RESOLVED that the new three year Asbestos Surveying and Licensed Removal Contract be awarded to Contractor 3. (Proposed by Cllr R B Evans and seconded by Cllr B A Moore.) Reason for Decision : there was a need to confirm the award of the tender so that the specified work could be progressed. Note : *Report previously circulated, copy attached to minutes.
Word for word from the decision Mid Devon published for this meeting.Source: democracy.middevon.gov.uk
Asbestos Surveying and Licensed Removal 2021-2024, Award
Cabinet Member: Cllr Bob Evans, Cabinet Member for Housing & Property Responsible Officer: Mike Lowman, Repairs Manager
Reason for Report and Recommendations: To advise Members on the results for the tendering of the Asbestos Surveying and Licensed Removal 2021-2024 and confirm the award of the contract.
RECOMMENDATION: It is recommended that the new three year Asbestos Surveying and Licensed Removal Contract is awarded to Contractor 3
Financial Implications: The budget for the works is £60,000.00 per annum. The management of asbestos is a legal requirement, which will also result in lower revenue costs in in coming years and enable the Building Service to operate more effectively and manage future maintenance costs.
Legal Implications: We have a legal duty to manage asbestos and meet the Decent Homes Standard. The contract is a JCT Minor Works Contract 2016, combined with the specific contractual requirements.
Risk Assessment: The principal risk is failing to limit costs due to additional works. The performance of the contract shall be monitored monthly; corrective action will be taken where performance falls below Key Performance Indicator Targets. These include: 1) Customer satisfaction; 2) Variations and extras; 3) Number of defects; 4) Managing Health and Safety.
Equality Impact Assessment: All staff have received Equality and Diversity awareness training. MDDC discuss equality and diversity at the progress meetings and encourage the contractor to carry out awareness training.
Relationship to Corporate Plan: To contribute towards meeting the Decent and Affordable Homes target by making best use of the existing stock.
Impact on Climate Change: Investment in the MDDC stock will lower the amount of fossil fuels used to run and maintain the homes.
1.0Introduction
1.1The term of this contract is three years, with the option to terminate the contract at the end of each year subject to performance.
1.2Due to the nature and value of this procurement, the appropriate procedure was an open tender process. This means that anyone who expressed an interest in the contract would be invited to tender.
MDDC Report: Asbestos Surveying and Unlicensed Removal 2021-2024 1 1.3 To ensure quality of contractors, a number of minimum requirements were set out within the ITT. Any contractor failing to meet these would be disqualified.
2.0Procurement Process
2.1Licensed asbestos works are a particular category of asbestos removal works covered by the Control of Asbestos Regulations 2012 and can legally, only be carried out by a licensed contractor. By splitting out the licensed and unlicensed works within separate contracts we are aiming to make savings on the costs of these works.
2.2Expressions of interest were invited via a notice in the Supplying the South West Procurement Portal published on the 23 July 2020.
2.3Evaluation criteria set out in the ITT:
2.4Quality 60% Mobilisation of the works 20% Diversity, challenges and complaints 20% Works to void properties 10% Response to defects 10%
Price 40%
2.5Responses were required by midday on 4 September 2020.
2.6There were a total of 26 expressions of interest of which 9 submitted their tenders on time, but 1 was not complete, 2 opted out and 15 did not respond. The reason for opting out given by one contractor was that they were unable to be competitive; the other contractor did not provide a reason. Following the submission date, one contractor withdrew from the tender process.
2.7Evaluations were carried out during September and October 2020, by representatives from Mid Devon District Council’s Building Service.
2.8The price was based a schedule of rates within the tender. The lowest priced tender was awarded 40% and the higher priced tenders were awarded the percentage difference.
2.9The outcome of the evaluation is shown below:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
2027/28 Draft Budget Update (00:04:00)RESOLVED that: 1. The proposed approach to balancing the 2027/28 General Fund and Housing Revenue Account budget gaps...
Minutes of the Previous MeetingThe minutes of the previous meeting held on 07 July 2026 were APPROVED as a correct record and SIGNED by the Leader. ...
2026/27 Budget Monitoring- Quarter 1The Cabinet had before it a report * from the Deputy Chief Executive (S151) on the 2025/26 Budgeting Monitoring quart...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.