RESOLVED that the new three year vinyl flooring renewal contract be awarded to Contractor 2. (Proposed by Cllr R B Evans and seconded by Cllr C R Slade) Reason for the decision - there was a need to confirm the award of the tender so that the specified work could be progressed Note : *Report previously circulated, copy attached to minutes.
Word for word from the decision Mid Devon published for this meeting.Source: democracy.middevon.gov.uk
Cabinet Member: Cllr Bob Evans, Cabinet Member for Housing & Property Responsible Officer: Mike Lowman Repairs Manager
Reason for Report and Recommendations: To advise Members on the results for the tendering of the Vinyl Flooring Renewal Contract 2021-2024 and confirm the award of the contract.
RECOMMENDATION: It is recommended that the new three year Vinyl Flooring Renewal Contract is awarded to Contractor 2
Financial Implications: The budget for the works is £200,000.00 per annum. The funding will come from the individual budgets to which the works apply. The contract will be administered on a call off basis, and only those works required will be carried out as per the schedule of rate prices within the tender.
Legal Implications: We have a legal duty to maintain our housing stock and meet the Decent Homes Standard. The contract is a JCT Measured Term Contract 2016, combined with the specific contractual requirements.
Risk Assessment: The principal risk is failing to limit costs due to additional works. The performance of the contract shall be monitored monthly; corrective action will be taken where performance falls below Key Performance Indicator Targets. These include: 1) Customer satisfaction; 2) Variations and extras; 3) Number of defects; 4) Managing Health and Safety.
Equality Impact Assessment: All staff have received Equality and Diversity awareness training. MDDC discuss equality and diversity at the progress meetings and encourage the contractor to carry out awareness training.
Relationship to Corporate Plan: To contribute towards meeting the Decent and Affordable Homes target by making best use of the existing stock.
Impact on Climate Change: The contractor is part of a recycling scheme for the existing vinyl sheet flooring that is removed, so reducing the amount of waste taken to landfill.
1.0Introduction
1.1The contract will deliver the renewal of vinyl sheet flooring to Council properties, supporting the Responsive Repairs Works, the Disabled Facilities Grant works and the Void process within Mid Devon during the financial years from 2021-2024.
1.2The term of this contract is three years, with the option to terminate the contract at the end of each year, subject to performance.
MDDC Report: Asbestos Surveying and Unlicensed Removal 2021-2024 1 1.3 Due to the nature and value of this procurement, the appropriate procedure was an open tender process. This means that anyone who expressed an interest in the contract would be invited to tender.
1.4To ensure quality of contractors, a number of minimum requirements were set out within the ITT. Any contractor failing to meet these would be disqualified.
2.0Procurement Process
2.1Expressions of interest were invited via a notice in the Supplying the South West Procurement Portal published on the 11 December 2020, with a closing date set at the 15 January 2021, but because we only received one submission by the original closing date, the contract was advertised again and the closing date extended to the 19 February 2021.
2.2We received 16 Expressions of Interest, 1 contractor opted out due to a lack of resource, 12 did not respond and 3 submitted a tender.
2.3Evaluation criteria set out in the ITT:
2.4Quality 60% Mobilisation of the works 20% Diversity, challenges and complaints 20% Product life expectancy and guarantees 10% Membership of trade organisations 5% Works to void properties
Price 40%
2.5Evaluations were carried out during February and March 2021, by representatives from Mid Devon District Council’s Building Service.
2.6The price was based a schedule of rates within the tender. The lowest priced tender was awarded 40% and the higher priced tenders were awarded the percentage difference.
2027/28 Draft Budget Update (00:04:00)RESOLVED that: 1. The proposed approach to balancing the 2027/28 General Fund and Housing Revenue Account budget gaps...
Minutes of the Previous MeetingThe minutes of the previous meeting held on 07 July 2026 were APPROVED as a correct record and SIGNED by the Leader. ...
2026/27 Budget Monitoring- Quarter 1The Cabinet had before it a report * from the Deputy Chief Executive (S151) on the 2025/26 Budgeting Monitoring quart...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.