AI summaryMid Devon Cabinet noted a forecast £156k General Fund and £745k HRA overspend for 2025/26, and will ask Full Council to add £526k to the Capital Programme, with delegated disposal of a derelict social home.
Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet notes monitoring; recommends capital increase and disposal
Money£156k GF, £745k HRA overspendPlus £526k proposed capital programme increase
What happens nextFull Council to decideOn £526k capital programme increase
Who it affectsAll Mid Devon wardsIncluding HRA and social rent tenants
What was decided
Cabinet noted the financial monitoring for the three months to 30 September 2025 and the projected outturn, including a General Fund overspend of £156k and an HRA deficit of £745k. Report 2.1, 3.1, 4.1
Cabinet agreed to recommend to Full Council an increase of £526k to the Capital Programme, made up of £276k of additional grant and £250k of extra budget for Right to Buy buybacks. Report 5.3, 5.5, P10
Cabinet gave delegated authority to the Head of Housing and Health, working with the Deputy Chief Executive (S151), to dispose of a derelict social house and reinvest the capital receipt in new social housing. Report 5.6
Why
The General Fund £156k overspend is driven mainly by nearly £140k in extra agency staff costs covering long-running vacancies in Waste, Finance, Legal and Planning Enforcement, and lower income from Planning, Building Control and waste recyclate. The General Reserve is forecast to fall to £1,868k, below the agreed £2m minimum. Report 2.2, 2.3, 2.4, 3.4
The HRA £745k deficit mainly reflects £512k higher contractor and materials costs in housing operations, £295k higher premises insurance, £62k lower treasury income and £55k lost rent from voids, partly offset by a £228k salary underspend. Report 4.2, P33
Right to Buy buybacks are described as the most cost effective way to grow the HRA stock, and the derelict home is judged uneconomic to renovate with no assessed need for that size of property in the village. Report 5.5, 5.6
What happens next
Full Council to consider the recommendation to increase the Capital Programme by £526k, comprising £276k of additional grant and £250k for further HRA buybacks. Report 5.3, 5.5
The Head of Housing and Health and Deputy Chief Executive (S151) to dispose of the derelict HRA property and reinvest the capital receipt in additional social housing. Report 5.6
The Council awaits DWP advice on Universal Credit cases for the social rent refunds, expected in early November, with the next regulator meeting on 13 November. Report 8.3, 8.4
The money
£156k General Fund forecast overspend for 2025/26 Report 2.1, 3.1
£745k HRA forecast deficit for 2025/26 Report 2.1, 4.1
£526k Proposed increase to 2025/26 Capital Programme Report P10
£276k Additional grant received since the budget was set Report 5.3
£64,277k Year 4 Shared Prosperity Fund grant Report 5.3
£211,536 Year 3 Rural England Prosperity Fund grant Report 5.3
£250k Extra budget for additional Right to Buy buybacks (around 2 units) Report 5.5
£1,868k Forecast General Reserve at 31 March 2026, below the £2m minimum Report 2.4, P28
Options considered
Chosen: Recommend £526k increase to the Capital Programme to Full Council. Reflects £276k of additional grant and £250k for further Right to Buy buybacks Report P10, 5.3, 5.5
Chosen: Dispose of a derelict HRA house and reinvest the capital receipt. Property is uneconomic to renovate and there is no assessed need for a home of that size in the village Report 5.6
Chosen: Note the use of procurement waivers and direct award contracts. No procurement waivers were raised in the quarter; two direct awards via frameworks were made Report P60, 7.2, P63
Implications
Financial: If the forecast overspend is delivered, the General Reserve will fall to £1,868k, below the agreed £2m minimum, and the position will be reviewed at year end against uncertainty on central government funding and Local Government Reform or Devolution. Report 2.4, P28, 9.2
Financial: If the £745k HRA overspend cannot be covered by the existing HRA Reserve, a draw on the Housing Maintenance Reserve (currently over £12m) will be required. Report 4.5, P28
Legal: The Local Government Finance Act 1992 requires the Council to keep expenditure within resources and to set a balanced budget; regular monitoring by the Executive supports compliance. Report P72
Risk: The Strategic Risk Register (Audit Committee) includes a specific risk CR7 reflecting the Council's financially difficult and uncertain future. Report P72
Staffing: Recruitment difficulties in Waste, Finance, Legal and Planning Enforcement have driven nearly £140k of agency staff cost pressure above salary savings. Report 2.2, 3.4
Climate: The General Fund, Capital Programme and HRA all contain significant investment in support of the Council's Carbon Reduction Pledge. Report P72
Social rent tenants who have received refunds, including those in receipt of Housing Benefit Report 8.2, 8.3
Social rent tenants in receipt of Universal Credit, awaiting DWP guidance Report 8.3
HRA tenants in the village where the derelict property is located Report 5.6
Council staff in Waste, Finance, Legal and Planning Enforcement where vacancies persist Report 2.2, 3.4
Timeline
11 July 2025: Refunds began for non benefit and Housing Benefit social rent cases Report 8.3
12 July 2025: Wavenet business continuity contract started (£107k inc VAT, runs to 11 July 2028) Report P63
18 August 2025: Risk Ledger subscription contract started (£25k, runs to 17 August 2028) Report P63
30 September 2025: End of Q2 monitoring period Report P10
17/10/2025: Over 150 social rent refunds issued, value over £165k Report 8.2
4 November 2025: Cabinet considered and decided on the Q2 budget monitoring report Report P2
13 November: Next planned meeting with the social rent regulator Report 8.4
31 March 2026: Forecast year end reserve position Report 1.2, P28
Plain English for the jargon
HRA: Housing Revenue Account, a ring fenced reserve for the Council's housing landlord function, increased or decreased by the annual surplus or deficit.
EMR: Earmarked Reserves, set aside for specific purposes and used in this report to mitigate some unbudgeted expenditure.
PSDS: Public Sector Decarbonisation Scheme, a government grant programme referenced for works at Culm Valley.
Procurement waiver: Approval to act outside contract procedure regulations in exceptional circumstances, such as urgency or specialist goods with no effective competition.
Direct award via framework: A contract awarded to a pre-qualified supplier on a framework agreement, used to streamline procurement of goods, services or works.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item67
Resolved
The Cabinet had before it a report * from the Deputy Chief Executive (S151) Officer and the Head of Finance, Property and Climate Resilience on the 2025/26 Quarter 2 Budget Monitoring. RESOLVED that: a) The financial monitoring information for the income and expenditure for the three months to 30 September 2025 and the projected outturn position be NOTED . b) To recommend to Full Council that the increase to the Capital Programme of £526k in respect of additional Grant funding received (£276k – see par 5.3) and extra budget to further increase the HRA Housing Stock (£250k – see para 5.5) be AGREED. c) Delegated Authority be given for the Head of Housing and Health in association with the Deputy Chief Executive (S151) to dispose of a derelict social house which was uneconomic to renovate, and where there was no need for such a home and use the capital receipt generated to reinvest in the provision of additional social housing - see para 5.6. d) The use of Waivers and Direct Awards for the Procurement of goods and services as included in Section 7 be NOTED . e) The performance achieved in respect of resolving the Social Rent errors within the Council’s direct control and recognise the impact of the delays in responses from partner organisations, as outlined within Section 8 be NOTED . f) The update on future funding given in paragraphs 9.2 be NOTED . Note: *Report previously circulated Good financial management and administration underpin the entire document. A surplus or deficit on the Revenue Budget would impact on the Council’s General Fund balances. The Council’s financial position was constantly reviewed to ensure it was continued financial health. Note: *Report previously circulated
Word for word from the decision Mid Devon published for this meeting.Source: democracy.middevon.gov.uk
Cabinet Member: Cllr John Downes, Cabinet Member for Governance, Finance and Risk
Responsible Officer: Andrew Jarrett, Deputy Chief Executive (S151)
Exempt: N/a
Wards Affected: All
Enclosures: Appendix A – General Fund Summary Appendix B – General Fund Service Variances Appendix C – Employee Cost Summary Analysis Appendix D – Income Summary Analysis Appendix E – HRA Summary and detail variances Appendix F – Capital Programme Summary
Section 1 – Summary and Recommendation(s) To present the forecast Outturn position for the General Fund, Housing Revenue Account and Capital Programme for the financial year 2025/26.
Recommendation(s): 1. The Cabinet are asked to: a) Note the financial monitoring information for the income and expenditure for the three months to 30 September 2025 and the projected outturn position; b) Recommend to Full Council the increase to the Capital Programme of £526k in respect of additional Grant funding received (£276k – see par 5.3) and extra budget to further increase the HRA Housing Stock (£250k – see para 5.5) c) Delegated approval is sought for the Head of Housing and Health in association with the Deputy Chief Executive (S151) to dispose of a derelict social house which is uneconomic to renovate, and where there is no need for such a home and use the capital receipt generated to reinvest in the provision of additional social housing- see para 5.6. d) Note the use of Waivers and Direct Awards for the Procurement of goods and services as included in Section 7; e) Note the performance achieved in respect of resolving the Social Rent errors within our direct control and recognise the impact of the delays in responses from partner organisations, as outlined within Section 8; f) Note the update on future funding given in paragraphs 9.2.
Section 2 – Report 1.0 Introduction
1.1This report contains information relating to the Council’s overall financial performance for the 2025/26 financial year. Monitoring the Budget is an important part of the Council’s performance management framework. The aim is to keep a tight control on spending on services within a flexible budget management framework.
1.2The purpose of this report is to highlight to Cabinet the current financial status and the likely reserve balances at 31 March 2026. It encompasses the General Fund, the Housing Revenue Account (HRA), and Capital Programme. The detail under pinning these projections is included within the body of report in the following sections / appendices:
The projected General Fund outturn position for 2025/26 (Section 3 + Appendices A to D); The projected HRA Outturn position for 2025/26 (Section 4 + Appendix E); The projected Capital Outturn position for 2025/26 (Section 5 + Appendix F); Collection Fund (Section 6); Procurement Waivers (Section 7) Social Rent Update (Section 8).
1.3Favourable variances generating either increased income or cost savings are expressed as credits (negative numbers), whilst unfavourable overspends or incomes below budget are debits (positive numbers). Any variance against the agreed budget will impact on the Council’s reserves. This monitoring focuses on significant budget variances (+/- £20k), including any remedial action where necessary leading to an estimated overall Outturn position.
1.4The Council’s financial position will be constantly reviewed to ensure its continued financial health and delivery of excellent Value for Money.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
2027/28 Draft Budget Update (00:04:00)RESOLVED that: 1. The proposed approach to balancing the 2027/28 General Fund and Housing Revenue Account budget gaps...
Minutes of the Previous MeetingThe minutes of the previous meeting held on 07 July 2026 were APPROVED as a correct record and SIGNED by the Leader. ...
2026/27 Budget Monitoring- Quarter 1The Cabinet had before it a report * from the Deputy Chief Executive (S151) on the 2025/26 Budgeting Monitoring quart...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.