Mid Devon District Council
Cabinet, Tuesday 3 March 2026 at 5.15pm

Painting and Repairs before Painting of Council Homes 2026-2031

Decided Executive 1 paper

AI summaryMid Devon Cabinet received a report on the proposed 2026-2031 painting contract for council homes, noting the Decent Homes Standard duty and an HRA budget of £350,000 a year.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedCllr S Keable abstained, arriving late
Money£350,000.00 per annumFrom the Housing Revenue Account
What happens nextWeekly contract performance monitoringCorrective action if KPIs missed
Who it affectsCouncil tenants in MDDC stockPainted and repaired to Decent Homes Standard

What was decided

Cabinet received the report and noted the Council's legal duty to meet the Decent Homes Standard and maintain the health and safety of employees and tenants, with the contract enabling compliance with statutory obligations. Report P2

Statutory officers (Section 151, Monitoring Officer, Chief Executive, and Corporate Performance and Improvement Manager) all signed off the report on 23 February 2026. Report P21, P22, P23, P24

Cllr S Keable abstained from the vote because of arriving late during the item's discussion.

Why

As a social landlord, Mid Devon Homes must meet the Decent Homes Standard and other statutory requirements, including Awaab's Law, to protect tenant and staff health and safety. Report P2, P8

Failure to award would risk a Regulator of Social Housing C3 or C4 rating for serious failings in the consumer standards, plus financial, legal and reputational costs. Report P8, P9, P10, P11

The proposed award follows a tender evaluation; one contractor was excluded for an abnormally low bid and unsatisfactory response, with the Contract Award Recommendation issued on 11 February 2026. Report P6

What happens next

Performance against the contract will be monitored weekly, with corrective action where KPIs on customer satisfaction, variations, programme delivery, defects, and health and safety fall short. Report P13

Equality and diversity will be raised at progress meetings and the contractor encouraged to carry out awareness training. Report P17

The draft JCT Standard Building Contract 2016 has been reviewed and approved with the Council's legal services team. Report P4, P5

The money

  • £350,000.00 per annum Housing Revenue Account budget for the painting and repairs works Report P1

Options considered

  • Chosen: Award the painting and repairs contract. Supports Decent Homes Standard compliance and a likely C1 or C2 Regulator of Social Housing rating Report P2, P11
  • Rejected: Do not award or seek alternative provision. Would risk sub-standard housing, Awaab's Law non-compliance, RSH C3 or C4 rating, and tenant harm Report P8, P9, P10
  • Rejected: Accept the abnormally low bidder. Excluded under price evaluation with an unsatisfactory response Report P6

Implications

  • Legal: Awarding the contract supports compliance with the Decent Homes Standard, Awaab's Law and the Regulator of Social Housing consumer standards, and uses a JCT 2016 contract approved by legal services. Report P2, P4, P5, P8
  • Risk: Not awarding risks a C3 or C4 RSH performance rating, maladministration costs, disrepair claims, and reputational harm; delivery risks will be tracked against five KPIs. Report P8, P9, P10, P11, P13
  • Financial: Annual HRA budget of £350,000.00, with capital investment expected to lower future revenue maintenance costs. Report P1
  • Equalities: Staff have received Equality and Diversity training and the topic will be revisited at progress meetings with the contractor. Report P17
  • Climate: Environmental impact was part of the contractor evaluation; investment in the stock should cut fossil fuel use and carbon emissions. Report P15

Who and where

  • Tenants in Mid Devon District Council housing stock Report P2, P8
  • Mid Devon Homes as the social landlord Report P2
  • Mid Devon District Council as commissioner and landlord Report P8, P9
  • Council staff and contractor staff delivering the works Report P2, P13

Timeline

  • 11 February 2026: Contract Award Recommendation issued after tender evaluation Report P6
  • 23.02.26: Statutory officers signed off the report Report P21, P22, P23
  • 2026 to 2031: Term of the proposed painting and repairs contract
  • 3 March 2026: Cabinet meeting to receive the report

Plain English for the jargon

  • HRA: Housing Revenue Account, the ringfenced account for council housing income and spending
  • MDH: Mid Devon Homes, the council's social landlord function
  • Decent Homes Standard: Government standard setting minimum condition requirements for social housing
  • Awaab's Law: Legal duty on social landlords to fix specified hazards within set time limits
  • RSH: Regulator of Social Housing, which rates landlord compliance with consumer standards
  • C1 to C4 ratings: RSH judgements from fully compliant (C1) to very serious failings (C4)
  • TSM: Tenant Satisfaction Measures, the mandated landlord performance indicators
  • JCT: Joint Contracts Tribunal, publisher of standard building contracts used here as the 2016 Standard Building Contract
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item128

Resolved

The Council had a legal duty to meet the Decent Homes Standard and maintain the health and safety of its employees and tenants. Painting and Repairs before Painting were a key part of the Decent Homes Standard where the Contract would enable compliance with relevant requirements and other statutory obligations. Note ( i )* Report previously circulated (ii) Cllr S Keable ABSTAINED from voting due to arriving late during discussion of this item.
Word for word from the decision Mid Devon published for this meeting. Source: democracy.middevon.gov.uk

Follow this further

Built from Mid Devon's papers

What the report saysPro

Report to Cabinet

Report for: Cabinet

Date of Meeting: 3 March 2026

Subject: AWARD OF PAINTING AND REPAIRS BEFORE PAINTING OF COUNCIL HOMES 2026-2031

Cabinet Member: Cllr Jane Lock - Cabinet Member for Housing, Assets and Property Services

Responsible Officer: Simon Newcombe - Head of Housing and Health

Exempt: Annex A – PART II report

PART II, which are Exempt from publication under paragraph 3, Part 1 of Schedule 12A to the Local Government Act 1972 (as amended) as it contains information relating to the financial or business affairs of any particular person (including the authority holding that information)

Wards Affected: All

Enclosures: Annex A – PART II report

Section 1 – Summary and Recommendation(s)

To advise Members on the results of the tendering of the Painting and Repairs before Painting of Council Homes 2026-2031 and confirm the award of the contract.

