RESOLVED that: a) The JCT Minor Works Building Contract with Contractor’s Design 2016 Edition for the MSCP improvement works be awarded to supplier B; b) Delegated authority be given to the Deputy Chief Executive (151) and the Cabinet Member for Housing and Property Services to agree on which Category 2 items as detailed on Part 2 Annex B should be included within the Contract award to supplier B, subject to ongoing budget authority after essential works have been concluded. c) An additional £50k to the Capital project for 2019/20 as set at item 5.4. be approved. (Proposed by Cllr S J Clist and seconded by Cllr L D Taylor) Note : *Report previously circulated, copy attached to minutes.
Word for word from the decision Mid Devon published for this meeting.Source: democracy.middevon.gov.uk
Cabinet Member: Cllr Simon Clist, Cabinet Member for Housing and Property Services.
Responsible Officer: Andrew Busby, Group Manager for Corporate Property and Commercial Assets.
Reason for Report: For Cabinet to review the results of the Multi Storey Car Park (MSCP) Improvement works tender and to award the JCT minor works Building Contract to a contractor.
RECOMMENDATION: To award the JCT Minor Works Building Contract with Contractor’s Design 2016 Edition for the MSCP improvement works. To delegate authority to the Deputy Chief Executive (151) and the Cabinet Member for Housing and Property Services to agree on which Category 2 items as detailed on Part 2 Annex B should be included within the Contract award to supplier B, subject to ongoing budget authority after essential works have been concluded. To approve an additional £50k to the Capital project for 2019/20 as set at item 5.4.
Relationship to Corporate Plan: Property assets are linked to the delivery, vision and priorities of the Council. The way that the Council manages its land and property assets has a direct impact on the quality of services delivered, as well as maximising the value derived from our property holdings for the on-going contribution in balancing the Councils budget. It is, therefore, important that efficient and effective use is made of our asset portfolio to support corporate and service objectives.
Financial Implications: The tender contract was to incorporate improvement works in all areas of the asset. The budget available in the 2019/20 financial year does not meet the cost involved therefore the improvement works will need to be phased over three financial years.
Legal Implications: The contract will be let via a JCT Minor Works Building Contract with Contractor’s Design 2016 Edition (MWD) with a JCT Public Sector Supplement 2011. Special conditions of Contract were contained in the Invitation to Tender and the Contract shall be subject to those special conditions with a JCT Public Sector Supplement 2011.
Risk Assessment: As part of the contract the contractor will need to provide a risk assessment specific to the site. All works will be compliant with the construction (design and management) regulation 2015.
MSCP Improvement works V1. 1 Equality Impact: There is no negative impact to equality
Impact on Climate Change: The Contractor will be required to be committed to managing and minimising our environmental impact.
This project is planned in a manner which takes account of the environmental impact, seeking to reduce such effects as much as possible. This will include travelling to site and effective planning to reduce the number of deliveries. This will introduce and promote environmental monitoring as a key element of management of the project. The impact of these works will result in an increase in our reported Carbon Footprint under scope 2 which will be reported in 2020/21 figures and the Council will look at measures to offset the additional carbon used on this project, e.g. energy efficiency lighting.
1.0INTRODUCTION
1.1The MSCP has had works identified for essential maintenance and improvement works. Some of the works are required for insurance purposes, this includes but is not limited to increasing the height of the safety railings to meet current standards and this work has been prioritised. The Property Services team were aware of the pending Premier Inn Project and given the scope of the works to construct the hotel it was sensible to hold back the improvement scheme until the construction works for the project had been completed.
1.2The detailed specification incorporated a range of essential improvement works which was tendered during May 2019 and the tender submissions were received on 12 July 2019.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
2027/28 Draft Budget Update (00:04:00)RESOLVED that: 1. The proposed approach to balancing the 2027/28 General Fund and Housing Revenue Account budget gaps...
Minutes of the Previous MeetingThe minutes of the previous meeting held on 07 July 2026 were APPROVED as a correct record and SIGNED by the Leader. ...
2026/27 Budget Monitoring- Quarter 1The Cabinet had before it a report * from the Deputy Chief Executive (S151) on the 2025/26 Budgeting Monitoring quart...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.