Resolved
That the committee noted the report.
South London Waste Partnership Joint Committee noted this item on Wednesday 28 September 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
That the committee noted the report.
This paper provides an update on the Partnership’s budget position for month 4 (July) of the 2022/23 financial year and the projected outturn for the financial year.
1. Background 1.1 The SLWP partnership team is required to produce a budget for consideration by the Joint Waste Committee each year that covers the cost of delivering partnership wide activities and running the partnership team.
1.2At the Joint Committee in February 2022, the Joint Committee was asked to agree the Core Partnership budget of £792,000 and to endorse a further £370,000 in commissioning related activities and £167,000 to support improvement activities. Further details around the work included under each of these categories can be found in the February 2022 Joint Committee report.
1.3The budget is monitored monthly to allow the budgets to be flexed where appropriate in order to respond to any budget pressures.
2. Financial Position 2022/23
2.1Core Partnership budget - The table below details the total annual budget for the Core Partnership Team activities, and our anticipated outturn for the year including actuals up to and including month 4 (July) of the 2022/23 financial year. This budget covers core staff salaries, ad hoc advisor support on contract issues and / or variations and document management functions. The core staff activities include contract management and finance administration.
Anticipated Budget Variance Outturn Core Partnership Team Activity £792,000 £795,773 £3,773 Advisors and Corporate Support £64,400 £65,309 £909 Core Staff Resources £708,000 £710,554 £2,554 Document Management £19,600 £19,910 £310
2.2The Core Partnership Team Activity budget is forecasting an overspend of £3,773. £2,554 of which is due to an overspend in the Core Staff Resources attributed to
Page 19 1 interim staff costs covering vacant posts. The SLWP staffing restructure is now complete, all vacant posts recruited to, and all new starters are now in post.
2.3A further overspend of £909 relates to internal legal advisor support and £310 relating to an increase in document Management costs.
2.4Improvement Projects - The table below refers to the budget position for the Improvement Projects budget for month 4 (July) of the 2022/23 financial year.
Anticipated Budget Variance Outturn Improvement Projects £167,000 £150,094 -£16,906 Contract Management Improvements £20,000 £3,746 -£16,254 Communication and Improvement Projects £147,000 £146,348 -£653
2.5Notable contract management improvement projects are still under review, resulting in a current underspend of £16,906. Communications projects are progressing well and are forecasted to be delivered within budget.
2.6Strategy and Commissioning - The table below provides a projected outturn for the year including actuals up to and including month 4 (July) in relation to the Strategy Development and Service Commissioning budget.
Anticipated Budget Variance Outturn Strategy Development and Service Commissioning £370,000 £377,901 £7,901 Intelligence Gathering £170,000 £237,602 £67,602 Commissioning Resource £200,000 £140,299 -£59,701
At month 4, there is a forecasted overspend of £7,901. The budget exceedance for Intelligence Gathering Projects is due to intelligence gathering tenders coming back with higher than budgeted prices. The forecast overspend from Intelligence gathering activities has been managed through a reduction in the commissioning and technical support.
2.7Summary - The table below shows the combined position across the budget areas described above.
Anticipated Budget Variance Outturn TOTAL £1,329,000 £1,323,768 -£5,232 COST PER BOROUGH £332,250 £330,942 -£1,308
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Budget UpdateReport | 234 KB | DownloadRead as text |
Follow South London Waste Partnership Joint Committee at Merton and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Jun 2023 | Minutes of the Previous MeetingThat minutes of the meeting held on 25 April 2023 were agreed and signed as an accurate record. | Agreed | Open |
| 15 Jun 2023 | Contract Performance ReportThat the Joint Committee; · noted the contents of the report, and · commented on any aspects of the performance of th... | Noted | Open |
| 15 Jun 2023 | Partnership Budget Update 22/23 - Final Out-turnThat the report was noted. | Noted | Open |
| 25 Apr 2023 | Minutes of the Previous MeetingThat the minutes of the meeting held on 12 January were agreed as an accurate record. Item 8 on the agenda would be b... | Agreed | Open |
| 25 Apr 2023 | Partnership Budget Update - Month 11That the Committee noted the contents of the report. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.