What was decided
Cabinet noted the key performance indicators for the first year of the Recycling and Waste Collection Services contract which commenced on 1 April 2025. Report 3.3
Cabinet approved a variation of the contract with Veolia for £92k for 2026/27 to deliver the free bulky waste service introduced on 1 June 2026. Report 5.14
Cabinet noted the financial impact and approved £750k capital growth to implement improved containerisation to all kerbside households for dry mixed recycling, replacing 55L green boxes with green-lidded wheeled bins. Report 5.10, 5.13, 8.1
Cabinet delegated authority to the Executive Director of Environment, Civic Pride and Climate in consultation with the Lead Member for Cleaner Streets, Environment and Transport to approve any subsequent contract variations permitted by the Council's Contract Standing Orders.
Why
The preferred option utilises the existing waste contract with Veolia, which is well positioned to accommodate the proposed service changes and avoids the need for additional contract management or project management resources. Report 7.3
Improved containerisation is expected to increase recyclate capture rates, reduce material strewn from unlidded containers, improve street scene cleanliness, and save money on residual waste disposal costs. Report P44, 5.12
The free bulky waste service may help reduce fly-tipping by providing residents with a convenient and responsible disposal option, particularly for residents experiencing financial hardship. Report 5.15, 8.3
The contract variation is the most practical and cost-effective approach, leveraging existing economies of scale, and is legally compliant with Regulation 72(1)(f) of the Public Contracts Regulations 2015. Report 5.19, P89
What happens next
The call-in period runs from 23 September to 28 September 2026 at noon. The deed of variation and contract change control will be signed on 5 October 2026, with commencement of the variation on 6 October 2026. Report P84
A trial of wheeled bins for dry mixed recycling will be undertaken across two collection rounds commencing in September 2026, evaluating recyclate capture rates, operational productivity, container sizes, and impact on street cleanliness. Report 5.12
The initial implementation period of the free bulky waste service (June 2026 to March 2027) will be used to assess demand and evaluate whether current resourcing levels are sufficient. Report 5.16
The money
- £92k Contract variation with Veolia for free bulky waste service in 2026/27
- £750k Capital growth required for improved containerisation to kerbside households Report 8.1
- £2m Estimated cost of supplying wheeled bins to approximately 67,000 properties Report 5.10
- £1.25m Capital funding secured in 2023/24 for wheeled bins Report 5.9
- £323k Pro-rata budget impact for free bulky waste service in 2026/27
- £380k Estimated full-year cost of free bulky waste service from 2027/28 onwards Report P90
- £8.48m Annual value of the Recycling and Waste Collection Services contract Report 5.2
- £205m Total potential value of the contract including all extension options Report 5.2
- £29.34 Cost per household for new wheeled bin and associated distribution services Report P48
- £110,611 Defra grant for transitional receptacles for food waste service Report P25
- £204,600 Defra grant for additional waste vehicles for food waste collection Report P25
Options considered
- Chosen: Approve recommendations: vary contract for free bulky waste service and provide capital growth for containerisation. This option utilises the existing contract which is well positioned to accommodate the proposed changes, avoids additional contract or project management resources, and delivers wider place improvement benefits. Report 7.1, 7.3
- Rejected: Do Nothing: do not approve recommendations. Insufficient capital for borough-wide rollout would result in partial rollout only, incurring additional revenue costs of £376k per year for hybrid container model; failing to provide fit-for-purpose containers once soft plastics collection is mandated under Simpler Recycling from April 2030; and reputational risk from withdrawing the free bulky waste service. Report P57, P58, P59
- Rejected: Procure New Services: separately commission alternative services for bulky waste collections and container provision. Additional officer time required for separate procurement; unlikely to achieve more competitive price; another contract to manage; risk of challenge from Veolia as these services were awarded as part of the broader contract; and likely to be more expensive with dedicated project management resources required. Report P68, P69
Implications
- Financial: Revenue implications for free bulky waste service are estimated at £323k pro-rata for 2026/27, to be met from existing department budgets, with full-year cost of £380k from 2027/28 to be considered in future budget-setting. Report P90
- Legal: The contract variation is legally compliant with Regulation 72(1)(f) of the Public Contracts Regulations 2015. The total contract value currently stands at £68,357,676, with potential value of £205m including extensions. Report P89
- Legal: The delegation of authority under Recommendation D is permissible under s.9E of the Local Government Act 2000. Report P89
- Staffing: To deliver the free bulky waste service, an extra vehicle and two members of staff have been secured, deploying a second bulky waste collection round that effectively doubles the resources originally allocated within the core contract. Report 5.17
- Risk: The free bulky waste service could receive higher demand than proposed resources accommodate. This is being monitored daily and will be reviewed following the initial implementation period. Report P46
- Risk: If capital growth is not provided, only part of the borough could receive wheeled bins and a hybrid container model would require additional revenue resources of £376k per year. Report P57, P59
- Environment: Improved containerisation is expected to deliver environmental benefits including reducing risk of materials being blown from containers, minimising litter on collection days, and preventing access by rodents. Report 5.12
- Health and safety: The transition to wheeled bins removes the need for transfer bins, enabling safer and more efficient collection methodology with direct loading into collection vehicles, reducing manual handling requirements and improving operational productivity. Report P95
Who and where
- All kerbside households in Merton Report 5.10, 5.13
- Approximately 67,000 properties receiving new green-lidded wheeled bins for dry mixed recycling Report 5.10, P48
- Approximately 1,800 flats above shops receiving communal food waste container solutions Report 5.6
- Residents booking bulky waste collections Report 5.14, 5.15
- Veolia Environmental Services as the contractor Report 5.2, 5.17
Timeline
- April 2025: Recycling and Waste Collection Services contract with Veolia commenced Report 3.3, 5.1
- April 2026: Legal requirement for all households to have access to weekly food waste collection Report 5.6
- 1 June 2026: Free bulky waste collection service introduced Report 5.14
- 14 July 2026: Date of decision on Forward Plan Report P84
- 21 July 2026: Procurement Board Report P84
- September 2026: Trial of wheeled bins for dry mixed recycling across two collection rounds Report 5.12
- 21 September 2026: Cabinet meeting Report P84
- 23 September to 28 September 2026: Call-in period Report P84
- 5 October 2026: Deed of variation and contract change control signed Report P84
- 6 October 2026: Commencement of contract variation Report P84
- March 2027: End of initial implementation period for free bulky waste service Report 5.16
- April 2030: Simpler Recycling will mandate collection of soft plastics from all domestic properties
- 31 March 2033: Initial contract term concludes Report 5.2
Plain English for the jargon
- Simpler Recycling: Government reforms requiring weekly food waste collections from April 2026 and soft plastics collections from April 2030
- Dry mixed recycling: Cans, plastics, glass and paper collected for recycling from kerbside households
- Containerisation: Transition from 55L green boxes to green-lidded wheeled bins for dry mixed recycling
- Regulation 72(1)(f): Public Contracts Regulations 2015 provision allowing contract modifications for additional services
- Capital growth: Additional capital funding approved above existing budget allocation
- Call-in period: Five working day period after Cabinet decision during which decisions can be called in for scrutiny