RESOLVED that: 1. Delegated authority be given to the Deputy Chief Executive (S151) to progress the works as planned. Noting that, any subsequent specific spend or contractual awards in line with key decisions thresholds would be brought ... view the full minutes text for item 21.
Word for word from the decision Mid Devon published for this meeting.Source: democracy.middevon.gov.uk
Cabinet Member: Cllr Josh Wright, Cabinet Member for Service Delivery and Continuous Improvement
Responsible Officer: Andrew Jarrett, Deputy Chief Executive (S151)
Exempt: N/A
Wards Affected: All
Enclosures: Appendix 1 – Site Plan for proposed changes Appendix 2 – Indicative New Office complex option
Section 1 – Summary and Recommendation(s) To present proposals to remodel the waste depot to meet new Environment Agency permit regulations and requirements, and enable the service to accommodate increased volumes and waste types as well as have the capacity to further increase its recycling portfolio.
This report seeks approval for the high-level plan with delegation sought to progress the set out schedule, specify the detail and subsequently implement the changes.
Recommendation(s): That Cabinet consider the proposed remodelling of the site, and 1. Give delegated authority to the Deputy Chief Executive (S151) to progress the works as planned. Noting, any subsequent specific spend or contractual awards in line with key decisions thresholds will be brought back to Cabinet for agreement. 2. Agree the purchase of a new Modular Office complex, to be specified, up to the value of £250k. 3. Agree the alignment of the leases of the various existing units to end on the same date as that recently agreed for the new car park site – 7 November 2039. Section 2 – Report 1.0 Introduction
1.1The Environment Agency (EA) announced on the 18 December 2024 that it has consolidated 28 existing “standard rules permits” into 8 new “standard rules permits”. These changes come into force on 19 June 2026. This update aims to streamline permitting processes and aligns them with modern standards.
1.2To meet the new requirements some significant changes are required to the Waste Depot; the main changes being certain elements of Waste and Recycling require storing undercover, that the recyclate is securely stored and with some recycling materials needing to be baled. This demands that the service have sufficient capacity and space to ensure service delivery is legally compliant. This requires a new building to house the materials.
1.3The proposals regarding the remodelling of the site will also help increase our storage capacity at Carlu regarding recycling materials. This will include a considerable increase in our undercover storage capacity, which will allow the housing of extra baled bay areas. This will give us the future provision to store flexible/soft plastics, disposable nappies and other potential recycling initiatives.
1.4This is vital to help the Council further build on and sustain the excellent performance it has achieved regarding enhancing its recycling rate and reducing its residual tonnage over the last two years. This work has seen Mid Devon catapulted into the top 5% of national performance as well as gain recognition from OFLOG and be shortlisted for a national LGC award.
1.5A paper setting out the proposed future direction of travel and appetite regarding additional recycling activity will be taken to the next Service Delivery and Continuous Improvement PDG in September. This will then inform the future permit variation application that will be required to be sent to the EA regarding the remodelling exercise so future changes are processed in the same submission (thus saving time and expense).
1.6This report outlines at a high level the plans to remodel the depot to meet the permit requirements and enhance and future proof the operation. The Council has a firm deadline of 19 June 2026 to meet the new regulatory guidance. Following approval of the plans that are presented in this paper, subsequent planning, building and preparation work is required over the coming 10-month period to ensure everything is in place well before the deadline.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
2027/28 Draft Budget Update (00:04:00)RESOLVED that: 1. The proposed approach to balancing the 2027/28 General Fund and Housing Revenue Account budget gaps...
Minutes of the Previous MeetingThe minutes of the previous meeting held on 07 July 2026 were APPROVED as a correct record and SIGNED by the Leader. ...
2026/27 Budget Monitoring- Quarter 1The Cabinet had before it a report * from the Deputy Chief Executive (S151) on the 2025/26 Budgeting Monitoring quart...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.