Mid Devon District Council
Cabinet, Tuesday 13 January 2026 at 5.15pm

Multi- Storey Solar Project

Approved Executive 1 paper

AI summaryMid Devon Cabinet approved a £640,000 solar and battery storage project on the roof of the Phoenix Lane multi-storey car park in Tiverton, aiming to cut electricity costs by £67,500 a year and save 215 tonnes of carbon annually.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedSolar PV and battery storage on car park roof
Money£640,000 project cost£600k approved, £40k from earmarked reserve
What happens nextOn-site works from Q1 2026Completion targeted for Q3 2026
Who it affectsAll wardsPhoenix Lane car park, Tiverton

What was decided

Cabinet approved the Phoenix Lane Solar and Battery Energy Storage System project under Option 3, which removes existing car ports and adds a new raised car port structure on level 9 to maximise solar yield.

Delegated authority was given to the Cabinet Member for Governance, Finance and Risk, in consultation with the Deputy Chief Executive (s151) and the Head of Finance, Property and Climate Resilience, to deliver the project. Report P16, P17

The project would install a solar PV array across the top three levels of the Phoenix Lane car park in Tiverton, supported by a battery energy storage system, to power Phoenix House. Report P14

Why

Option 3 was chosen because it delivers the highest solar yield, the shortest payback period, and the largest financial return over the 25-year array lifetime, despite higher initial costs.

The project supports the council's Corporate Plan and Climate Change Strategy by cutting greenhouse gas emissions, reducing energy costs, and acting as a model for future sites. Report P35, P36, P37, P38, P45

The council already invests in solar at its leisure centres, and this would be its first bespoke solar PV and battery storage installation.

What happens next

Project management will be led by the Corporate Projects Officer, with oversight by the corporate Programme Board and support from the South West Net Zero Hub on procurement and design.

Planning permission will be required for the new car port on level 9; phases on levels 10 and 11 could be delivered first under permitted development rights while planning is sought.

Further consents are needed from the District Network Operator (National Grid) for supply agreements and system compliance before sign-off by the Deputy Chief Executive (s151). Report P41

The money

  • £640k Estimated total project cost for Option 3
  • £600k Capital Programme funding already approved by Cabinet
  • £40k Remainder, covered by earmarked reserve for car park maintenance, including £10k contingency
  • £50k Earmarked reserve capital available for car park maintenance
  • £67,500 Projected annual electricity cost savings by year 5 (Option 3)
  • £2,476,542.63 Projected total 25-year value of Option 3
  • circa £55k Estimated extra cost of Option 3 over Option 2 for the new raised car port
  • £50k-£100k Possible additional cost range for heavy-duty surface preparation and unforeseen risk

Options considered

  • Rejected: Option 1: Retain existing car ports and use all available surfaces; cost £425,000. Very low solar potential due to suboptimal slope configuration
  • Rejected: Option 2: Remove existing car ports and use fully opened floor surface; cost £595,000. Lower yield and financial return than Option 3; shaded areas on level 9 not fully resolved
  • Chosen: Option 3: Remove car ports and add new raised car port on level 9; cost £640,000. Highest solar potential, shortest payback (circa 9.1 years), greatest 25-year return, plus covered storage
  • Rejected: Sale of energy to neighbouring businesses. Too complex compared to using solar power directly for the council's own use

Implications

  • Financial: Funded by existing approved budgets: £600k from the Capital Programme and £40k from earmarked reserve for car park maintenance. Report P40
  • Financial: Estimated annual electricity savings of £67,500 by year 5 and total 25-year return of £2,476,542.63 under Option 3.
  • Legal: Planning permission required for the new car port on level 9; District Network Operator consents also needed. No legal implications identified. Report P41
  • Equalities: No equality impacts associated with the proposal. Report P44
  • Climate: Estimated annual carbon savings of circa 215 tCO2e (Option 3), contributing to the council's Climate Change Strategy 2024-2028. Report P32, P43, P45
  • Risk: Key risks include vandalism, theft, structural engineer-imposed limitations, supply-chain delay, and grid-connection timing. Contracts must include retention payments and performance benchmarks. Report P42
  • Other: Could improve ICT power backup and support timed electric vehicle recharging at Phoenix House, while securing previously vandalised top levels of the car park.

Who and where

  • All wards of Mid Devon (the car park and Phoenix House serve the district council's operations) Report P11
  • Residents and visitors in the Phoenix Lane area of Tiverton, where the multi-storey car park is located Report P11
  • District Network Operator (National Grid) and other statutory consultees Report P41
  • Internal stakeholders including the ICT Operations Manager and Property Services Operations Manager
  • Neighbouring businesses (option of selling surplus energy was considered and ruled out)

Timeline

  • 15 December 2025: Sign-off by the Corporate Performance and Improvement Manager Report P49
  • 23 December 2025: Statutory sign-off by the s151 Officer, Monitoring Officer, and Chief Executive Report P46, P47, P48
  • 13 January 2026: Cabinet decision to approve Option 3 Report P2
  • Q1 2026: On-site works anticipated to commence in earnest
  • Q3 2026: Anticipated completion of installation
  • 25-year project lifetime: Period over which financial returns and carbon savings are projected

