RESOLVED that under Section 100A( 4) of the Local Government Act 1972 the public be excluded on the grounds that it involves the likely disclosure of exempt information as defined in paragraph 3 respectively of Part 1 of Schedule 12A of the Act, namely information relating to the financial or business affairs of any particular person (including the authority holding that information) Having discussed a number of business issues with regard to the tender process, the meeting moved back into open session. RESOLVED that: the Vinyl Flooring Contract be awarded to Supplier A with a forecast annual budget of £200,000. (Proposed by the Chairman) Note : * Report previously circulated, copy attached to minutes.
Word for word from the decision Mid Devon published for this meeting.Source: democracy.middevon.gov.uk
Cabinet Member: Cllr Ray Stanley Responsible Officer: Andrew Pritchard, Director of Operations
Reason for Report: To advise Cabinet of the outcome of the recent tender of the Vinyl Flooring Renewal 2017 – 2021 to Council houses and confirm the award of the contract.
RECOMMENDATION: It is recommended that Cabinet award the Vinyl Flooring Contract to Supplier A with a forecast annual budget of £200,000. Two tender opportunities were advertised and on both occasions only one compliant tender submission was received.
Both tenders were run on the basis of 60% price and 40% Quality.
Contracted Works: The contract will deliver the renewal of vinyl sheet flooring to Council properties, supporting the Responsive Repairs Works, the Disabled Facilities Grant works and the Void process within Mid Devon during the financial years from 2017-2021
Phase 1 Start 2 Oct 2017 Completion 31 March 2018 Phase 2 Start 1 April 2018 Completion 31 March 2019 Phase 3 Start 1 April 2019 Completion 31 March 2020 Phase 4 Start 1 April 2020 Completion 31 March 2021
Relationship to Corporate Plan: To contribute towards meeting the Decent and Affordable Homes target by making best use of the existing stock.
Financial Implications: The budget for this contract is £200,000 per annum, with year one pro-rata. The funding will come from the individual budgets to which the works apply. The contract will be administered on a call off basis, and only those works required will be carried out as per the schedule of rate prices within the tender.
Legal Implications: We have a legal duty to maintain the stock and meet the Decent Homes Standard. The conditions of engagement are based on a JCT Minor Works Building Contract 2016, combined with the contractual requirements. This provides a robust framework for managing and controlling the performance of the contractor to meet our legal obligations.
Risk Assessment: The principal risk is overspending against the annual budget as this is a call off contract driven by need.. The performance of the contract will be monitored monthly and corrective action will be taken, as necessary, where performance falls below Key Performance Indicator Targets. These include: 1) Financial Performance, 2) Customer satisfaction, 3) Variations and extras, 4) Number of defects; 5) Managing Health and Safety MDDC Report: Vinyl Flooring renewal 1 2017 – 2021 award 1 Introduction
1.1The term of this contract is 4 years subject to funding; with the option to terminate the contract at the end of each year subject to performance.
1.2Due to the nature and value of this procurement, the appropriate procedure was an open tender process. This means anyone who expressed an interest in the contract was invited to tender.
1.3To ensure the quality of contractors, a number of minimum requirements were set out within the ITT. Any contractor failing to meet these was disqualified.
2 Procurement Process
2.1Expressions of interest were invited through notices in the “Supplying the Southwest” Procurement Portal published on the 19th May 2017 and 23rd June 2017
2.2Evaluation criteria set out in the ITT:
Quality 40%
Ability to meet timescales for delivery Pass/Fail Management Structure and Method Statement 15% Subcontracting 10% Life Expectancy and guarantees 10% Trade Association Membership 5%
Price 60%
2.3Tender 1 was open to submissions from the 19th May 2017 to the 19th June 2017. A total of 17 expressions of interest; 3 submitted their tenders on time but 2 were disqualified for failing to meet the minimum requirements.
Tender 2 was open to submissions from 23rd June 2017 to the 28th July 2017. There were a total of 11 expressions of interest; only 1 submitted their tender on time.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
2027/28 Draft Budget Update (00:04:00)RESOLVED that: 1. The proposed approach to balancing the 2027/28 General Fund and Housing Revenue Account budget gaps...
Minutes of the Previous MeetingThe minutes of the previous meeting held on 07 July 2026 were APPROVED as a correct record and SIGNED by the Leader. ...
2026/27 Budget Monitoring- Quarter 1The Cabinet had before it a report * from the Deputy Chief Executive (S151) on the 2025/26 Budgeting Monitoring quart...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.