CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Merton
Cabinet, Monday 13 July 2026 at 7.15pm

Budget 2027/28 and MTFS 2027-2031

Decided Executive 1 paper

AI summaryMerton Cabinet notes a revised Medium Term Financial Strategy for 2027 to 2031, with a forecast cumulative budget gap of 33,808 in 2030/31 (in £'000). The update increases pay inflation assumptions and reflects the end of a schools PFI contract.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedNotes rolling forward of the 2027 to 2031 strategy
MoneyForecast gap 33,808 (in £'000) by 2030/31Updated gap, in thousands, for 2030/31
What happens nextFurther reports to autumn 2026Options for a balanced 2027/28 budget by February 2027
Who it affectsAll Merton residents and servicesWhole-borough medium term financial planning

What was decided

Cabinet noted the approach to rolling forward the MTFS for 2027 to 2031, as set out in the report. Report P7

Officers revised the MTFS gap to 9,694 in 2027/28, 19,014 in 2028/29, 26,290 in 2029/30 and 33,808 in 2030/31, with all figures in £'000. Report P59, P60, P61

The report increases the pay inflation assumption from 2% to 3% in 2027/28 only, while keeping price inflation at 2%. Report P33, P35, P36

Why

The Council agreed the 2026/27 budget and MTFS 2026-30 on 25 February 2026, leaving a significant gap in later years that needs to be addressed. Report P8, P9

Global events, including the conflict in the Middle East, have pushed inflation and interest rates higher, increasing cost pressures on the Council. Report P19, P30

A new Finance Strategy is being developed to align resources, transformation and service priorities over the MTFS period. Report 4.3

What happens next

The MTFS will be reviewed again in autumn 2026, alongside the new Council Plan, to produce options for a balanced 2027/28 budget. Report P8, P66

The budget setting report will go to Council in February 2027. Report P66

Quarterly financial monitoring reports on SEND and the Dedicated Schools Grant will be submitted to the Department for Education, starting with the Q1 report in July 2026. Report P43

The money

  • 9,694 Revised MTFS gap 2027/28, in £'000 Report P61
  • 19,014 Revised MTFS gap 2028/29, in £'000 Report P61
  • 26,290 Revised MTFS gap 2029/30, in £'000 Report P61
  • 33,808 Revised MTFS gap 2030/31, in £'000 Report P61
  • 4,300 PFI saving in 2030/31 from end of schools PFI contract, in £'000 Report P61, 4.12
  • 1,568 Extra pay inflation cost in 2027/28 from raising assumption to 3%, in £'000 Report P34, P59
  • 175 Extra price inflation cost in 2027/28 from re-pricing, in £'000 Report P36, P60
  • £4.3 million General fund contribution to schools PFI contract in 2026/27 Report 4.12
  • £58.610m Usable reserves set aside against DSG deficit as at 31 March 2026 Report P40
  • £69.126 Forecast DSG deficit at end of 2025/26 Report P40
  • £63.197m Forecast High Needs Stability grant to clear most of the historic DSG deficit Report P40
  • £48.124m Set-aside reserves that could be unearmarked after HNS grant, in £m Report P41
  • 2,397 Children, Lifelong Learning and Families outturn overspend 2025/26, in £'000 Report P50, P52

Options considered

  • Chosen: Note the approach to rolling forward the MTFS for 2027 to 2031. Statutory requirement to set a balanced budget by March 2027 means no alternative options at this stage. Report P7, 7.2

Implications

  • Financial: A revised cumulative budget gap of 33,808 (in £'000) is forecast for 2030/31, with pay inflation revised up and the end of the schools PFI contract reducing the gap in that year. Report P59, P60, P61
  • Risk: Inflation and interest rates are flagged as key financial risks, with the Middle East conflict cited as a major source of uncertainty. Report P19, P30
  • Legal: The Council has a statutory duty to set a balanced budget each year under the Local Government Finance Act 1992 and Local Government Act 2003. Report P69
  • Equalities: Any equalities impacts from the 2027/28 budget process will be set out in future reports. Report P69
  • Climate: Any climate change impacts from the 2027/28 budget process will be set out in future reports. Report P69
  • Other: The government has indicated a High Needs Stability grant of £63.197m to clear most of the historic DSG deficit, subject to approval of Merton's SEND reform plan. Report P40, P41, P43

Who and where

  • Merton Council taxpayers and residents across the borough Report P3, P12
  • Children with SEND and their families, via SEND reform and DSG deficit management Report P40, P41, P43
  • Adult Social Care service users, through Integrated Neighbourhood Health and Care reforms Report P55
  • Households in temporary accommodation and on the housing register Report P57
  • Council staff covered by the National Joint Council pay agreement Report P23, P25, P26

Timeline

  • 25 February 2026: Council agreed the 2026/27 budget and MTFS 2026 to 2030 Report P8, P46
  • 26 March 2026: National Employers made a one year pay offer of 3.30% on NJC pay points and allowances Report P25, P26, P27
  • 17 June 2026: Bank of England Monetary Policy Committee voted to maintain Bank Rate at 3.75% Report P30
  • July 2026: First quarterly SEND and DSG monitoring report due to be submitted Report P43
  • Autumn 2026: Further MTFS review and options to be developed Report P8, P66
  • 13 July 2026: Cabinet noted the approach to rolling forward the MTFS for 2027 to 2031 Report P2
  • February 2027: Council expected to set the 2027/28 budget Report P66
  • 31 March 2028: Statutory Override on DSG deficits ends; from 2028/29 SEND spending covered by government DEL budget Report P40
  • 2029/30: Schools PFI contract ceases, removing the general fund contribution of £4.3 million Report 4.12, P61

Plain English for the jargon

  • MTFS: Medium Term Financial Strategy, the Council's multi-year financial planning document.
  • DSG: Dedicated Schools Grant, the ring-fenced funding for schools.
  • SEND: Special Educational Needs and Disabilities.
  • PFI: Private Finance Initiative, a contract with a private firm to run and maintain public buildings.
  • CPI: Consumer Prices Index, the main UK measure of inflation.
  • HNS grant: High Needs Stability grant, government funding to clear historic SEND deficits.
  • ASC: Adult Social Care.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9

Resolved

A. Cabinet notes the approach to rolling forward the MTFS for 2027-31. A. Cabinet notes the approach to rolling forward the MTFS for 2027-31.
Word for word from the decision Merton published for this meeting. Source: democracy.merton.gov.uk

Follow this further

Built from Merton's papers

What the report saysPro

Report to Cabinet

Agenda Item 9

Report cover sheet NAME OF DECISION-MAKER DATE Cabinet 13th July 2026

REPORT/DECISION TITLE WARD(S) Budget 2027/28 and MTFS 2027-31 All

CHIEF OFFICER(S) CABINET/LEAD MEMBER(S) Name: Asad Mushtaq, Executive Director of Name: Councillor Stephen Alambritis Finance & Digital Cabinet Member for Finance and Corporate Services

DECISION CLASSIFICATION IS THE FINAL DECISION ON THE RECOMMENDATIONS IN THIS Key REPORT TO BE MADE AT THIS Non-exempt MEETING?

Yes

1. Recommendations A. Cabinet notes the approach to rolling forward the MTFS for 2027-31.

2. Executive summary 2.1 This report provides an initial re-pricing of the Medium Term Financial Strategy (MTFS) as the first step towards setting a balanced budget for 2027/28 and future years. The MTFS will be furthered reviewed in the autumn to take into account any updates to the Council’s service priorities.

Page 205 2.2 It updates the MTFS for known changes and pricing updates to recast the MTFS budget gap and update some of the assumptions used for last year’s budget setting process. It also includes initial budget pressures that will need to be addressed.

3. Relevance to strategic priorities, including Council Plan priorities Strategic priority Relevant? Brief explanation of relevance

Borough of Sport

Building a The report outlines the forecast financial sustainable future position of the Council for the period 2027-2031. The financial health and X sustainability of the authority underpins every area of the Council’s services and is therefore vital for delivering against the Council’s strategic priorities.

Nurturing civic pride

Other service delivery priority

Organisational development

Page 206 Background, options and next steps

4. Introduction and background 4.1 This report presents an initial review and re-pricing of the Medium Term Financial Strategy (MTFS) for 2027-31 as the first stage of the Council’s financial planning process. The Council has a well-established MTFS approach which has supported previous budget setting and medium-term financial planning. However, as the Council's operating environment continues to evolve, there is an opportunity to further strengthen the alignment between resources, transformation and service priorities over the full MTFS period. To support this evolution, the Council is developing a new Finance Strategy which will strengthen the practical framework for how the MTFS is constructed, managed and delivered. This will build on existing arrangements while providing greater clarity on the rules for setting the base budget; the approach to demand, inflation and income forecasting; the identification, testing and monitoring of savings; the role of transformation in delivering financial sustainability; the relationship between capital investment and revenue consequences; the use of reserves; and the governance arrangements needed to maintain grip, pace and assurance. As the Finance Strategy is developed, it is expected to refine the way the MTFS is presented and the assessment of the budget gap over the period. In particular, it will enable a clearer view of the investment required over the next MTFS period, the transformation activity needed to reduce demand and cost, and the extent to which savings proposals are deliverable. The budget gap set out in this report should therefore be regarded as an initial baseline position, which will be updated through further MTFS reports during the year as the Finance Strategy, transformation programme and supporting financial assumptions are developed. 4.2 Council on 25 February 2026 agreed the Budget 2026/27 and MTFS 2026-30. Whilst a balanced budget was set for 2026/27, there is a significant gap remaining in future years which needs to be addressed as shown in the following table: - 2027/28 2028/29 2029/30 2030/31 Cumulative Gap £000 £000 £000 £000 MTFS 2025-29: (Council – Feb.2025) 7,951 16,936 23,879 35,363

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Budget 2027/28 and MTFS 2027-2031Report 342 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 22 attended
SE
Sharon EvansCouncil Staff, in attendance
LA
Lewis Addlington-LeeCouncil Staff, expected
RG
Ross GarrodChair, present
ES
Eleanor StringerCommittee Member, present
CC
Caroline Cooper-MarbiahCommittee Member, present
AJ
Andrew JudgeCommittee Member, present
SK
Sally KennyCommittee Member, present
PM
Peter McCabeCommittee Member, present
UK
Usaama KaweesaCommittee Member, present
TO
Test OfficerCouncil Staff, expected
EM
Edith Macauley MBECommittee Member, present
SN
Stuart NeaversonCommittee Member, present

All 22 on the meeting page

On this subject at Merton

Search all
  1. Budget 2027/28 and MTFS 2027-2031This decision
  2. Budget 2026/27 and MTFS 2026-30Agreed
  3. Budget 2026/27 and MTFS 2026-30Agreed
  4. Budget 2026/27 and MTFS 2026-30Agreed
  5. Budget 2026/27 and MTFS 2026-30Agreed
  6. Budget 2025/26 and MTFS 2025-29Agreed

More from Merton Cabinet

All decisions
MeetingDecisionOutcome
21 Sep 2026 Council’s New Homes ProgrammeCabinet is asked to: A. Approve the establishment of the (the Programme) as set out in this paper. B. Approve the pro... Approved Open
21 Sep 2026 Morden Town Centre RegenerationCabinet is asked to: A. Note the progress made on the Programme since Cabinet approved the procurement of a developme... Noted Open
21 Sep 2026 Property Asset Strategy Principles and corporate landlord modelCabinet is asked to: A. Approve the Property Asset Strategy principles as set out in this report. B. Agree the implem... Approved Open
21 Sep 2026 Recycling and Waste Collection Services Contract Update 2026Cabinet is asked to: A. Note the key performance indicators for the first year following the award of the contract fo... Noted Open
21 Sep 2026 Environmental Enforcement and Animal Welfare Contract – Extension and VariationCabinet is asked to: A. Approve the extension of the environmental enforcement contract (without the stray/abandoned ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies