Draft Budget Report 2026/27

Agreed Executive 3 papers

AI summaryMid Devon Cabinet kept amber budget options as planning assumptions pending government financial settlement clarity, and noted the emerging Capital Programme to 2030/31 with a forecast General Fund shortfall of up to £4,324k for 2026/27.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedCapital Programme noted with comments
MoneyUp to £4,324k shortfallGeneral Fund 2026/27 upper range
What happens nextFull Council 18 February 2026Final budget agreement
Who it affectsAll wardsCouncil-wide revenue and capital

What was decided

Amber budget options remain as budget planning assumptions until clarity is received from the government financial settlement announcement. Report P11

Cabinet considered and gave comments on the emerging Capital Programme covering 2026/27 to 2030/31. Report P11, 3.0

Cabinet noted that there remains little clarity on the financial settlement and that this is likely to require additional ad hoc updates, particularly after the Local Government Finance Settlement announcement. Report P11

Why

The Council has a legal requirement to set a balanced budget and must ensure overall costs are affordable. Report 1.7

There is significant uncertainty surrounding future funding streams, with a current forecast General Fund shortfall ranging from £1,820k to £4,324k for 2026/27 after Green options were agreed. Report 1.2, 1.4, P19

Many areas require greater clarity, particularly around national funding and possible changes to Government Policy. Report P54

What happens next

A further review of all budget options will be undertaken once full clarity is available on the funding position, with the 2026/27 budget finalised in February. Report 2.3, 2.5

A full review of Earmarked Reserves will be necessary to see what can be realigned and whether a minimum balance of £2m in General Reserves can be maintained. Report 4.4

Updates to the draft budget will be brought as and when greater clarity emerges in the run up to the budget being agreed at Full Council on 18 February 2026. Report 4.6

The money

  • £1,820k to £4,324k Current forecast General Fund shortfall for 2026/27 after Green options Report 1.4, P19
  • £846k to £3,350k Original General Fund funding shortfall estimate for 2026/27 from the first draft MTFP Report 1.2
  • £974k Net impact of 7 October Green Budget Options decision (£1,325k pressures and £351k savings) Report 1.4
  • £2m Target minimum balance for General Reserves Report 4.4
  • £1,769k HRA shortfall over the MTFP timeframe after Green options Report 1.5
  • £541k HRA initial forecast shortfall for 2026/27 Report 1.5, P21
  • £514k HRA current forecast shortfall for 2026/27 after Green options Report 1.5, P22
  • £120k Red saving rejected for ceasing Community Development Grants Report P31

Options considered

  • Chosen: Amber budget options retained as planning assumptions. Awaiting clarity on the government financial settlement announcement Report P11, 2.1
  • Chosen: Green Budget Options previously agreed on 7 October. Recommended by officers; net pressure of £974k accepted Report 1.4
  • Rejected: Red saving to cease Community Development Grants (£120k). Not the recommendation of officers Report P31
  • Rejected: Red saving to let out further space in Phoenix House. Local Government Reorganisation limits the partner pool; letting below commercial rate does not return the value Report P32, P33

Implications

  • Financial: Some level of draw from reserves may be required, and a full review of Earmarked Reserves is necessary to see if a £2m minimum General Reserve balance can be maintained. Report 4.4
  • Financial: Given the scale of likely funding reductions, it is unlikely a sufficient level of efficiency savings can be identified to fully balance the 2026/27 budget without significant implications on service provision. Report 4.2
  • Legal: There is a legal obligation to balance the budget; no direct legal implications arise from this report. Report P54
  • Risk: The MTFP makes several key financial assumptions based on a prudent approach, kept under review and updated where necessary. Report P54
  • Climate: Allocation of resources will impact the Council's ability to implement climate change activities, though some provision is already in the base budget. Report P54
  • Equalities: No implications arising from this report. Report P54

Who and where

  • All wards in Mid Devon Report P7
  • General Fund services Report 1.2
  • Housing Revenue Account tenants and services Report 1.5
  • Leisure centre users (sports offering review) Report P30
  • Community organisations receiving Community Development Grants Report P31
  • Phoenix House potential tenants Report P32

