Risk management was an integral part of the Council’s Corporate Governance arrangements and there was a statutory responsibility under the Account and Audit Regulations (2015) to put in place risk management arrangements. Note: *Report previously circulated.
Word for word from the decision Mid Devon published for this meeting.Source: democracy.middevon.gov.uk
Section 1 – Summary and Recommendation(s) To provide Members with a quarterly update on the Corporate Risk Register.
Recommendation(s): That Members review the Corporate Risk Register and feedback any areas of concern.
Section 2 – Report 1.0 Introduction 1.1 The Corporate Risk Register (CRR) contains the strategic risks which are most likely to impact the corporate priorities of the Council. It is reviewed at least quarterly by Heads of Service and the Leadership Team and updated as required. It is then presented to the Audit committee and to Cabinet. Risks are managed on the Council’s corporate performance and risk management system, SPAR. 1.2 The corporate risks are presented on a risk matrix (heat map), Appendix 1. Information on each risk is presented in a standard template, Appendix 2. These risks have been determined by the Council’s Leadership Team in consultation with Corporate Managers and other council officers.
2.0Summary of Corporate Risk 2.1 There are currently 17 risks on the CRR. Risks are presented with both their current and target risk ratings. Also included is a trend symbol indicating any change to the risk rating since the previous review. Risk Rating Risk Name Risk Owner Current Trend Target Culm Garden Village – Loss of CR1a Adrian Welsh 9 9 capacity funding Culm Garden Village – Delay/ CR1b impact to project arising from Adrian Welsh 15 15 infrastructure delays CR2 Cyber Security Brian Trebilcock 20 15 Failure to meet Climate CR3 Paul Deal 15 9 Change Commitments by 2030 CR4 Homes for Ukraine Scheme Simon Newcombe 4 9 CR5 Information Security Lisa Lewis 12 8 CR7 Financial Sustainability Paul Deal 16 12 Quality of Planning Committee CR8 Decisions Richard Marsh 6 3 Reputational Impact of 3 CR9a Rivers Stephen Walford 3 2 Cullompton Town Centre Relief CR10 Road Adrian Welsh 15 15
CR11 Cost of Living Crisis Dean Emery 16 16 CR12 Housing Crisis Simon Newcombe 12 9 CR15 Corporate Property Fire Safety Stephen Walford 9 6 Building Control Service CR16 viability Andrew Howard 12 2 Severe Weather Emergency CR17 Recovery Simon Newcombe 12 9
CR18 Housing Rent Error Correction Simon Newcombe 8 New 3 Devolution and Local CR19 Stephen Walford 20 New 15 Government Reorganisation
Risk rating change since previous update: Increased No change Decreased
2.2For each risk the following information is given in Appendix 2: Risk name Risk description Current risk severity and likelihood Current risk rating Risk Owner Risk Type Mitigating actions (including name, description, responsible officer, current effectiveness and when it was reviewed) Notes.
2.3Since this report was last published in December 2024, the following significant changes have been made to the CRR: The risk rating of CR1a Culm Garden Village – Loss of capacity funding has been reduced from 12 to 9. The risk rating of CR8 Quality of Planning Committee Decisions has been reduced from 9 to 6. Corporate Risk 9 “SPV – 3 Rivers – Delivery of Closedown Plan” has been removed from the CRR and will no longer be reported on. All relevant actions have been completed, including the closedown process CR13 Operation of a Waste Management Service, and CR14 Workforce Shortage: These risks have been effectively managed and as such they have been removed from the CRR and will no longer be reported on. CR18 Housing Rent Error Correction has been added to the CRR. CR19 Devolution and Local Government Reorganisation has been added to the CRR.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
2027/28 Draft Budget Update (00:04:00)RESOLVED that: 1. The proposed approach to balancing the 2027/28 General Fund and Housing Revenue Account budget gaps...
Minutes of the Previous MeetingThe minutes of the previous meeting held on 07 July 2026 were APPROVED as a correct record and SIGNED by the Leader. ...
2026/27 Budget Monitoring- Quarter 1The Cabinet had before it a report * from the Deputy Chief Executive (S151) on the 2025/26 Budgeting Monitoring quart...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.