Resolved
RESOLVED that the application be deferred ... view the full minutes text for item 31.
Planning Committee deferred this item on Wednesday 8 June 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the application be deferred ... view the full minutes text for item 31.
Application No. 15/01034/MFUL Plans List No.
Grid Ref: 299621 : 112764
Applicant: [name removed]: Land at NGR 299621 112764 (Red Linhay) Crown Hill Halberton
Proposal: Erection of a 500kW anaerobic digester and associated works with 2 silage clamps. Revised Scheme to include the change of orientation of the layout and installation of 2 driers
Date Valid: 17th July 2015 Application No. 15/01034/MFUL
RECOMMENDATION Grant permission subject to conditions.
PROPOSED DEVELOPMENT
The proposed development is for a revised scheme for the installation of an anaerobic digester (AD) to generate 500kW of electricity converted from biogas via a combined heat and power unit (CHP). Some of the power will be used to run the site with the remainder exported to the National Grid. The site was a pasture field which formed part of the Hartnoll Farm agricultural holding accessed via the existing access on Crown Hill and is adjacent to existing agricultural buildings associated with Hartnoll Farm. Works have already commenced on site and this application is to regularise the proposed scheme following approval under 13/01605/MFUL.
The current proposal is not to consider if the principle of the AD plant is appropriate as this has been established previously, but to consider if the changes to site layout and additional items within the site which vary the current scheme from that previously approved under 13/01605/MFUL are acceptable. The scheme is essentially the same as that approved under 13/01605/MFUL. A synopsis of the changes proposed is attached as Appendix 1.
The AD plant comprises:
- A digester tank: height 8m, diameter 25m and capacity 3926 cubic metres with a gas collection dome above of height 5.5m. overall height from excavated site is 13.5m - A digestate storage tank: height 8m, diameter 25m and capacity of 3926 cubic metres. - A buffer tank: height 4m and diameter 9m. - A control cabin housing the control panels for the anaerobic digester: 12 long, 3m wide and 2m high - 1 x CHP unit (combined heat and power unit): 13.5m long and 3 m wide contained in an acoustic box including a chimney of 7m - Control building 14m long x 7m wide x 3m high - Gas compressor building 8m x 3.5m x 3m high - Transformer, HV switch each 2.5m x 2.5m x 2.4m high - LV panel 12m x 2.5m x 2.5m high - Office 13.5m x 2.5m x 2.5m high - Solids feeder 9m x 4m x 4m high - 2 x Dryers 43m x 6m x 3.5m high - Gas flare 6m x 3m x 4.8m high - A separator frame and clamp: 9m long, 7m wide and 5.5m high - Feedstock clamps comprising 2 bays: 60m x 30m x 4m high proposed to hold material - A concrete yard for vehicular movements - A GRP kiosk to house metering circuit breaker
The buffer tank, separator frame and clamp and solids feeder would be contained within a bund recessed into the ground by 2.0m metres. The digester tank and digestate store will be set a further 2.5m below these. The overall area covered by the plant will be approximately 1.23 hectares, with an additional area to accommodate planting for screening.
The AD will be fed by approximately 14,231 tonnes of feedstock per annum comprising the following as set out in the Odour Management Plan:
- Cow slurry - 2,000 tonnes - Farmyard manure - 1,000 - Chicken manure - 2,000 tonnes - Maize - 4,444 tonnes - Grass Silage - 2981 tonnes - Beet - 1500 tonnes No animal by-products will be processed at the plant. The manures will be sourced from Swanhams Farm located approximately 4.25 km east of Halberton and Rix Farm located immediately north of the A361 between Tiverton and Bolham. The maize, grass and beet silage will be sourced from a number of local sites named by the applicant as Hartnoll Farm, Manley Lane, Maunders and 'Plots' all located within approximately 3km of the AD site and Wellington Farm which is located approximately 20km away.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
1501034 Committee Report with UPDATES 10.2.16Report | 453 KB | DownloadRead as text |
PDF |
1501034MFUL Appendix 1: Committee 13.1.2016Appendix | 152 KB | Download |
PDF |
1501034MFUL Implications Report 6th April 2016Report | 260 KB | Download |
PDF |
160526_Red Linhay_Technical Report_Final Issue.compressedReport | 8.5 MB | Download |
PDF |
APPLICATION 15/01034/MFUL: ERECTION OF A 500KW ANAEROBIC DIGESTER AND ASSOCIATED WORKS WITH 4 SILAGE CLAMPS: REVISED SCHEME TO INCLUDE THE CHANGE OF ORIENTATION OF THE LAYOUT AND INSTALLATION OF 2 DRIERS AT LAND AT NGR 299621 112764 (RED LINHAY), CROWN HILL (1-25-06)Report | 334 KB | Download |
Follow Planning Committee at Mid Devon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Sep 2026 | The plans list (00:15:54)RESOLVED to grant consent. (Proposed by Cllr G DuChesne and seconded by Cllr B Holdman) 2. 25/01736/MFUL - Demolition... | Decided | Open |
| 19 Aug 2026 | The plans list (00:07:32)RESOLVED that planning permission be granted subject to conditions. (Proposed by Cllr S Clist and seconded by Cllr S ... | Decided | Open |
| 29 Jul 2026 | Election of chair for the municipal year 2026/2027RESOLVED that Cllr L Cruwys be elected Chair of the Planning Committee for the municipal year 2026/2027. (Proposed by... | Decided | Open |
| 29 Jul 2026 | Election of vice-chair for the municipal year 2026/2027RESOLVED that Cllr G Cochran be elected Vice-Chair of the Planning Committee for the municipal year 2026/2027. (Propo... | Decided | Open |
| 29 Jul 2026 | The plans listRESOLVED that planning permission be granted for non-material amendments. (Proposed by Cllr S Clist and seconded by C... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.