monitoring be noted. 2. The Revenue Estimates for 2017/18 as submitted be approved. 3. That the precepts for the financial year ended 31 March 2018 be set at zero. 4. That the Board establishes it’s next meeting in June 2017 to ensure that information is despatched to Merton’s External Auditors by 30 th June 2017. 5. That the Board review and approve the Risk Management Strategy and Risk Register (as at February 2017)attached as Appendix G
1. Purpose of the Report and Executive Summary
1.1This report presents the projected outturn for 2016/17 based on the budgetary monitoring to 31 January 2017 and revenue estimates for 2017-2018.
2. Details
2.1Estimates
2.1.1 The Board’s 2016/17 Budgetary Monitoring are attached at Appendix A. The draft Revenue Estimates for 2017/18 are attached as Appendix B. All estimates are at outturn prices. Supplementary details of direct employee expenses are contained in Appendix C, with Appendix D providing a breakdown of Management and Administration Expenses. Appendix F contains the precept history of the Merton and Sutton Joint Cemetery Board.
2.1.2 Estimates have been compiled utilising the best information available at the time of despatch, the costs and income will continue be monitored. A monitoring update will be provided at the June meeting of the board.
Page 3 2.2 Income
2.2.1 From 1 February 2017 cemeteries fees and charges will be collected by the contractor and a guaranteed level of income paid to the Authority based on 2014/15 Outturn plus inflation. Income above this threshold will be shared between the Council and the Contractor. Appendix H.
2.2.2 Details of rental income and interest calculations are also included in Appendix H
2.4Salaries
2.4.1 Salaries to the Board’s part time Chief Officers, i.e. Clerk, Treasurer, Registrar and Consultant Surveyor are increased annually in line with negotiated and announced Joint Negotiating Committee (JNC) awards in accordance with the Board policy, approved on 8th March 1972 (Min. 48/3/72).
2.4.2 The Board meeting of 24th April 1989 resolved that subject to there being no legal impediment, future salary awards for the Board’s part time officers be implemented from 1 April each year so as to coincide with the Board’s financial year. Allowance of 1% pay award has been built into salary estimates for 2017/18.
2.4.3 Every three years Authorities are required to evaluate the sufficiency of their pension funds to meet future commitments and review appropriate contribution rates. This is called an Actuarial Evaluation. The pension contribution is based on the draft report received from Surrey Count Councils Actuary.
2.5Interest / Minimum Revenue Provision
2.5.1 Machinery: Based on analysis undertaken in previous years regarding the replacement programme for machinery and equipment an annual minimum revenue provision of £23,220 has been entered into the revenue estimates over the projection period.
2.5.2 Loan: Appendix E sets out the interest and principle repayments incurred from the £1.763 million loan for various works. It is assumed that the loan will be over 25 years (the anticipated life of the extension) at a rate of 3.47%(rate as at June 2013). These figures have been fed into the estimates in Appendices A and B.
Page 4 2.6 Special Projects
2.6.1 The special projects budget for 2016/17 has been broken down into the schemes progressed. A total of £50,000 has been set aside for special projects in 2017/18 – these will be determined and progressed as part of the client side function.
3. Common Fund Balances
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Appointment of Chair and Vice ChairIt was RESOLVED that Cllr Joan Henry was appointed Chair of the Merton Sutton Joint Cemetery Board, and Cllr Rob Beck...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.