RESOLVED that the concept design contract for Cullompton Town Centre Public Realm Enhancement Design be awarded to Supplier 4. (Proposed by Cllr R J Chesterton and seconded by Cllr Mrs N Woollatt) Reason for the decision –there was a need to confirm the award of the tender to enable the specified work to be progressed Note : *Report previously circulated, copy attached to minutes.
Word for word from the decision Mid Devon published for this meeting.Source: democracy.middevon.gov.uk
REPORT OF THE HEAD OF PLANNING, ECONOMY AND REGENERATION.
Cullompton High Street Heritage Action Zone Public Realm Enhancement Project
Cabinet Member: Cllr Richard Chesterton Responsible Officer: [name removed], Head of Planning, Economy and Regeneration
Reason for Report and Recommendations: To advise Members on the results for the procurement of consultants on the Cullompton High Street Heritage Action Zone Town Centre Public Realm Enhancement Design.
RECOMMENDATION: It is recommended that the concept design contract for the Cullompton Town Centre Public Realm Enhancement Design is awarded to Supplier 4.
Relationship to Corporate Plan: The Cullompton High Street Heritage Action Zone project contributes to the corporate priorities of economic growth, empowering local communities and caring for the environment.
Financial Implications: Historic England has awarded a High Street Heritage Action Zone (HAZ) to Cullompton, following a successful bid by this Council. The administration of the HAZ programme of works rests with this Council through to March 2024 and includes public realm improvements around the Higher Bullring delivered in partnership with Devon County Council. Evaluation criteria set out in the tender document establishes that price forms 40% of the total score available.
Budget and Policy Framework: The cost of engaging consultants to deliver the Cullompton Town Centre Public Realm Enhancement design will be financed through High Street Heritage Action Zone agreed funding. A total of £60,000 has been budgeted for these works and the tender process has gone out on that basis.
Legal Implications: The contract will be let subject to the council standard terms and conditions for supply of services. The supplier referred to below is not identified – such information is confidential and not necessary to reach a decision. Any discussion which may identify a supplier should be treated as exempt information and must therefore be pre-empted by passing a resolution in accordance with Section 100A(4) of and Schedule 12A to the Local Government Act 1972, namely that such discussion would result in the disclosure of exempt information as defined in paragraph 3 of Part 1 of Schedule 12A of the said Act, being information relating to the financial or business affairs of any particular person (including the authority holding that information).
Risk Assessment: The tender process has assessed against a series of quality criteria as well as price in order to ensure that the successful contractor not only represents suitable value for money, but is also sufficiently experienced and suited to undertake the role.
MDDC Report: Asbestos Surveying and Unlicensed Removal 2021-2024 1 Equality Impact Assessment: The procurement was undertaken following all the Council’s policies and adheres to our quality process. No equality impacts are foreseen from the letting of the procurement contract.
Impact on Climate Change: One of the quality assessment criteria questions asked how suppliers would seek to ensure the design can support Mid Devon becoming carbon neutral by 2030. Answers to this question formed part of the overall assessment of tenders received.
1.0Introduction
1.1The procurement procedure selected was an open tender process. This means that anyone who expressed an interest in the Prior Information Notice would be invited to tender.
1.2The scope of work was for landscape/ public realm design services up to the Royal Institute of British Architects (RIBA) stage 3 (spatially coordinated design), to cover the town centre of Cullompton from the Higher Bullring through the Fore Street to the Lower Bullring.
1.3The scope of work was discussed with Devon County Council and Historic England to ensure their requirements were addressed as both delivery partners and funding partners respectively.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
2027/28 Draft Budget Update (00:04:00)RESOLVED that: 1. The proposed approach to balancing the 2027/28 General Fund and Housing Revenue Account budget gaps...
Minutes of the Previous MeetingThe minutes of the previous meeting held on 07 July 2026 were APPROVED as a correct record and SIGNED by the Leader. ...
2026/27 Budget Monitoring- Quarter 1The Cabinet had before it a report * from the Deputy Chief Executive (S151) on the 2025/26 Budgeting Monitoring quart...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.