Mid Devon District Council
Cabinet, Tuesday 6 July 2021 at 10.00am

Contract Award for Carbon Decarbonisation Project (00-32-16)

Agreed Executive 1 paper

Cabinet agreed this item on Tuesday 6 July 2021. Below is the council's own wording, with the papers it was decided on.

Item34

Resolved

RESOLVED that: (1) That the Cabinet accepts the grant from the Public Sector Decarbonisation Scheme and agrees to implement the works to reduce the Council’s carbon emissions. (2) That the Cabinet agrees to approve and award the contract for the supply and installation of low energy efficient LED lighting to Contractor 1. (3) That the Deputy Chief Executive (S151) and the Deputy Leader and Cabinet Member for Housing and Property Services are given delegated authority to take all necessary actions to deliver the Salix funded projects as detailed in para 1.3, for any contract variations and approval of any necessary significant design changes. (Proposed by Cllr C R Slade and seconded by Cllr B A Moore) Reason for the decision – there is a need to deliver the three grant aided projects to reduce the carbon emissions of our facilities. Note : *Report previously circulated, copy attached to minutes.
Word for word from the decision Mid Devon published for this meeting. Source: democracy.middevon.gov.uk

Follow this further

Built from Mid Devon's papers

What the report saysPro

Report to Cabinet

Recommendation

(1) That the Cabinet accepts the grant from the Public Sector Decarbonisation Scheme and agrees to implement the works to reduce the Council’s carbon emissions.

(2) That the Cabinet agrees to approve and award the contract for the supply and installation of low energy efficient LED lighting to Contractor 1.

(3) That the Deputy Chief Executive (S151) and the Deputy Leader and Cabinet Member for Housing and Property Services are given delegated authority to take all necessary actions to deliver the Salix funded projects as detailed in para 1.3, for any contract variations and approval of any necessary significant design changes.

Financial Implications: These are detailed within the report on section 4.

Budget and Policy Framework: The cost for replacing end of life light fittings and heating plant have been identified within the capital and revenue budgets, under the 30-year maintenance programme for corporate property. This project is 100% funded by Salix and includes project support costs. Pursuant to section 31(4) of the Local Government Act 2003, the Minister of State determines that the grant will be paid subject to the conditions stated within the Salix agreements.

Legal Implications: The decarbonisation project will be carried out in accordance with the terms and conditions of the Grant agreement and its relevant schedules. The Council continues to liaise with Salix and provide regular progress reports. Procurement exercises have been conducted to comply with the Council’s policy and legal obligations, specifically in compliance with the Council’s Contract Procedure Rules and the Public Contracts Regulations 2015. The form of contract for the LED lighting will be JCT Intermediate Building Contract 2011 and our own standard terms and conditions 2019.

Contract Award for Carbon Decarbonisation Project v3 1 Risk Assessment: The main risk is in relation to the delivering the project within the allocated timeframe. Procurement has been undertaken in two parts, one for the air source heat pump installation by seeking three quotations and the other via competitive tender as outlined within this report.

Equality Impact Assessment: This report does not specifically highlight any equality implications; however, officers will continue to comply with the public sector equality duty as set out in Section 149 of the Equality Act 2010.

Relationship to Corporate Plan: Environment – Encourage retrofitting of measures to reduce energy use in buildings.

Impact on Climate Change: The projects will deliver significant savings on carbon emissions at very little direct cost. Successful delivery of the project not only signals the Council’s commitment to its climate emergency declaration in action, this will also demonstrate to Salix and central government that the Council can deliver projects to reduce carbon emissions within the district. The recommendations of the report are environmentally positive and will reduce the Council’s carbon footprint by up to 520 tonnes over the life of the new assets.

1.0Introduction

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Contract Award for Carbon Decarbonisation Project (00-32-16)Report 337 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 24 attended
BD
Councillor Bob DeedAssociate Member, present
RC
Councillor Richard ChestertonCommittee Member, present
CD
Councillor Chris DawCommittee Member, present
BE
Councillor Bob EvansCommittee Member, apologies
DK
Councillor Dennis KnowlesCommittee Member, present
AM
Councillor Andrew MooreCommittee Member, present
CS
Councillor Colin SladeCommittee Member, present
NW
Councillor Nikki WoollattCommittee Member, present
SW
Stephen WalfordOfficer, in attendance
JC
Jenny CliffordOfficer, expected
KT
Kathryn TebbeyOfficer, expected
MD
Maria De LeiburneOfficer, expected

All 24 on the meeting page

On this subject at Mid Devon

Search all
  1. Contract Award for Carbon Decarbonisation Project (00-32-16)This decision
  2. Award of Contract- The Laurels- Temporary AccommodationDecided
  3. Award of Gas Servicing Contract for 2026 - 2032 (01:01:08)Decided
  4. Award of Modernisation Contract for 2026-2030 (01:07:21)Decided
  5. Award of Replacement Roofing Programme Contract for 2026-2030 (01:10:05)Decided
  6. Award of Contract for the Air Source Heat Pump (ASHP) upgrades 2025/28Approved

More from Mid Devon Cabinet

All decisions
MeetingDecisionOutcome
1 Sep 2026 2027/28 Draft Budget Update (00:04:00)RESOLVED that: 1. The proposed approach to balancing the 2027/28 General Fund and Housing Revenue Account budget gaps... Approved Open
4 Aug 2026 Minutes of the Previous MeetingThe minutes of the previous meeting held on 07 July 2026 were APPROVED as a correct record and SIGNED by the Leader. ... Approved Open
4 Aug 2026 2026/27 Budget Monitoring- Quarter 1The Cabinet had before it a report * from the Deputy Chief Executive (S151) on the 2025/26 Budgeting Monitoring quart... Noted Open
4 Aug 2026 Air Source Heat Pump (ASHP) Contract 2026-2030The Cabinet had before it a report * from Head of Housing and Health on the Air Source Heat Pump (ASHP) Contract 2026... Decided Open
4 Aug 2026 Notification of Key DecisionsThe Cabinet had before it, and NOTED , the notification of Key Decisions *. Note: * Key Decisions previously circulated. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies