RESOLVED that planning permission be refused as recommended by the Head of Planning and Regeneration. (Proposed by Cllr Mrs J Roach and seconded by Cllr F W Letch) Notes : i) Cllr R F Radford declared a personal interest as the applicant and the objectors were well known to him and his involvement in the application as Ward Member and chose to leave the meeting during the discussion thereon; ii) Cllrs [name removed], [name removed], [name removed], R J Dolley, P J Heal, F W Letch, B A Moore, [name removed], J D Squire and R L Stanley made declarations in accordance with the Protocol of Good Practice for Councillors Dealing in Planning Matters as they had all received correspondence regarding the application; iii) Cllr Mrs F J Colthorpe declared a personal interest as one of the objectors was known to her; iv) Cllr R J Dolley declared a personal interest as the applicant and the objectors were known to him; v) Cllr Mrs J Roach declared a personal interest as some of the objectors were known to her; vi) [name removed] ... view the full minutes text for item 8.
Word for word from the decision Mid Devon published for this meeting.Source: democracy.middevon.gov.uk
APPROVAL OF OUTLINE PLANNING APPLICATION Name and Address of Applicant: Name and Address of Agent: Friends Life Ltd [name removed] C/o AXA Real Estate Investment Managers RPS Planning & Development Ltd UK Ltd 2420 The Quadrant 155 Bishopsgate Aztec West London Almondsbury EC2M 3XJ Bristol BS32 4AQ
Date Registered : 4th July 2013
Proposal: Application to replace extant planning permission 10/00546/MOUT (to extend time limit). Outline for the erection of mixed use facilities building with associated parking and highway works (Revised scheme) Location: Land at NGR 305036 113872 (Junction 27) Sampford Peverell Devon
Site Vicinity Grid Ref: 305037/113872
MID DEVON DISTRICT COUNCIL HEREBY GRANTS OUTLINE PLANNING PERMISSION FOR THE ABOVE DEVELOPMENT
Subject to the following conditions:
1. Before any part of the development hereby permitted is begun, detailed drawings to an appropriate scale of the layout, scale and appearance of the building(s), and the landscaping of the site (hereinafter called the Reserved Matters) shall be submitted to and be approved in writing by the Local Planning Authority.
2. Application(s) for approval of all the Reserved Matters shall be made to the Local Planning Authority before the expiration of three years from the date of this permission.
3. The development hereby permitted shall be begun either before the expiration of three years from the date of this permission, or before the expiration of two years from the date of approval of the last of the Reserved Matters which have been approved, whichever is the later.
4. The development hereby permitted shall be carried out in accordance with the approved plans listed in the schedule on the decision notice.
5. The development hereby approved shall not be carried out other than in accordance with a phasing programme which shall previously have been submitted to and approved by the Local Planning Authority.
PEMOUZ 6. No work shall commence on site until details of a Sustainable Urban Drainage System for managing surface water have been submitted to and approved in writing by the Local Planning Authority. The sustainable urban drainage system shall incorporate porous paving, swales, filter strips, attenuation ponds and reed beds. The surface water management system shall thereafter be completed on site in accordance with the approved drawings and a timetable to be agreed in writing by the Local Planning Authority and thereafter retained.
7. A management plan, setting out the long term management responsibilities and maintenance schedules for the Sustainable Urban Drainage System shall be submitted to and approved in writing by the Local Planning Authority prior to any of the buildings first coming into use.
8. Prior to being discharged into any watercourse, surface water sewer or soakaway system, all surface water drainage from impermeable parking areas and hardstandings shall be passed through an oil interceptor designed and constructed to have a capacity and details compatible with the site being drained. Roof water shall not pass through the interceptor.
9. Oil or chemical storage facilities shall be sited in bunded areas. The capacity of the bund shall be at least 10% greater than the capacity of the storage tank or, if more than one tank is involved, the capacity of the largest tank within the bunded area. Hydraulically inter-linked tanks shall be regarded as a single tank. There shall be no working connections outside the bunded area.
10. The landscaping details required by Condition 1 above shall include all existing trees and hedgerows on the site, and details of those which are to be retained, with measures for their protection during the course of the development, together with a phasing scheme of planting of trees and shrubs (which shall include details of the species, siting and numbers to be planted).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.