Recommendation(s):

1. It is recommended that the new five-year (3+1+1) Painting and Repairs before Painting Contract be awarded to Contractor 1.

2. Delegated authority be granted to the S151 Officer (in consultation with the Cabinet Member for Housing, Assets and Property Services) to complete the associated Painting and Repairs before Painting Contract (the Contract).

Section 2 – Report

1 Introduction 1.1 Mid Devon Housing (MDH) has a requirement to maintain its stock and meet the statutory Decent Homes Standard. In turn this will support compliance with the new serious hazards legislation (The Hazards in Social Housing (Prescribed Requirements) (England) Regulations 2025 more commonly referred to as Awaab’s Law) which, amongst other things, sets out strict timescales for the investigation and treatment of damp and mould. Adherence to the Decent Homes Standard also supports MDH in meeting its other statutory obligations in relation to repair and maintenance.

1.2Further information on the legal context and risk assessment associated with sub-standard housing is set out in the legal implications and risk assessment at the end of the report.

1.3We anticipate that the actual spend will be within the annual budget of £350,000.00.

1.4The term of the Contract is five years with the option to terminate the Contract at the end of each year subject to performance.

1.5Due to the nature and value of this procurement, the appropriate procedure was an open tender process. This meant that anyone who expressed an interest in the Contract was invited to tender.

1.6To ensure quality of contractors, several minimum requirements were set out within the ITT. Any contractor who failed to meet these was disqualified.

2 Procurement Process

2.1Expressions of interest were invited via a notice in the Supplying the South West Procurement Portal published on the 21 October 2025.

2.2The following evaluation criteria were set out in the ITT:

Quality 60% Capacity and Resources 20% Communication, Residents and Complaints 20% Environmental Benefits 20%

Price 40%

2.3Responses were required by midday on 12 December 2025.

2.4There were a total of 57 expressions of interest of which 8 submitted their tenders on time (of which 2 were non-compliant), 10 opted out, and 39 did not respond. The main reason given for opting out was due to workload and insufficient resources at that time. Insufficient resources may also have included capacity to fulfil the Contract against its specification and relevant time period. 2.5 Evaluations were carried out during December 2025 by representatives from MDH building services teams. This was supported by the procurement team who undertook a compliance check.

2.6One contractor was then excluded from the process for submitting an abnormally low bid leading to concerns around validity, quality and deliverability. Although clarification of this bid was requested the response was not satisfactory.

2.7The price was based on a schedule of rates within the tender. The lowest priced tender was awarded 40% and the higher priced tenders were awarded the percentage difference. Contractor 1 scored highest on both price and quality as set out below.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Painting and Repairs before Painting of Council Homes 2026-2031Report 278 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

17 of 17 attended
LT
Cllr Luke Taylor Leader of the CouncilCommittee Member, present
JL
Cllr Jane Lock Cabinet Member for Housing, Assets and Property ServicesCommittee Member, present
NB
Cllr Natasha Bradshaw Cabinet Member for Environment and Climate ChangeCommittee Member, present
JD
Cllr John Downes Cabinet Member for Governance, Finance and RIskCommittee Member, present
GD
Cllr Gwen Duchesne MBE Cabinet Member for Parish and Community EngagementCommittee Member, present
MF
Cllr Matt Fletcher Cabinet Member for People DevelopmentCommittee Member, present
SK
Cllr Steve Keable Cabinet Member for Planning and Economic RegenerationCommittee Member, present
JW
Cllr Josh Wright Cabinet Member for Service Delivery and Continuous ImprovementCommittee Member, present
DW
Cllr David Wulff Cabinet Member for Quality of Living, Equalities and Public HealthCommittee Member, present
SW
Stephen WalfordOfficer, present
AJ
Andrew JarrettOfficer, present
MD
Maria De LeiburneOfficer, present

All 17 on the meeting page

On this subject at Mid Devon

Search all
  1. Painting and Repairs before Painting of Council Homes 2026-2031This decision
  2. External Painting and Repairs before Painting of Council Homes 2021-26 (1-18-51)Decided
  3. Painting and Repairs before Painting of Council Homes 2020 - 2025Approved

More from Mid Devon Cabinet

All decisions
MeetingDecisionOutcome
1 Sep 2026 2027/28 Draft Budget Update (00:04:00)RESOLVED that: 1. The proposed approach to balancing the 2027/28 General Fund and Housing Revenue Account budget gaps... Approved Open
4 Aug 2026 Minutes of the Previous MeetingThe minutes of the previous meeting held on 07 July 2026 were APPROVED as a correct record and SIGNED by the Leader. ... Approved Open
4 Aug 2026 2026/27 Budget Monitoring- Quarter 1The Cabinet had before it a report * from the Deputy Chief Executive (S151) on the 2025/26 Budgeting Monitoring quart... Noted Open
4 Aug 2026 Air Source Heat Pump (ASHP) Contract 2026-2030The Cabinet had before it a report * from Head of Housing and Health on the Air Source Heat Pump (ASHP) Contract 2026... Decided Open