Cabinet, Tuesday 2 December 2025 at 5.15pm

Waste Depot Remodelling- Update

Decided Executive 1 paper

AI summaryMid Devon Cabinet approves Contractor 1 for the Carlu waste depot Civils Contract, as part of a £1,800k remodelling needed to meet new Environment Agency permit rules by 19 June 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedPreferred bidder for weighbridge, fuelling station, wash-down area
Money£1,800k total projectCivils Contract element estimated at £450k
What happens nextWorks start 12 January 2026Lasting approximately 4 months on site
Who it affectsAll wards in Mid DevonWaste and recycling collection service

What was decided

Cabinet approved the Civils Contract award to Contractor 1 for the new weighbridge, fuelling station and wash-down area at Carlu Close Waste Depot. Report P11, P38

Cabinet noted progress on the wider Carlu Close depot remodelling and delegated authority to the S151 Officer to complete the Civils Contract award, in consultation with the relevant Cabinet Member. Report P11

Why

The Environment Agency changed waste permit rules, with the statutory application deadline set for 19 June 2026; the depot works are needed to comply and to handle increased recycling volumes. Report 1.1

Contractor 1 scored highest in the tender evaluation at 86.13%, ahead of nine other bidders, with the award assessed 40% on price and 60% on quality. Report 3.5, P38

What happens next

The new office complex and Grounds Maintenance service will complete their move, freeing space for the main structural and Civils works to begin on 12 January 2026. Report P20, P21, 4.1

The council will apply for the new Environment Agency permit well before the 19 June 2026 deadline, with further tenders for bay wall extensions and the new storage building to follow. Report P16, P18

The money

  • £50k Relocating Ground Maintenance and Welfare Units (estimated, unchanged from July) Report P30
  • £250k Purchasing new modular Office complex (estimated, unchanged from July) Report P30
  • £450k Groundworks and new weighbridge, fuel station and wash-down area (current estimate, up from £400k) Report P30
  • £400k Extension to Recycling Transfer Station (current estimate, down from £500k; paid via lease uplift) Report P30
  • £250k New Storage Building (estimated, unchanged from July) Report P30
  • £100k Extending the bay walls (estimated, unchanged from July) Report P30
  • £100k Other Costs (estimated, unchanged from July) Report P30
  • £100k Contingency (estimated, unchanged from July) Report P30
  • £1,800k Total current estimated project cost (up from £1,750k in July) Report P30
  • £1,381k 2025/26 Extended Producer Responsibility grant allocation funding the project
  • £53k pa Annual cost of the new lease on the car park unit (excluded from the £1,800k total) Report P30

Options considered

  • Chosen: Award the Civils Contract to Contractor 1 (preferred bidder, 86.13%). Highest combined price and quality score among ten evaluated tenders Report P38
  • Rejected: Continue to use the existing weighbridge location for welfare units. Decision taken to re-site existing welfare units to free up space and avoid relocating the weighbridge Report P22

Implications

  • Legal: The Environment Agency published legal guidance that waste and recycling services must meet; non-compliant recycling services risk disruption. Report 1.1, P43
  • Financial: Project costs are within the 2025/26 Capital Programme, funded mainly by the Extended Producer Responsibility grant; increased recycling should lower residual waste costs and boost income. Report P43
  • Risk: Risks span health and safety, finance, failure to secure the permit, and contractor and internal resource availability; managed via a risk log reviewed by the Project Board. Report P43
  • Climate: Solar panels on the new roof, additional EV charging points and a well-insulated office complex will be included to support net zero aims. Report P43
  • Staffing: Some unavoidable service disruption is expected during the works; much of the project will be cordoned off and out-of-hours working used where possible. Report 2.3
  • Other: No equalities issues were identified for this report. Report P43

Who and where

  • Households and businesses across all Mid Devon wards receiving waste and recycling collections Report P8, P43
  • Mid Devon Waste and Recycling collection staff and Grounds Maintenance staff Report P20, P21
  • The landlord of the Carlu Close site, who will own the new Recycling Transfer Station extension Report P17

Timeline

  • 18 December 2024: Environment Agency announced waste permit rule changes Report 1.1
  • 8 July 2025: Cabinet previously agreed the proposed remodelling changes Report 1.1, P53
  • 10 September 2025: Open tender notice published and Invitation to Tender issued via ProContract Report 3.2
  • 17 October 2025: Tender return deadline Report 3.2
  • November 2025: Tender evaluations carried out by Property Services and Horizon Consulting Engineers Report 3.6
  • 18 November 2025: Statutory officers signed off the report via Leadership Team Report P45, P46, P47, P48
  • 2 December 2025: Cabinet considered the report and approved the Civils Contract award Report P2, P11
  • Week commencing 15 December 2025: New office complex expected to complete and Grounds Maintenance service to relocate Report P20
  • 12 January 2026: Civils works and Recycling Transfer Station extension works expected to start on site Report P17, P21
  • 19 June 2026: Statutory deadline to apply for the new Environment Agency permit Report 1.1
  • 9 June 2039: Aligned end date for leases of the various units on the site Report P26

Plain English for the jargon

  • Civils Contract: The contract covering groundworks and installation of the new weighbridge, fuelling station and wash-down area at the depot.
  • EA: Environment Agency, the regulator setting new waste permit rules.
  • Extended Producer Responsibility grant: Government funding paid to councils to cover the cost of recycling packaging, based on producer payments.
  • WEEE: Waste Electrical and Electronic Equipment, to be stored in the new building.
  • Carlu Close Depot: Mid Devon's main waste and recycling depot, the subject of this remodelling project.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item88

Resolved

The EA published legal guidance that Waste and Recycling services needed to both abide to and meet for its collection services to be permitted and carried out. Recycling services that did not comply with this guidance may be disrupted
Word for word from the decision Mid Devon published for this meeting. Source: democracy.middevon.gov.uk

Follow this further

Built from Mid Devon's papers

What the report saysPro

Report to Cabinet

Report for: Cabinet

Date of Meeting: 2 December 2025

Subject: Waste Depot Remodelling – Update

Cabinet Member: Cllr Josh Wright, Cabinet Member for Service Delivery and Continuous Improvement Cllr Jane Lock, Cabinet Member for Housing, Assets and Property Services

Responsible Officer: Andrew Jarrett, Deputy Chief Executive (S151)

Exempt: Annex A – Part II

which are Exempt from publication under paragraph 3, Part 1 of Schedule 12A to the Local Government Act 1972 (as amended) as it contains information relating to the financial or business affairs of any particular person (including the authority holding that information)

Wards Affected: All

Enclosures: Annex A – Part II (Contractor details and pricing submission)

Section 1 – Summary and Recommendation(s) To present a progress update on the remodelling project at the Carlu waste depot, necessary to meet new Environment Agency permit regulations and requirements and enable the service to accommodate increased volumes of recycling and enable new collections to be trialled in 2026, future proofing the service. Also to approve the preferred bidder to fit the new weighbridge, fuel station and washdown area (“Civils Contract”).

Recommendation(s): That Cabinet: 1. Note the progress made to date with the planned remodelling of the Carlu Close Depot; 2. Approve the contract award for the installation of a new Weighbridge, fuelling station and wash-down area at the Carlu Close Waste Depot, to Contractor 1. 3. Delegate authority to the S151 Officer (in consultation with the Cabinet Member for Housing, Assets and Property Services) to complete the “Civils Contract” award. Section 2 – Report 1.0 Introduction

1.1The Environment Agency (EA) announced on the 18 December 2024 that the rules surrounding waste permits were changing from 19 June 2026. To meet these statutory requirements, several changes are required at our Carlu waste depot. At the same time, the proposed changes will offer increased capacity and enable the service to trial potential new recycling collections in 2026, future proofing the service. The proposed changes were agreed at the Cabinet meeting in July 2025. This report gives an update on the progress to date.

1.2As part of the changes, a new weighbridge, fuel station and washdown area are being commissioned. Given the scale of the contract, this is a key decision and in line with the July approval, the award of the contract to the preferred bidder is being brought back for specific approval.

2. Update on the Planned Works

2.1As outlined in July, there are a minimum set of works required to enable the Council to meet the permit requirements. The specification of the required works is backed by independent external advice. At a broad high-level, the minimum requirements and progress to date are:

Task Update 1 Raise Bay walls in the Recycling Transfer Specification for the work is being Station to allow one metre of “free board” at drawn up with technical support. the end and above the materials stored, Contract will be tendered in due making them sufficiently fireproof to contain course. the fire for 2 hours.

2 The Recycling Transfer Station to be Planning permission submitted and extended to allow for storage bays for baled decision expected before the end of products, with associated fire protection and the calendar year. Contractor water management – this requires planning appointed by landlord and works approval, and the landlord is progressing this expected to start on site 12 January and will undertake the build as it will remain 2026 lasting approximately 4 months. in their ownership after the lease expires.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Waste Depot Remodelling- UpdateReport 510 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 24 attended
LT
Cllr Luke Taylor Leader of the CouncilCommittee Member, apologies
JL
Cllr Jane Lock Cabinet Member for Housing, Assets and Property ServicesCommittee Member, present
NB
Cllr Natasha Bradshaw Cabinet Member for Environment and Climate ChangeCommittee Member, present
JD
Cllr John Downes Cabinet Member for Governance, Finance and RIskCommittee Member, present
GD
Cllr Gwen Duchesne MBE Cabinet Member for Parish and Community EngagementCommittee Member, present
MF
Cllr Matt Fletcher Cabinet Member for People DevelopmentCommittee Member, present
SK
Cllr Steve Keable Cabinet Member for Planning and Economic RegenerationCommittee Member, apologies
JW
Cllr Josh Wright Cabinet Member for Service Delivery and Continuous ImprovementCommittee Member, present
DW
Cllr David Wulff Cabinet Member for Quality of Living, Equalities and Public HealthCommittee Member, present
SW
Stephen WalfordOfficer, present
AJ
Andrew JarrettOfficer, present
PD
Paul DealOfficer, present

All 24 on the meeting page

On this subject at Mid Devon

Search all
  1. Waste Depot Remodelling- UpdateThis decision
  2. Waste Depot Remodelling (50:00)Decided

More from Mid Devon Cabinet

All decisions
MeetingDecisionOutcome
1 Sep 2026 2027/28 Draft Budget Update (00:04:00)RESOLVED that: 1. The proposed approach to balancing the 2027/28 General Fund and Housing Revenue Account budget gaps... Approved Open
4 Aug 2026 Minutes of the Previous MeetingThe minutes of the previous meeting held on 07 July 2026 were APPROVED as a correct record and SIGNED by the Leader. ... Approved Open
4 Aug 2026 2026/27 Budget Monitoring- Quarter 1The Cabinet had before it a report * from the Deputy Chief Executive (S151) on the 2025/26 Budgeting Monitoring quart... Noted Open
4 Aug 2026 Air Source Heat Pump (ASHP) Contract 2026-2030The Cabinet had before it a report * from Head of Housing and Health on the Air Source Heat Pump (ASHP) Contract 2026... Decided Open
4 Aug 2026 Notification of Key DecisionsThe Cabinet had before it, and NOTED , the notification of Key Decisions *. Note: * Key Decisions previously circulated. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies