London Borough of Merton
Cabinet, Monday 21 September 2026 at 7.15pm

Morden Town Centre Regeneration

Noted Executive 1 paper

AI summaryCabinet noted progress on Morden Town Centre Regeneration Programme, approved the vision and procurement timeline, with Pre Market Engagement due end September 2026 and formal procurement in November 2026, building on the £30m capital allocation approved in January 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNoted
Money£30mInitial capital allocation approved by Cabinet and Council in January 2026
What happens nextPre Market EngagementDue to launch end September 2026, formal procurement launch November 2026
Who it affectsMorden Town CentreResidents, businesses, community organisations within the regeneration area

What was decided

Cabinet noted the progress made on the Morden Town Centre Regeneration Programme since Cabinet approved the procurement of a development partner in January 2026 Report 2.3

Cabinet noted the Town Centre Vision and Strategic Objectives for the development of the new Civic Hub, which establish the Council's strategic ambitions for Morden Town Centre Report 4.10, 4.11, 4.12, 4.13, 4.14

Cabinet noted the updated procurement programme, targeting Pre Market Engagement by end September 2026 and formal procurement launch end November 2026, and noted the planned communications programme and engagement approach Report 4.35, 4.36

Why

The Council cannot deliver the regeneration on its own and needs to take a clear, credible and investable proposition to market to attract the best development partner Report 2.2

The Vision brings together what the Council has heard over time from residents, businesses and community stakeholders with the opportunities presented through the regeneration programme Report 4.12, 4.28

The procurement approach was approved by Cabinet in January 2026 and this report provides an update on progress and readiness to proceed Report 2.3, 4.34, 4.35

What happens next

Preliminary Market Engagement will start at the end of September 2026 to test the procurement proposition with the market Report 4.35, 4.36

Subject to governance approvals, formal procurement is targeted for November 2026 with a two-stage Competitive Flexible Procedure Report 4.36, 4.37, 4.38

A Community Panel will be established to provide an ongoing forum for the existing community throughout the life of the programme

The money

  • £30m Initial capital allocation approved by Cabinet and Council in January 2026 to support programme delivery and begin addressing land assembly and enabling challenges Report 2.3

Options considered

  • Rejected: Do not note the progress and proceed to procurement. The report recommends noting progress to demonstrate programme advancement and readiness Report P1, P2, 4.1, 4.8
  • Chosen: Note the progress, vision, procurement programme and communications approach. This enables the programme to continue to the next phase of procurement with stakeholder support Report P2, 2.4

Implications

  • Financial: The Council has bid to GLA for Affordable Housing Grant in May 2026 and is engaging with GLA to achieve a successful outcome and explore other funding opportunities Report 4.28
  • Risk: Key risks include lack of private sector interest, further public and Council funding required to achieve viability, upfront land assembly requirements, potential economic downturn, and reliance on Compulsory Purchase Order for land assembly Report P127
  • Equalities: Potential beneficial impacts identified for people with protected characteristics including children, older people, disabled people, ethnic minorities, care-experienced people and lower socio-economic backgrounds, with adverse impacts anticipated during construction including demolition and relocation Report P125, P126
  • Legal: The procurement approach using two-stage Competitive Flexible Procedure complies with the Procurement Act 2023 and Council contract standing orders Report P123, P124
  • Climate: Key sustainability and climate targets will be included in procurement documentation in line with the Council's Local Plan and Net Zero objectives Report P126

Who and where

  • Residents, businesses and community organisations within the regeneration area Report 4.39
  • Ward councillors Report 4.39
  • Transport for London, Places for London, Greater London Authority and other public-sector partners Report 4.41

Timeline

  • September 2025: Cabinet agreed the Council should take a leading role in enabling and delivering the long-term regeneration of Morden Town Centre Report 2.3, 4.2, 4.3
  • January 2026: Cabinet approved the procurement of a development partner through a phased Development Agreement and approved an initial £30m capital allocation Report 2.3, 4.6
  • May 2026: Council's bid to GLA for Affordable Housing Grant included the town centre regeneration Report 4.28
  • End September 2026: Pre Market Engagement to launch Report P2, 4.35
  • November 2026: Formal procurement launch Report P2, 4.36
  • November 2026 to February 2027: Invitation to Participate stage
  • February 2027: Evaluation and shortlisting
  • March 2027: Invitation to Tender stage
  • Spring and Summer 2027: Dialogue phase
  • End Summer 2027: Call for final tenders
  • Autumn 2027: Final tender evaluation and moderation

Plain English for the jargon

  • Competitive Flexible Procedure: A procurement process under the Procurement Act 2023 allowing structured dialogue with bidders to test viability and develop solutions
  • Civic Hub: A new building intended to be the democratic heart of the borough, providing an accessible front door for residents and services
  • Minimum Requirements: Non-negotiable requirements that bidders must meet, including minimum size of Civic Hub, affordable homes share, commercial units and sustainability standards
  • Preliminary Market Engagement: Testing the procurement proposition with the market before formal launch to refine the approach
  • Phased Development Agreement: A contractual structure allowing development to proceed in stages while retaining flexibility
  • Project Objectives: Objectives bidders must respond to in dialogue and tenders, forming part of how they would deliver Council outcomes
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5

