RESOLVED that the report be noted and that officers continue to explore funding opportunities for the next stages of the project. (Proposed by Cllr R J Chesterton and seconded by Cllr Mrs N Woollatt) Reason for Decision : to continue to move the project forward. Note : *Report previously circulated, copy attached to minutes
Word for word from the decision Mid Devon published for this meeting.Source: democracy.middevon.gov.uk
1. That Members note the contents of this report; and
2. That Officers continue to explore funding opportunities for the next stages of the project.
Financial implications
In May 2020, the partnership was successful in securing funding of up to £50k from the Department for Transport’s “Restoring your Railway” Ideas Fund. This funding has supported the development of the Strategic Outline Business Case (SOBC) referred to in more detail in the main body of the report. The “Restoring Your Railways – Ideas Fund” provides 75% of the cost of preparing the SOBC the remainder has been funded from existing budgets previously set aside for the project along with contributions from partners.
The SOBC is the first phase of work for any major transport infrastructure intervention and at the time of writing is in the process of being finalised and submitted to the Department for Transport (DfT). We can expect a decision in early 2021 by DfT on whether it is appropriate to progress to the next stage of the project and enter the next stage of the Rail Network Enhancements Pipeline described below.
The Government recently announced alongside its Comprehensive Spending Review its intention to invest in the railway network and Officers are working closely with the DfT in anticipation of a fourth round to the “New Stations Fund” in 2021. The third round having been expanded in November 2020.
In addition to the Strategic Outline Business Case other development works are necessary to support a bid to the New Stations Fund. For the Cullompton Station element it is estimated to cost approximately £200,000 to prepare the bid material MDDC Report Cullompton Railway Stations Project 1 V1 and complete other rail industry requirements. Officers are currently investigating external funding opportunities to finance this work as part of an integrated transport approach to facilitate the delivery of the Culm Garden Village.
The detailed capital costs of delivering a new station at Cullompton is currently unknown; however initial estimates would suggest that it would be in the order of £16 million. If the station reinstatement was supported by DfT through the New Stations Fund process the typical level of government contribution would be 75% of the delivery costs. This would leave a shortfall of approximately £4 million. Officers are currently investigating where these funds could be secured. It is likely that it would be through a combination of s106 contributions, partnership investment and other external funding mechanisms.
Budget and Policy Framework: The Strategic Outline Business Case has been funded primarily through the Restoring Your Railways fund alongside partner contributions including Mid Devon District Council from previously pledged and allocated funding within the budget for 2020/2021. Funds for future stages of the project have yet to be identified. Members however will be updated once a clearer idea of a possible funding package emerges.
The Mid Devon Local Plan 2013-2033 includes a site allocation for a Cullompton Railway Station. The Cullompton area is the largest focus for strategic growth in the Local Plan accommodating 50% of planned growth during the plan period. The station and service enhancement will form part of a wider multi modal approach to transport in and around Cullompton and the proposed garden village scheme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
2027/28 Draft Budget Update (00:04:00)RESOLVED that: 1. The proposed approach to balancing the 2027/28 General Fund and Housing Revenue Account budget gaps...
Minutes of the Previous MeetingThe minutes of the previous meeting held on 07 July 2026 were APPROVED as a correct record and SIGNED by the Leader. ...
2026/27 Budget Monitoring- Quarter 1The Cabinet had before it a report * from the Deputy Chief Executive (S151) on the 2025/26 Budgeting Monitoring quart...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.