APPLICATION 16/00352/MFUL - CONSTRUCTION OF A NEW TWO STOREY SCHOOL ON EXISTING SCHOOL GROUNDS, WITH ASSOCIATED LANDSCAPING WORKS AND DEMOLITION OF EXISTING SCHOOL BUILDINGS AT CASTLE PRIMARY SCHOOL, BARRINGTON STREET, TIVERTON (2-34-00)
DecidedPlanning1 paper
Planning Committee decided this item on Wednesday 8 June 2016. Below is the council's own wording, with the papers it was decided on.
RESOLVED that planning permission be granted subject to conditions as recommended by the Head of Planning and Regeneration with delegated authority being given to the Head of Planning and Regeneration to negotiate amendments to the external materials and colour. (Proposed by Cllr Mrs H Bainbridge and seconded by Cllr D J Knowles) Notes: i) Cllr Mrs F J Colthorpe declared a personal interest in the matter as she had in the past chaired the Tiverton Education Foundation which owned the land the school was built on and chose to leave the meeting whilst discussion took place; (Cllr P J Heal, Vice Chairman took the chair); ii) Cllr R F Radford declared a personal interest as a County Councillor; iii) Cllr D J Knowles declared a personal interest as a Member of the Civic Society and that some of the objectors were known to him; iv) [name removed] ( Headteacher ) spoke in support of the application; v) Cllr C J Eginton spoke ... view the full minutes text for item 32.
Word for word from the decision Mid Devon published for this meeting.Source: democracy.middevon.gov.uk
This application is relevant to the Corporate Plan priorities of community and environment.
Financial implications
Education Funding Agency funding for this scheme has been secured under the Priority Schools Building Programme.
Legal implications
None identified.
Risk Assessment:
Clarification has been sought from the Education Funding Agency (EFA) on the status of the Priority Schools Building Programmes award associated with this site and the extent to which building retention and refurbishment has been considered as part of the bid process. The upgrading of school facilities is a public benefit resulting from the scheme. Clarification has been sought – the retention and refurbishment of the existing main school building has been considered as an option in the funding assessment and has been rejected. The EFA Funding Manager for the south west has confirmed that in his view funding would not be available or awarded for a retention and refurbishment based scheme. Accordingly it would appear that the only viable option in order to achieve a significant upgrade in the education facilities to achieve a 21st century teaching environment is the demolition of the existing building and the erection of a new school as proposed.
AGITEM Members need to weight the harm arising from the demolition of the existing school as a non-designated heritage asset and on the Conservation Area against the public benefit in realising upgraded school accommodation. If planning permission is refused, financial support from the EFA under the Priority Schools Building Programme will be lost. In that event, any future bid for EFA funding would still be made on the basis of a demolition and new build scheme.
Consultation carried out with:
1. Tiverton Town Council 2. Highway Authority 3. Devon County Education 4. Mid Devon Council Tree Officer 5. Environment Agency 6. Tiverton Civic Society 7. Historic Environment Service 8. Development Services Manager 9. Devon and Cornwall Police 10. Teignbridge District Council Conservation Team 11. Environmental Health 12. Lead Local Flood Authority 13. Natural England 14. Waste and Transport Manager
1.0PROPOSED DEVELOPMENT
This application proposes the construction of a new two storey school within the existing school grounds at Castle Primary School, Tiverton, including associated landscaping works and demolition of existing school buildings. The existing school buildings are proposed to be demolished.
The design of the proposed school is shown on drawing number 1090-PL07 REV A. The proposal is a modular design with a functional appearance. The proposal will be constructed from a mixture of concrete blockwork (Steel Grey and Bathstone), aluminium windows and doors (which incorporate blue and green panelling), and a shallow, dual pitched metal profiled roof. The overall size of the proposal measures approximately 76metres x 24metres with a height of 8.6metres to ridge and 7.2metres to eaves. The building includes a mixture of flues and ventilation cowls to support utilities within the building.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
APPLICATION 16/00352/MFUL: CONSTRUCTION OF A NEW TWO STOREY SCHOOL ON EXISTING SCHOOL GROUNDS, WITH ASSOCIATED LANDSCAPING WORKS AND DEMOLITION OF EXISTING SCHOOL BUILDINGS AT CASTLE PRIMARY SCHOOL, BARRINGTON STREET, TIVERTON (2-34-00)Report
32APPLICATION 16/00352/MFUL - CONSTRUCTION OF A NEW TWO STOREY SCHOOL ON EXISTING SCHOOL GROUNDS, WITH ASSOCIATED LANDSCAPING WORKS AND DEMOLITION OF EXISTING SCHOOL BUILDINGS AT CASTLE PRIMARY SCHOOL, BARRINGTON STREET, TIVERTON (2-34-00)This decision
APPLICATION 16/00352/MFUL - CONSTRUCTION OF A NEW TWO STOREY SCHOOL ON EXISTING SCHOOL GROUNDS, WITH ASSOCIATED LANDSCAPING WORKS AND DEMOLITION OF EXISTING SCHOOL BUILDINGS AT CASTLE PRIMARY SCHOOL, BARRINGTON STREET, TIVERTON (2-34-00)This decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.