Timeline

  • 2 September 2025: First draft MTFP for 2026/27 to 2028/29 presented to Cabinet Report 1.2
  • 7 October 2025: Cabinet agreed Green Budget Options Report 1.4
  • 4 November 2025: Cabinet meeting: draft budget report considered Report P2
  • 26 November 2025: Autumn Budget announcement expected
  • November (Homes PDG): Will consider Convergence option 2 (up to £2 per week cap) for HRA Report 2.4
  • 18 February 2026: Final budget to be agreed at Full Council Report 4.6

Plain English for the jargon

  • MTFP: Medium-Term Financial Plan
  • HRA: Housing Revenue Account
  • PDG: Policy Development Group
  • CSAG: Corporate Strategic Asset Advisory Group
  • S151: Statutory chief finance officer (Section 151 of the Local Government Act 1972)
  • EPR: Extended Producer Responsibility (grant)
  • S106: Section 106 planning obligation
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item66

Resolved

The Cabinet had before it a report * from the Deputy Chief Executive (S151) Officer and the Head of Finance, Property and Climate Resilience on the draft Budget 2026/27. RESOLVED that: The amber budget options remained as budget planning assumptions until clarity was received following the Government financial settlement announcement and that was AGREED . Consideration and comments were given regarding the emerging Capital Programme covering the period 2026/27 to 2030/31 within Appendix 1a and 1b; There remained little clarity on the financial settlement currently and that this was likely to require additional ad hoc updates as and when greater information was known, particularly following the announcement of the Local Government Finance Settlement be NOTED Note: *Report previously circulated By undertaking regular reviews of the Medium-Term Financial Plan, the Council could ensure that the Corporate Plan priorities were affordable. The implications of the budget gap were set out within the paper. Many areas required greater clarity, particularly around national funding and possible changes to Government Policy. Note: *Report previously circulated
Word for word from the decision Mid Devon published for this meeting. Source: democracy.middevon.gov.uk

Follow this further

Built from Mid Devon's papers

What the report saysPro

Report to Cabinet

Report for: Cabinet

Date of Meeting: 4 November 2025

Subject: 2026/27 Draft Budget Update

Cabinet Member: Cllr John Downes – Cabinet Member for Governance, Finance and Risk

Responsible Officer: Andrew Jarrett – Deputy Chief Executive (S151)

Exempt: N/a

Wards Affected: All

Enclosures: Appendix 1a – Emerging 2026/27 – 2030/31 Capital Programme for the General Fund Appendix 1b – Emerging 2026/27 – 2030/31 Capital Programme for the Housing Revenue Account

Section 1 – Summary and Recommendation(s) To approve the budget options as previously recommended by the Policy Development Groups to mitigate the forecast Medium-Term Financial Plan (MTFP) shortfall covering the period 2026/27 to 2028/29. Also, to trail the emerging Capital Programme covering the period 2026/27 to 2030/31.

Recommendation(s): That Cabinet Members:

1. Consider and agree to leave amber budget options in as budget planning assumptions until clarity is received from the government financial settlement announcement; 2. Consider and comment on the emerging Capital Programme covering the period 2026/27 to 2030/31 within Appendix 1a and 1b; 3. Note that there remains little clarity on the financial settlement currently and that this is likely to require additional ad hoc updates as and when greater information is known, particularly following the announcement of the Local Government Finance Settlement. Section 2 – Report 1.0 Introduction and purpose of the Medium-Term Financial Plan

1.1The main purpose of the MTFP is to show how the Council will strategically manage its finances to support the delivery of the priorities detailed in the Corporate Plan 2024 – 2028 and years beyond that.

1.2On 02 September, the first draft MTFP covering the period 2026/27 to 2028/29 for the General Fund and Housing Revenue Account (HRA) was presented to Cabinet. For the General Fund, this estimated a funding shortfall for 2026/27 within the range £846k to £3,350k, due to the significant uncertainty surrounding future funding streams.

1.3During the summer, Leadership Team and senior service managers have been reviewing a range of budget options that could be considered to help mitigate that remaining budget shortfall across this MTFP, with a particular focus on 2026/27. In putting forward the budget options, officers have applied a risk level to them based upon Red, Amber, Green as follows:

Red – indicates the saving could be taken, but there are higher risks/ implications associated with it and therefore officers would not recommend it; Amber – indicates the saving could be taken, but there are risks and implications associated that members need to be aware of / accept; Green – indicates a saving that is recommended by officers – previously approved.

1.4On 07 October, Cabinet agreed the Green Budget Options summing to a net pressure of £974k (£1,325k pressures and £351k savings). Based on the original assumptions, this increases the current projected funding shortfall to a range of £1,820k to £4,324k.

Table 1 General Fund Option 1a Option 1b Option 1c

Initial forecast Shortfall £919k £846k £3,350k

Net Impact of decision on 7 October +£974k +£974k +£974k Current Forecast Shortfall + £1,893k + £1,820k + £4,324k

1.5For the HRA, an estimated funding shortfall of £541k in 2026/27 rising to £1,796k by 2028/29 was presented. The future years shortfall is a cumulative figure without any remedial action taken, i.e. if the £546k is found to balance the 2026/27 position, the overall budget gap will reduce to £1,255k. Also on 07 October, Cabinet agreed the Green Budget Options summing to £27k, thereby reducing the forecast shortfall to £514k for 2026/27 and £1,769k over the MTFP timeframe. Table 2 Housing Revenue Account Budget Shortfall

Initial forecast Shortfall £541k

Net Impact of decision on 7 October - £27k Current Forecast Shortfall £514k

1.6Cabinet deferred consideration of the Amber and Red Budget Options until this meeting.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
GF Capital Programme 2026_27 to 2030_31Appendix 1a 229 KB Download
PDF
HRA Capital Programme 2026_27 to 2030_31Appendix 1b 208 KB Download
PDF
Draft Budget Report 2026/27Report 494 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

16 of 17 attended
LT
Cllr Luke Taylor Leader of the CouncilCommittee Member, present
JL
Cllr Jane Lock Cabinet Member for Housing, Assets and Property ServicesCommittee Member, present
NB
Cllr Natasha Bradshaw Cabinet Member for Environment and Climate ChangeCommittee Member, apologies
JD
Cllr John Downes Cabinet Member for Governance, Finance and RIskCommittee Member, present
GD
Cllr Gwen Duchesne MBE Cabinet Member for Parish and Community EngagementCommittee Member, present
MF
Cllr Matt Fletcher Cabinet Member for People DevelopmentCommittee Member, present
SK
Cllr Steve Keable Cabinet Member for Planning and Economic RegenerationCommittee Member, present
JW
Cllr Josh Wright Cabinet Member for Service Delivery and Continuous ImprovementCommittee Member, present
DW
Cllr David Wulff Cabinet Member for Quality of Living, Equalities and Public HealthCommittee Member, present
SW
Stephen WalfordOfficer, present
AJ
Andrew JarrettOfficer, present
MD
Maria De LeiburneOfficer, present

All 17 on the meeting page

On this subject at Mid Devon

Search all
  1. Draft Budget Report 2026/27This decision
  2. 2027/28 Draft Budget Update (00:04:00)Approved
  3. 2026/27 Budget Monitoring- Quarter 1Noted
  4. 2025/26 Budget Monitoring- Quarter 3 (00:46:35)Decided
  5. Draft Budget Report 2026/27Noted
  6. Budget Update 2026/27Noted

More from Mid Devon Cabinet

All decisions
MeetingDecisionOutcome
1 Sep 2026 2027/28 Draft Budget Update (00:04:00)RESOLVED that: 1. The proposed approach to balancing the 2027/28 General Fund and Housing Revenue Account budget gaps... Approved Open
4 Aug 2026 Minutes of the Previous MeetingThe minutes of the previous meeting held on 07 July 2026 were APPROVED as a correct record and SIGNED by the Leader. ... Approved Open
4 Aug 2026 2026/27 Budget Monitoring- Quarter 1The Cabinet had before it a report * from the Deputy Chief Executive (S151) on the 2025/26 Budgeting Monitoring quart... Noted Open
4 Aug 2026 Air Source Heat Pump (ASHP) Contract 2026-2030The Cabinet had before it a report * from Head of Housing and Health on the Air Source Heat Pump (ASHP) Contract 2026... Decided Open
4 Aug 2026 Notification of Key DecisionsThe Cabinet had before it, and NOTED , the notification of Key Decisions *. Note: * Key Decisions previously circulated. Noted Open