Mid Devon District Council
Cabinet, Thursday 13 May 2021 at 6.00pm

3 Rivers Developments Limited Update Report (1-1-42)

Decided Executive 1 paper

Cabinet decided this item on Thursday 13 May 2021. Below is the council's own wording, with the papers it was decided on.

Item15

Resolved

RESOLVED that the Audit Committee be requested to undertake a lessons learned review, providing a report to Cabinet on the financial and other impacts from the process followed for the sale of Park Road Nursery and recommending what improvements might be made in future. (Proposed by Cllr B A Moore and seconded by the Chairman) Reason for decision – so that improvements can be made to the process. Note : *Report previously circulated, copy attached to minutes.
Word for word from the decision Mid Devon published for this meeting. Source: democracy.middevon.gov.uk

Follow this further

Built from Mid Devon's papers

What the report saysPro

Report to Cabinet

CABINET 13 MAY 2021

3 Rivers Developments Limited - Performance Update as at 31/3/21

Cabinet Members: Councillor Bob Evans – Deputy Leader and Housing & Property Councillor Andrew Moore – Finance

Responsible Officers: Deputy Chief Executive (S151) – Andrew Jarrett

Reason for Report: To provide Cabinet an update on current project performance and any key risks.

RECOMMENDATION: That Cabinet note the update report on current performance and key risks.

Relationship to Corporate Plan: 3 Rivers Developments Limited’s (3Rivers) primary objective is to generate future returns in order to grow the business and to recycle monies made back to the Council to mitigate some of the cuts in Government funding.

Financial Implications: The Council has a duty to obtain value for money. All financial interactions between the Council and 3Rivers are carried out at commercially evidenced rates and subject to individual loan agreements.

Legal Implications: None to this report. However this report is prepared in accordance with the Shareholder Agreement, Company’s Memorandum and Articles of Association and currently Approved Business Plan.

Risk Assessment: Detailed within the report.

Equality impact assessment: No equality issues identified for this report.

Impact on climate change: 3Rivers is a commercial organisation and where deliverable sustainable options are available they are utilised; however, as a commercial organisation it is acknowledged that where there is a significant cost differential and what the market will sustain that this plays heavily in the choices made.

1.0Introduction

1.1This is now the 8th in a series of monthly updates on the progress of 3 Rivers since the recommendations made by the Cabinet at its meeting on the 13 July 2020. This report continues to provide the Council with a regular update on company performance, including associated risks and also gives a progress update on the recommendations made at the aforementioned Cabinet meeting.

3 Rivers Developments Ltd – Performance update March 2021 2.0 Company Update

2.1Attached to this report is the commercial company update provided by the Directors of 3Rivers Developments Limited for Cabinet’s consideration. In order to provide members and the public more insight into the company’s operations this report continues with the process of including an overarching part 1 summary of activities and a detailed part 2 report from the company.

2.2Below shows a brief overview of project progress and any associated issues as at the end of March 2021, which is the last full financial month of company accounting information.

Current Projects

The Orchard, Halberton – 4 semi-detached market houses and a barn conversion - the 4 semis are complete and 3 units are now occupied and viewings are still ongoing for the remaining one. Work is well under way on the new barn and is estimated to be completed by the end the beginning of June 2021.

St Georges Court, Tiverton – 39 market flats/houses – work is ongoing. Estimated completion of the whole project is planned for May 2022.

Bampton – 9 market houses. Pre-construction work is progressing well and start on site is estimated for July 2021.

Rental properties

Banksia Close/Cemetery Lodge, Tiverton – all rental payments up to date

Future Schemes

The company is currently considering 2 new developments; a medium sized development which is likely to be a mixed unit site and has recently made an offer on a medium sized site in Tiverton.

Financial Overview

No sales have been made since the last update.

3 Rivers Developments Ltd – Performance update March 2021 Project and Company Risk Analysis

This information is provided within the company report and reflects on changing markets, land availability, changes to the prevailing economic position, etc.

2.3The table below summarises all the major financial transactions that have been made between the company and the Council during 2020/21.

Financial transactions between 3Rivers and Mid Devon DC during 2020/21

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
3 Rivers Developments Limited Update Report (1-1-42)Report 221 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 36 attended
BD
Councillor Bob DeedAssociate Member, present
RC
Councillor Richard ChestertonCommittee Member, present
CD
Councillor Chris DawCommittee Member, present
BE
Councillor Bob EvansCommittee Member, present
DK
Councillor Dennis KnowlesCommittee Member, present
AM
Councillor Andrew MooreCommittee Member, present
CS
Councillor Colin SladeCommittee Member, present
NW
Councillor Nikki WoollattCommittee Member, present
SW
Stephen WalfordOfficer, in attendance
KT
Kathryn TebbeyOfficer, in attendance
MD
Maria De LeiburneOfficer, expected
AJ
Andrew JarrettOfficer, in attendance

All 36 on the meeting page

On this subject at Mid Devon

Search all
  1. 3 Rivers Developments Limited Update Report (1-1-42)This decision
  2. 3 Rivers Developments Limited - Business Plan 2023-2028 and associated Business CasesDecided
  3. 3 Rivers Developments Ltd Business Plan and the 3 Rivers project appraisal for development in Bampton and Park Road, TivertonAgreed
  4. 3 rivers developments ltd - business plan (0.12.059)Decided
  5. 3 Rivers Developments Limited – Funding RequestAgreed
  6. 3 Rivers Developments Limited – Funding Request (00:05:00)Agreed

More from Mid Devon Cabinet

All decisions
MeetingDecisionOutcome
1 Sep 2026 2027/28 Draft Budget Update (00:04:00)RESOLVED that: 1. The proposed approach to balancing the 2027/28 General Fund and Housing Revenue Account budget gaps... Approved Open
4 Aug 2026 Minutes of the Previous MeetingThe minutes of the previous meeting held on 07 July 2026 were APPROVED as a correct record and SIGNED by the Leader. ... Approved Open
4 Aug 2026 2026/27 Budget Monitoring- Quarter 1The Cabinet had before it a report * from the Deputy Chief Executive (S151) on the 2025/26 Budgeting Monitoring quart... Noted Open
4 Aug 2026 Air Source Heat Pump (ASHP) Contract 2026-2030The Cabinet had before it a report * from Head of Housing and Health on the Air Source Heat Pump (ASHP) Contract 2026... Decided Open
4 Aug 2026 Notification of Key DecisionsThe Cabinet had before it, and NOTED , the notification of Key Decisions *. Note: * Key Decisions previously circulated. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies