RESOLVED that: (1) That the Cabinet accepts the grant from the Public Sector Decarbonisation Scheme and agrees to implement the works to reduce the Council’s carbon emissions. (2) That the Cabinet agrees to approve and award the contract for the supply and installation of low energy efficient LED lighting to Contractor 1. (3) That the Deputy Chief Executive (S151) and the Deputy Leader and Cabinet Member for Housing and Property Services are given delegated authority to take all necessary actions to deliver the Salix funded projects as detailed in para 1.3, for any contract variations and approval of any necessary significant design changes. (Proposed by Cllr C R Slade and seconded by Cllr B A Moore) Reason for the decision – there is a need to deliver the three grant aided projects to reduce the carbon emissions of our facilities. Note : *Report previously circulated, copy attached to minutes.
Word for word from the decision Mid Devon published for this meeting.Source: democracy.middevon.gov.uk
(1) That the Cabinet accepts the grant from the Public Sector Decarbonisation Scheme and agrees to implement the works to reduce the Council’s carbon emissions.
(2) That the Cabinet agrees to approve and award the contract for the supply and installation of low energy efficient LED lighting to Contractor 1.
(3) That the Deputy Chief Executive (S151) and the Deputy Leader and Cabinet Member for Housing and Property Services are given delegated authority to take all necessary actions to deliver the Salix funded projects as detailed in para 1.3, for any contract variations and approval of any necessary significant design changes.
Financial Implications: These are detailed within the report on section 4.
Budget and Policy Framework: The cost for replacing end of life light fittings and heating plant have been identified within the capital and revenue budgets, under the 30-year maintenance programme for corporate property. This project is 100% funded by Salix and includes project support costs. Pursuant to section 31(4) of the Local Government Act 2003, the Minister of State determines that the grant will be paid subject to the conditions stated within the Salix agreements.
Legal Implications: The decarbonisation project will be carried out in accordance with the terms and conditions of the Grant agreement and its relevant schedules. The Council continues to liaise with Salix and provide regular progress reports. Procurement exercises have been conducted to comply with the Council’s policy and legal obligations, specifically in compliance with the Council’s Contract Procedure Rules and the Public Contracts Regulations 2015. The form of contract for the LED lighting will be JCT Intermediate Building Contract 2011 and our own standard terms and conditions 2019.
Contract Award for Carbon Decarbonisation Project v3 1 Risk Assessment: The main risk is in relation to the delivering the project within the allocated timeframe. Procurement has been undertaken in two parts, one for the air source heat pump installation by seeking three quotations and the other via competitive tender as outlined within this report.
Equality Impact Assessment: This report does not specifically highlight any equality implications; however, officers will continue to comply with the public sector equality duty as set out in Section 149 of the Equality Act 2010.
Relationship to Corporate Plan: Environment – Encourage retrofitting of measures to reduce energy use in buildings.
Impact on Climate Change: The projects will deliver significant savings on carbon emissions at very little direct cost. Successful delivery of the project not only signals the Council’s commitment to its climate emergency declaration in action, this will also demonstrate to Salix and central government that the Council can deliver projects to reduce carbon emissions within the district. The recommendations of the report are environmentally positive and will reduce the Council’s carbon footprint by up to 520 tonnes over the life of the new assets.
1.0Introduction
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
2027/28 Draft Budget Update (00:04:00)RESOLVED that: 1. The proposed approach to balancing the 2027/28 General Fund and Housing Revenue Account budget gaps...
Minutes of the Previous MeetingThe minutes of the previous meeting held on 07 July 2026 were APPROVED as a correct record and SIGNED by the Leader. ...
2026/27 Budget Monitoring- Quarter 1The Cabinet had before it a report * from the Deputy Chief Executive (S151) on the 2025/26 Budgeting Monitoring quart...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.