Draft Budget Report 2026/2027 (6:35)

Deferred Executive 5 papers

AI summaryMid Devon Cabinet approves only Green-rated budget savings and pressures for 2026/27, defers Red options to next meeting, leaving a forecast shortfall of £942k to £3,446k.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDeferredAmber and Red options deferred or rejected
MoneyShortfall £942k to £3,446kGeneral Fund after Green savings only
What happens nextRed options to next CabinetFurther savings to be considered
Who it affectsAll wards, council tenantsGeneral Fund and Housing Revenue Account

What was decided

Cabinet approved the Green pressures on the General Fund in Appendix 1, after an amendment removed Amber options from the recommendation. Report P11

Cabinet approved only the Green savings options for the General Fund (Appendices 2 and 3) and for the Housing Revenue Account (Appendix 4), again with Amber removed by amendment. Report P11

Cabinet deferred consideration of the Red risk and deliverability pressures and savings in Appendices 1 to 4 to its next meeting. Report P11

Why

The Medium Term Financial Plan shows a forecast General Fund shortfall of between £846k and £3,350k in 2026/27, driven by inflation and possible cuts in grant funding. Report 1.2

The Housing Revenue Account has a forecast shortfall of £546k in 2026/27, rising to £1,796k by 2028/29 if no action is taken. Report 1.3

Officers and Policy Development Groups generally did not support Red-rated savings, and the Service Delivery and Continuous Improvement PDG did not wish to use stretched Amber options either. Report P35, P41, P44

What happens next

Red risk pressures and savings will be brought back to the next Cabinet meeting for decision. Report P11

Policy Development Groups will be asked to identify further savings and report back to Cabinet to close the remaining General Fund and HRA shortfalls. Report P11

Updates to the draft budget will go through November PDG meetings and Cabinet in the run up to Full Council setting the budget on 18 February 2026. Report 4.6

The money

  • £846k to £3,350k Initial forecast General Fund shortfall range for 2026/27 Report 1.2
  • £546k Initial forecast Housing Revenue Account shortfall for 2026/27 Report 1.3
  • £1,796k Forecast cumulative HRA shortfall by 2028/29 without action Report 1.3
  • £1,513k Green and Amber emerging budget pressures added Report P26
  • £1,417k Total Green and Amber savings options identified Report P27
  • £1,015k Revised forecast General Fund shortfall under Option 1a after Green and Amber savings Report P28
  • £942k Revised forecast General Fund shortfall under Option 1b after Green and Amber savings Report P28
  • £3,446k Revised forecast General Fund shortfall under Option 1c after Green and Amber savings Report P28
  • £69k Revised HRA forecast shortfall after Green and Amber savings Report P60
  • £2m Target minimum balance for General Reserves Report 4.4

Options considered

  • Rejected: Approve Green and Amber pressures and savings (officer recommendation). Amendment removed Amber from all four recommendations Report P11, P20
  • Chosen: Approve Green pressures and Green savings only (Leader's amendment). Amendment carried by vote
  • Rejected: Decide on Red risk pressures and savings in Appendices 1 to 4. Deferred to next Cabinet meeting Report P11
  • Rejected: Replace Green Option 1 with stretched Amber Option 2 savings. Service Delivery and Continuous Improvement PDG did not support the stretched options Report P35

Implications

  • Financial: Even after Green and Amber savings, a revised shortfall of £942k to £3,446k remains on the General Fund and £69k on the HRA for 2026/27. Report P28, P60
  • Financial: Officers warn that a draw from reserves may be required, and a full review of Earmarked Reserves will be needed to keep a minimum General Reserve balance of £2m. Report 4.4
  • Legal: The Council has a legal duty to set a balanced budget and keep overall costs affordable. Report 1.4
  • Risk: The Autumn Budget is now set for 26 November, meaning the local funding settlement may arrive later and with greater uncertainty.
  • Staffing: Some savings depend on reducing staff through natural turnover only and cannot be guaranteed, and any agreed staffing savings will stretch service delivery. Report 2.4
  • Climate: The allocation of resources will affect the Council's ability to fund new climate change activity, although some provision is already in the base budget. Report P68

Who and where

  • All wards in Mid Devon Report P7
  • Council tenants and the Housing Revenue Account Report 3.1, 3.3
  • Council tax payers across the district
  • Service users facing potential reductions in service provision Report 2.4, 4.2
  • Partner organisations approached to take space in Phoenix House Report P48, P49

Timeline

  • 2 September 2025: First draft MTFP for 2026/27 to 2028/29 presented to Cabinet Report 1.2, P77
  • 23 September 2025: Statutory officers signed off the report via Leadership Team Report P70, P71, P72
  • 7 October 2025: Cabinet considered the Draft Budget Report 2026/27 and approved the Leader's amendment Report P2
  • November 2025: Further draft budget updates to go through PDGs and Cabinet, around the 26 November Autumn Budget Report 4.6
  • Next Cabinet meeting: Red risk pressures and savings to be considered
  • 18 February 2026: Full Council to agree the 2026/27 budget Report 4.6

Plain English for the jargon

  • General Fund: The main council account for day to day services, funded by council tax, business rates and government grants.
  • Housing Revenue Account (HRA): A ring fenced account that records all income and spending on the Council's own housing stock.
  • Medium Term Financial Plan (MTFP): A multi year forecast of the Council's spending and funding, used to plan how the budget will be balanced.
  • RAG rating: A Red, Amber, Green system used to show the level of risk attached to a budget option.
  • Policy Development Group (PDG): A committee of councillors that reviews draft budget options for their service area before Cabinet decides.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item49

Resolved

The Cabinet had before it a report * from the Deputy Chief Executive (S151) Officer and the Head of Finance, Property and Climate Resilience on the draft Budget 2026/27. The Leader of the Council moved an AMENDMENT that ‘and Amber’ be removed from recommendation 1,2,3 and 4 and recommendation 5 be deferred to the next Cabinet meeting. Upon a vote being taken the AMENDMENT was declared to have been CARRIED. RESOLVED that: The Green pressures on the General Fund within Appendix 1 be AGREED . The Green savings options for the General Fund for services reporting directly into the Cabinet, as shown within Appendix 2 be AGREED . The Green savings options for the General Fund for services reporting into the five Policy Development Groups Cabinet within Appendix 3, taking into account the recommendations from the Policy Development Groups as noted in paragraph 2.11 be AGREED. The Green savings options for the Housing Revenue Account within Appendix 4, taking into account the recommendations from the Homes Policy Development Group as noted in paragraph 2.11 be AGREED. The pressures / savings options with a Red risk/deliverability rating within Appendices 1 – 4 and if any should be included within the 2026/27 Budget; was AGREED to be deferred to the next meeting of the Cabinet. Any additional suggestions to balance the remaining shortfall for both the General Fund and Housing Revenue Account and any further savings identified by the Policy Development Groups and recommended back to Cabinet for approval, be considered. Note: *Report previously circulated
Word for word from the decision Mid Devon published for this meeting. Source: democracy.middevon.gov.uk

Follow this further

Built from Mid Devon's papers

What the report saysPro

Report to Cabinet

Report for: Cabinet

Date of Meeting: 7 October 2025

Subject: 2026/27 Draft Budget Update

Cabinet Member: Cllr John Downes – Cabinet Member for Governance, Finance and Risk

Responsible Officer: Andrew Jarrett – Deputy Chief Executive (S151)

Exempt: N/a

Wards Affected: All

Enclosures: Appendix 1 – Emerging Budget Pressures Appendix 2 – Savings Options – General Fund - Cabinet Appendix 3 – Savings Options – General Fund - PDGs Appendix 4 – HRA Savings Options

Section 1 – Summary and Recommendation(s) To present to Members the potential pressures and savings options for consideration / approval to mitigate the forecast Medium Term Financial Plan (MTFP) shortfall covering the period 2026/27 to 2028/29.

Recommendation(s): That Cabinet Members:

1. Consider and agree the Green and Amber pressures on the General Fund within Appendix 1; 2. Consider and agree the Green and Amber savings options for the General Fund for services reporting directly into the Cabinet, as shown within Appendix 2; 3. Consider and agree the Green and Amber savings options for the General Fund for services reporting into the five Policy Development Groups Cabinet within Appendix 3, taking into account the recommendations from the Policy Development Groups as noted in paragraph 2.11; 4. Consider and agree the Green and Amber savings options for the Housing Revenue Account within Appendix 4, taking into account the recommendations from the Homes Policy Development Group as noted in paragraph 2.11; 5. Consider the pressures / savings options with a red risk/deliverability rating within Appendices 1 – 4 and agree if any should be included within the 2026/27 Budget; 6. Consider any additional suggestions to balance the remaining shortfall for both the General Fund and Housing Revenue Account and request that the Policy Development Groups identify further savings options and recommend back to Cabinet for approval.

Section 2 – Report 1.0 Introduction and purpose of the Medium Term Financial Plan

1.1The main purpose of the MTFP is to show how the Council will strategically manage its finances in order to support the delivery of the priorities detailed in the Corporate Plan 2024 – 2028 and years beyond that.

1.2On 2 September, the first draft MTFP covering the period 2026/27 to 2028/29 for the General Fund and Housing Revenue Account (HRA) was presented to Cabinet. For the General Fund, this estimated a funding shortfall for 2026/27 within the range £846k to £3,350k, due to the significant uncertainty surrounding future funding streams. This number is largely driven by inflation and assumptions around further cuts in grant funding using the most up to date information available at this time. Clearly, any major variations in these assumptions would require a fundamental review of the Council’s MTFP and would be reported back to Cabinet and the wider Membership as soon as practical, coupled with proposed courses of action.

1.3For the HRA, an estimated funding shortfall of £541k in 2026/27 rising to £1,796k by 2028/29 was presented. The future years shortfall is a cumulative figure without any remedial action taken, i.e. if the £546k is found to balance the 2026/27 position, the overall budget gap will reduce to £1,255k.

1.4The Council has a legal requirement to set a balance budget and needs to ensure its overall costs are affordable i.e. they can be funded through income and planned short-term use of reserves. Members agreed to apply the four main principles for balancing the budget, and therefore need to take the necessary decisions and actions to manage net spending within affordable limits.

2.02026/27 Budget Options – General Fund

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
GF PressuresAppendix 1 207 KB Download
PDF
GF Savings (Cabinet)Appendix 2 206 KB Download
PDF
GF Savings (ALL PDGs)Appendix 3 224 KB Download
PDF
HRA SavingsAppendix 4 200 KB Download
PDF
Draft Budget Report 2026/2027 (6:35)Report 519 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

16 of 26 attended
LT
Cllr Luke TaylorCommittee Member, present
DW
Cllr David WulffCommittee Member, present
GD
Cllr Gwen Duchesne MBECommittee Member, present
JD
Cllr John DownesCommittee Member, present
SK
Cllr Steve KeableCommittee Member, present
MF
Cllr Matt FletcherCommittee Member, present
JW
Cllr Josh WrightCommittee Member, present
LW
Laura WoonOfficer, present
SW
Stephen WalfordOfficer, present
AJ
Andrew JarrettOfficer, present
MD
Maria De LeiburneOfficer, present
MP
Matthew PageOfficer, present

All 26 on the meeting page

On this subject at Mid Devon

Search all
  1. Draft Budget Report 2026/2027 (6:35)This decision
  2. 2027/28 Draft Budget Update (00:04:00)Approved
  3. 2026/27 Budget Monitoring- Quarter 1Noted
  4. 2025/26 Budget Monitoring- Quarter 3 (00:46:35)Decided
  5. Draft Budget Report 2026/27Noted
  6. Budget Update 2026/27Noted

More from Mid Devon Cabinet

All decisions
MeetingDecisionOutcome
1 Sep 2026 2027/28 Draft Budget Update (00:04:00)RESOLVED that: 1. The proposed approach to balancing the 2027/28 General Fund and Housing Revenue Account budget gaps... Approved Open
4 Aug 2026 Minutes of the Previous MeetingThe minutes of the previous meeting held on 07 July 2026 were APPROVED as a correct record and SIGNED by the Leader. ... Approved Open
4 Aug 2026 2026/27 Budget Monitoring- Quarter 1The Cabinet had before it a report * from the Deputy Chief Executive (S151) on the 2025/26 Budgeting Monitoring quart... Noted Open
4 Aug 2026 Air Source Heat Pump (ASHP) Contract 2026-2030The Cabinet had before it a report * from Head of Housing and Health on the Air Source Heat Pump (ASHP) Contract 2026... Decided Open
4 Aug 2026 Notification of Key DecisionsThe Cabinet had before it, and NOTED , the notification of Key Decisions *. Note: * Key Decisions previously circulated. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies