AI summaryMid Devon Cabinet noted the quarterly update on the Corporate Risk register; no direct financial implications were identified in the decision.
Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet noted the Corporate Risk report
MoneyNo direct financial implicationsUnmitigated risks may have financial implications
What happens nextNot stated
Who it affectsNot stated
What was decided
Cabinet noted the report from the Corporate Performance and Improvement Manager and the Head of People, Performance & Waste on the Corporate Risk.
Why
The item was presented as the quarterly update on the Council's Corporate Risk register.
Implications
Financial: No direct financial implications arose from the report, though risks which were not mitigated may have financial implications for the Council, and the treatment of risk may require resources to be reallocated.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item51
Resolved
Cabinet had before it and NOTED a report * from the Corporate Performance and Improvement Manager and the Head of People, Performance & Waste on the Corporate Risk. Note: *Report previously circulated There were no direct financial implications arising from this report. However, risks which were not mitigated, may have financial implications for the Council. Equally, the treatment of risk may require resources to be (re)allocated. Note: *Report previously circulated
Word for word from the decision Mid Devon published for this meeting.Source: democracy.middevon.gov.uk
Section 1 – Summary and Recommendation(s) To provide Members with a quarterly update on the Corporate Risk Register.
Recommendation(s): That Cabinet Members review the Corporate Risk Register and feedback any areas of concern.
Section 2 – Report 1.0 Introduction 1.1 The Corporate Risk Register (CRR) contains the strategic risks which are most likely to impact the corporate priorities of the Council. It is reviewed at least quarterly by Heads of Service and the Leadership Team and updated as required. It is then presented to the Audit committee and to Cabinet. Risks are managed on the Council’s corporate performance and risk management system, SPAR. 1.2 The corporate risks are presented on a risk matrix (heat map), Appendix 1. Information on each risk is presented in a standard template, Appendix 2. These risks have been determined by the Council’s Leadership Team in consultation with Heads of Service and other Council officers.
2.0Summary of Corporate Risk 2.1 There are currently 17 risks on the CRR. Risks are presented with both their current and target risk ratings. Also included is a trend symbol indicating any change to the risk rating since the previous review. Risk Rating Risk Name Risk Owner Current Trend Target Culm Garden Village – Group Manager for CR1a 9 9 Loss of capacity funding GED Culm Garden Village – Delay/ impact to project Group Manager for CR1b arising from GED 15 15 infrastructure delays ICT Operations CR2 Cyber Security 20 15 Manager Failure to meet Climate Head of Finance, CR3 Change Commitments Property & Climate 15 9 by 2030 Resilience Homes for Ukraine Head of Housing & CR4 Scheme Health 4 9 Head of Digital CR5 Information Security Transformation & 12 8 Customer Engagement Head of Finance, CR7 Financial Sustainability Property & Climate 25 12 Resilience Quality of Planning Director of Place & CR8 Committee Decisions Economy 9 3 Cullompton Town Group Manager for CR10 Centre Relief Road GED 15 15 Head of Revenues, CR11 Cost of Living Crisis Benefits & Leisure 16 16 Head of Housing & CR12 Housing Crisis Health 12 9 Corporate Property Fire CR15 Safety Chief Executive 9 6 Building Control Service Building Control CR16 viability Manager 12 2 Head of Housing & CR17 Emergency Recovery Health 8 4 Housing Rent Error Head of Housing & CR18 Correction Health 8 3 Devolution and Local CR19 Government Chief Executive 20 15 Reorganisation Emergency Planning Head of Housing & CR20 8 New 4 Response Health
Risk rating change since previous update: Increased No change Decreased 2.2 For each risk the following information is given in Appendix 2: Risk name Risk description Current risk severity and likelihood Current risk rating Risk Owner Risk Type Mitigating actions (including name, description, responsible officer, current effectiveness and when it was reviewed) Notes.
2.3Since this report was last published in June 2025, the following significant changes have been made to the CRR: CR7 Financial Sustainability: Risk Rating has increased from 16 to 25 in light of local government funding announcements. CR8 Quality of Planning Decisions: Risk Rating has increased from 6 to 9, reflecting the fact that the Local Plan is out of date. CR17 Severe Weather Emergency Recovery has been redrafted and widened out to Emergency Recovery. Risk Rating reduced from 12 to 8. CR20 Emergency Planning Response was added to the CRR in August 2025.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
2027/28 Draft Budget Update (00:04:00)RESOLVED that: 1. The proposed approach to balancing the 2027/28 General Fund and Housing Revenue Account budget gaps...
Minutes of the Previous MeetingThe minutes of the previous meeting held on 07 July 2026 were APPROVED as a correct record and SIGNED by the Leader. ...
2026/27 Budget Monitoring- Quarter 1The Cabinet had before it a report * from the Deputy Chief Executive (S151) on the 2025/26 Budgeting Monitoring quart...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.