Budget Monitoring 2019/20 and Revenue Estimates 2020/21
NotedCommittee1 paper
Merton and Sutton Joint Cemetery Board noted this item on Tuesday 11 February 2020. Below is the council's own wording, with the papers it was decided on.
RESOLVED 1. That the current budgetary position for 2019/20 based on the end of December 2019 shown in Columns 1 to 3 of Appendix A be noted. 2. The Revenue Estimates for 2020/21 shown in Column 4 of Appendix A be approved. 3. That the precepts for the financial year ended 31 March 2021 be set at zero. 4. That the Board establishes its next meeting as early as possible in June 2020 to ensure that approved information is included in Merton’s Accounts and information is despatched to Merton’s External Auditors as soon as possible. 5. That the Board review and approve the Risk Management Strategy and Risk Register (as at January 2020) attached as Appendix H
Word for word from the decision Merton published for this meeting.Source: democracy.merton.gov.uk
1. That the current budgetary position for 2019/20 based on the end of December 2019 shown in Columns 1 to 3 of Appendix A be noted. 2. The Revenue Estimates for 2020/21 shown in Column 4 of Appendix A be approved. 3. That the precepts for the financial year ended 31 March 2021 be set at zero. 4. That the Board establishes its next meeting as early as possible in June 2020 to ensure that approved information is included in Merton’s Accounts and information is despatched to Merton’s External Auditors as soon as possible. 5. That the Board review and approve the Risk Management Strategy and Risk Register (as at January 2020) attached as Appendix H
1. Purpose of the Report and Executive Summary
1.1This report presents the projected outturn for 2018/19 based on the budgetary monitoring to 31 December 2019 and revenue estimates for 2020-2021.
2. Details
2.1Estimates
2.1.1 The Board’s 2019/20 Budgetary Monitoring is attached at Appendix A (columns 1 to 3). The draft Revenue Estimates for 2020/21 are attached as Appendix A (column 4). All estimates are at outturn prices. Supplementary details are contained within appendices: • Salaries, pension contributions – Appendix B • Management and administration expenses – Appendix C • Loan repayment – Appendix D • Rental income – Appendix E • Depreciation – Appendix G
2.1.2 Appendix F contains the precept history of the Merton and Sutton Joint Cemetery Board.
Page 5 2.1.2 Estimates have been compiled utilising the best information available at the time of despatch, the costs and income will continue be monitored. A monitoring update will be provided at the June meeting of the board.
2.2Income
2.2.1 Prudent assumptions on the level of income generated from contractual arrangements have been made (this the is original agreed income sum without inflation). The Client Side officer will be presenting information in relation to contractual activity.
2.2.2 Appendix E details the expected rental income in 2019/20 and 2020/21
2.4Salaries
2.4.1 Salaries to the Board’s part time Chief Officers, i.e. Clerk, Treasurer, Registrar and Consultant Surveyor are increased annually in line with negotiated and announced Joint Negotiating Committee (JNC) awards in accordance with the Board policy, approved on 8th March 1972 (Min. 48/3/72).
2.4.2 The Board meeting of 24th April 1989 resolved that subject to there being no legal impediment, future salary awards for the Board’s part time officers be implemented from 1 April each year so as to coincide with the Board’s financial year. Allowance of 2% pay award has been built into salary estimates for 2020/21.
2.4.3 Every three years Authorities are required to evaluate the sufficiency of their pension funds to meet future commitments and review appropriate contribution rates. This is called an Actuarial Valuation. Officers have just received the initial report which has shown a beneficial movement in the board’s position and recommends that contribution rates are increased to 28% of the pension payroll for the next three financial years. Officers estimate that this equates to an annual contribution of £50,000 for 2020/21, 2021/22 and 2022/23. This figure will be revised when information is finalised.
2.5Loan Repayments
2.5.1 Appendix D sets out the interest and principle repayments incurred from the £1.763 million loan for various works. It is assumed that the loan will be over 25 years (the anticipated life of the extension) at a rate of 3.47% (rate as at June 2013). The Appendix highlights that the board will be in year 8 of the repayment schedule in 2019/20.The repayment commitment within this schedule has been fed into the estimates in Appendix A.
Page 6 2.6 Special Projects
2.6.1 The special projects budget for 2020/21 is proposed as follows:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Appointment of Chair and Vice ChairIt was RESOLVED that Cllr Joan Henry was appointed Chair of the Merton Sutton Joint Cemetery Board, and Cllr Rob Beck...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.