Resolved

Cabinet is asked to: A. Note the progress made on the Programme since Cabinet approved the procurement of a development partner in January 2026. B. Note the Town Centre Vision and Strategic Objectives for the development of the new Civic Hub, both of which establish the Council's strategic ambitions for Morden Town Centre and will form the basis of the procurement of the development partner. C. Note the updated procurement programme, targeting the launch of Pre Market Engagement by the end September, and the formal procurement launch end November 2026. D. Note planned communications programme and engagement approach for the period before, during and beyond procurement.
Word for word from the decision Merton published for this meeting. Source: democracy.merton.gov.uk

Follow this further

Built from Merton's papers

What the report saysPro

Report to Cabinet

Recommendations

Cabinet is asked to:

A. Note the progress made on the Morden Town Centre Regeneration Programme since Cabinet approved the procurement of a development partner in January 2026. B Note the Town Centre Vision and Strategic Objectives for the development of the new Civic Hub, both of which establish the Council's strategic ambitions for Morden Town Centre and will form the basis of the procurement of the development partner. C Note the updated procurement programme, targeting the launch of Pre Market Engagement by the end September, and the formal procurement launch end November 2026. D Note planned communications programme and engagement approach for the period before, during and beyond procurement.

Page 7 2. Executive summary

2.1Morden Town Centre represents a major long-term regeneration opportunity. Building on Morden’s exceptional connectivity, established high street, civic role and relationship with Morden Hall Park, regeneration provides the opportunity to create a vibrant destination where people choose to spend time throughout the day and evening. It can bring new life and investment to the high street, create better streets, public spaces and connections to green space, introduce new opportunities for sport, leisure, culture and community activity, create jobs, attract investment and reinforce Morden’s role as the civic heart of the borough. Alongside this, new and affordable homes will help grow sustainable neighbourhoods and enable more people to make Morden their home.

2.2The Council cannot deliver this on its own. Realising this ambition will require the Council to take a clear, credible and investable proposition to market in order to attract the best development partner with whom to secure delivery.

2.3In September 2025, Cabinet agreed that officers should lead and enable the regeneration of Morden Town Centre. In January 2026, Cabinet approved the procurement of a development partner through a phased Development Agreement using the Competitive Flexible Procedure and approved an initial £30m capital allocation. Since then, the programme has moved from establishing the route to market to defining what the Council is seeking to achieve, and the requirements against which a future partner will be assessed.

2.4This report provides Cabinet with an update on all activities since the January 2026 decision, to demonstrate how the programme has progressed, as well as what remains to do, to be ready to successfully procure the Council’s a development partner.

3. Relevance to strategic priorities, including Council Plan priorities

Strategic priority Relevant? Brief explanation of relevance

Borough of Sport The regeneration of Morden Town Centre will contribute to delivering this strategic objective by creating opportunities for new sports and leisure activities and to deliver additional sporting initiatives. The regeneration of Morden Town Centre Building a will contribute to delivering new good - sustainable future quality and affordable housing, creating and restoring green spaces, encouraging sustainable modes of transport and improving air quality. Nurturing civic pride The regeneration of Morden will contribute to creating a more vibrant welcoming town centre and

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Morden Town Centre RegenerationReport 4 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 13 attended
SE
Sharon EvansCouncil Staff, expected
LA
Lewis Addlington-LeeCouncil Staff, expected
RG
Ross GarrodChair, expected
ES
Eleanor StringerCommittee Member, expected
CC
Caroline Cooper-MarbiahCommittee Member, expected
SK
Sally KennyCommittee Member, expected
PM
Peter McCabeCommittee Member, expected
UK
Usaama KaweesaCommittee Member, expected
TO
Test OfficerCouncil Staff, expected
EM
Edith Macauley MBECommittee Member, expected
SN
Stuart NeaversonCommittee Member, expected
SA
Stephen Alambritis MBECommittee Member, expected

All 13 on the meeting page

On this subject at Merton

Search all
  1. Morden Town Centre RegenerationThis decision
  2. Morden Town Centre RegenerationApproved
  3. Morden Town Centre RegenerationApproved
  4. Morden Town Centre Community Engagement and PlacemakingNoted
  5. Morden Town Centre Regeneration: Placemaking and Public RealmNoted
  6. Delivery of the regeneration of Morden town centreNoted

More from Merton Cabinet

All decisions
MeetingDecisionOutcome
21 Sep 2026 Council’s New Homes ProgrammeCabinet is asked to: A. Approve the establishment of the (the Programme) as set out in this paper. B. Approve the pro... Approved Open
21 Sep 2026 Property Asset Strategy Principles and corporate landlord modelCabinet is asked to: A. Approve the Property Asset Strategy principles as set out in this report. B. Agree the implem... Approved Open
21 Sep 2026 Recycling and Waste Collection Services Contract Update 2026Cabinet is asked to: A. Note the key performance indicators for the first year following the award of the contract fo... Noted Open
21 Sep 2026 Environmental Enforcement and Animal Welfare Contract – Extension and VariationCabinet is asked to: A. Approve the extension of the environmental enforcement contract (without the stray/abandoned ... Approved Open