Plain English for the jargon

  • Solar PV: Solar photovoltaic panels that convert sunlight into electricity.
  • BESS: Battery Energy Storage System, storing electricity for use when generation is low.
  • tCO2e: Tonnes of carbon dioxide equivalent, a standard measure of greenhouse gas emissions.
  • DNO: District Network Operator, in this case National Grid, which manages the local electricity distribution network.
  • Permitted Development (PD): A type of planning consent granted automatically without needing a full planning application, subject to limits and conditions.
  • s151 Officer: The local authority officer with statutory responsibility for the proper administration of its financial affairs.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item95

Resolved

The Cabinet had before it a report * from the Deputy Chief Executive (S151) to consider the Phoenix Lane Solar and Battery Energy Storage System. RESOLVED that: The Phoenix Lane Solar and Battery Energy Storage System project as outlined within Option 3 be APPROVED . That delegated authority be granted to the Cabinet Member for Governance, Finance and Risk - in consultation with the Deputy Chief Executive s151 and the Head of Finance, Property and Climate Resilience - to deliver the Phoenix Lane Solar and Battery Energy Storage System project. Note: *Report previously circulated
Word for word from the decision Mid Devon published for this meeting. Source: democracy.middevon.gov.uk

Follow this further

Built from Mid Devon's papers

What the report saysPro

Report to Cabinet

Report for: Cabinet

Date of Meeting: 13 January 2026

Subject: Phoenix Lane Solar and Battery Energy Storage System

Cabinet Member: Cllr John Downes - Cabinet Member for Governance, Finance and Risk.

Responsible Officer: William Styles - Corporate Projects Officer.

Jason Ball - Climate and Sustainability Specialist.

Paul Deal - Head of Finance, Property and Climate Resilience.

Exempt: None.

which are Exempt from publication under paragraph 3, Part 1 of Schedule 12A to the Local

Government Act 1972 (as amended) as it contains information relating to the financial or business affairs of any particular person (including the authority holding that information)

Wards Affected: All

Enclosures: None.

Section 1 – Summary and Recommendation(s)

The Phoenix Lane Solar and Battery Energy Storage System project would install a solar photovoltaic (PV) array on the top levels of the Phoenix Lane multi-storey car park at Tiverton supported by a battery energy storage system (BESS).

Recommendation(s):

1. That Cabinet approves the Phoenix Lane Solar and Battery Energy Storage System project as outlined within Option 3.

2. That delegated authority be granted to the Cabinet Member for Governance, Finance and Risk - in consultation with the Deputy Chief Executive s151 and the Head of Finance, Property and Climate Resilience - to deliver the Phoenix Lane Solar and Battery Energy Storage System project.

Section 2 – Report

1.0Introduction 1.1 The project is to install a solar PV array on the top levels of the Phoenix Lane multi-storey car park in Tiverton with a battery energy storage system (BESS). This installation would provide the Council’s premises at Phoenix Lane with renewable power in line with its Corporate Plan and Climate Change Strategy.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Multi- Storey Solar ProjectReport 451 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

19 of 23 attended
LT
Cllr Luke Taylor Leader of the CouncilCommittee Member, apologies
DW
Cllr David Wulff Cabinet Member for Quality of Living, Equalities and Public HealthCommittee Member, present
NB
Cllr Natasha Bradshaw Cabinet Member for Environment and Climate ChangeCommittee Member, present
JD
Cllr John Downes Cabinet Member for Governance, Finance and RIskCommittee Member, present
GD
Cllr Gwen Duchesne MBE Cabinet Member for Parish and Community EngagementCommittee Member, present
MF
Cllr Matt Fletcher Cabinet Member for People DevelopmentCommittee Member, present
SK
Cllr Steve Keable Cabinet Member for Planning and Economic RegenerationCommittee Member, present
JL
Cllr Jane Lock Cabinet Member for Housing, Assets and Property ServicesCommittee Member, present
JW
Cllr Josh Wright Cabinet Member for Service Delivery and Continuous ImprovementCommittee Member, present
SW
Stephen WalfordOfficer, present
AJ
Andrew JarrettOfficer, present
DE
Dean EmeryOfficer, present

All 23 on the meeting page

On this subject at Mid Devon

Search all
  1. Multi- Storey Solar ProjectThis decision
  2. Multi Storey Car Park, Tiverton - Tender Outcome (00-53-17)Agreed
  3. Application 16/00015/mful - erection of an 83 bedroom premier inn hotel and integral restaurant with associated access and landscaping at multi storey car park, phoenix lane, tiverton ((2-04-58)Approved

More from Mid Devon Cabinet

All decisions
MeetingDecisionOutcome
1 Sep 2026 2027/28 Draft Budget Update (00:04:00)RESOLVED that: 1. The proposed approach to balancing the 2027/28 General Fund and Housing Revenue Account budget gaps... Approved Open
4 Aug 2026 Minutes of the Previous MeetingThe minutes of the previous meeting held on 07 July 2026 were APPROVED as a correct record and SIGNED by the Leader. ... Approved Open
4 Aug 2026 2026/27 Budget Monitoring- Quarter 1The Cabinet had before it a report * from the Deputy Chief Executive (S151) on the 2025/26 Budgeting Monitoring quart... Noted Open
4 Aug 2026 Air Source Heat Pump (ASHP) Contract 2026-2030The Cabinet had before it a report * from Head of Housing and Health on the Air Source Heat Pump (ASHP) Contract 2026... Decided Open
4 Aug 2026 Notification of Key DecisionsThe Cabinet had before it, and NOTED , the notification of Key Decisions *. Note: * Key Decisions previously circulated. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies