Middlesbrough Borough Council
Executive, Wednesday 12 November 2025 at 6.00pm

2025/26 Transport and Infrastructure Capital Programme Update

Approved Executive 3 papers

AI summaryMiddlesbrough Borough Council’s Executive approved continued CRSTS funding for highways maintenance and integrated transport. The 2025/26 programme is funded through a £4.154m CRSTS grant, with mitigation to avoid clawback risk and maintain the ability to meet statutory obligations. [D]

AI summaryIn plain English

Written from the decision wording; the report is not read yetPDF Pro
OutcomeApprovedAcross Highways Maintenance and Integrated Transport; mitigation approved [D]
Money£4.154m CRSTS grant [D]Funds the 2025/26 Capital Programme [D]
What happens nextOfficers may reallocate funds [D]For accelerated delivery or emerging priorities [D]
Who it affectsHighways and transport schemes [D]Carriageways; Structures & Bridges; Stainton Way Phase 2 [D]

What was decided

The Executive approved continued CRSTS funding across Highways Maintenance and Integrated Transport.

It approved mitigation measures for schemes at risk of delay or underspend, particularly Carriageways, Structures & Bridges and Stainton Way Phase 2 schemes.

It noted progress on delivery of the 2025/26 Capital Programme and flexibilities allowing officers to reprofile or reallocate approved funds.

Why

75% of schemes were on programme (RAG: Green), while a further 25% had minor delays (RAG: Amber) but remained deliverable within the current or next financial year.

The mitigation is intended to maintain continued alignment with CRSTS grant conditions and avoid clawback risk.

Maintaining the Council’s ability to meet statutory obligations is a stated purpose of the mitigation.

What happens next

Implement mitigation measures for schemes at risk of delay or underspend.

Use programme management flexibilities to reprofile or reallocate approved funds, where appropriate, to support accelerated delivery of schemes ready to start or respond to emerging priorities.

The money

  • £4.154m City Region Sustainable Transport Settlement grant for the 2025/26 Capital Programme

Options considered

  • Chosen: Continue CRSTS allocation across Highways Maintenance and Integrated Transport. 75% of schemes were on programme, and a further 25% had minor delays but remained deliverable within the current or next financial year.
  • Chosen: Implement mitigation for schemes at risk of delay or underspend. To maintain continued alignment with CRSTS grant conditions, avoid clawback risk and maintain the Council’s ability to meet statutory obligations.

Implications

  • Financial: The 2025/26 Capital Programme is funded through the £4.154m CRSTS grant.
  • Risk: A further 25% of schemes had minor delays but remained deliverable within the current or next financial year.
  • Risk: Mitigation is intended to maintain continued alignment with CRSTS grant conditions and avoid clawback risk.
  • Legal: Maintaining the Council’s ability to meet statutory obligations is part of the mitigation’s purpose.
  • Financial: Officers may reprofile or reallocate approved funds, where appropriate, to support accelerated delivery or respond to emerging priorities.
  • Risk: Particular mitigation attention goes to Carriageways, Structures & Bridges and Stainton Way Phase 2 schemes.

Who and where

  • 2025/26 Capital Programme
  • Highways Maintenance workstream
  • Integrated Transport workstream
  • Schemes at risk of delay or underspend
  • Carriageways schemes
  • Structures & Bridges schemes
  • Stainton Way Phase 2 schemes

Timeline

  • 2025-11-12: Executive approved the continued CRSTS allocation and mitigation measures.
  • 2025/26: Delivery of the Capital Programme funded through the £4.154m CRSTS grant.
  • current or next financial year: A further 25% of schemes with minor delays remained deliverable.

Plain English for the jargon

  • CRSTS: The £4.154m City Region Sustainable Transport Settlement grant [D]
  • RAG: Scheme progress labels used here: Green and Amber [D]
  • RAG: Green: Scheme currently on programme [D]
  • RAG: Amber: Scheme experiencing minor delays [D]
  • Clawback risk: Grant funding risk that the mitigation is intended to avoid [D]
  • Reprofile: Adjust approved funds to support accelerated delivery or emerging priorities [D]
  • Underspend: Use less funding than planned [D]
  • Statutory obligations: Legal duties the Council must retain the ability to meet [D]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item25/49

Resolved

ORDERED that Executive: 1. Approve the continued allocation of CRSTS funding across both Highways Maintenance and Integrated Transport workstreams, noting that 75% of schemes were currently on programme (RAG: Green) and a further 25% were experiencing minor delays (RAG: Amber) but remained deliverable within the current or next financial year 2. Approve the implementation of mitigation measures for schemes at risk of delay or underspend — particularly those in the Carriageways, Structures & Bridges, and Stainton Way Phase 2 schemes — to ensure continued alignment with CRSTS grant conditions, avoid clawback risk, and maintain the Council’s ability to meet statutory obligations. AGREED that Executive 1. Note the progress to date on the delivery of the 2025/26 Capital Programme funded through the £4.154m City Region Sustainable Transport Settlement (CRSTS) grant, as detailed in Appendices 1 and 1A of the report. 2. Note ongoing programme management flexibilities, allowing officers to reprofile or reallocate approved funds where appropriate to support accelerated delivery of shovel-ready schemes or respond to emerging priorities.
Word for word from the decision Middlesbrough published for this meeting. Source: moderngov.middlesbrough.gov.uk

Follow this further

Built from Middlesbrough's papers

What the report saysPro

Report to Executive
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
2025/26 Transport and Infrastructure Capital Programme UpdateReport 335 KB Copy on its way
PDF
/49Appendix 1 468 KB Copy on its way
PDF
/49Appendix 1a 481 KB Copy on its way

At this meeting

Whole meeting

On this subject at Middlesbrough

Search all
  1. 2025/26 Transport and Infrastructure Capital Programme UpdateThis decision
  2. Transport and Infrastructure Capital Programme 2026/27Approved
  3. 2024/2025 Transport and Infrastructure Capital ProgrammeApproved

More from Middlesbrough Executive

All decisions
MeetingDecisionOutcome
2 Sep 2026 Final Report of the Overview and Scrutiny Board - The Council's Approach to PovertyORDERED that the Executive: 1. Note the report of the Overview and Scrutiny Board on The Council’s Approach to Povert... Noted Open
2 Sep 2026 Risk and Opportunity Management PolicyORDERED that Executive approve the 2026–2029. Approved Open
2 Sep 2026 Place Strategy to Investment ProspectusORDERED that Executive: 1. Note the work undertaken by the Place Leaders Partnership to develop a Place Strategy for ... Noted Open
2 Sep 2026 Cremator Refurbishment ProgrammeORDERED that Executive: 1. Approve the inclusion of the Teesside Crematorium in the Council’s Capital Programme, and ... Approved Open
2 Sep 2026 Stainton Way Highway ImprovementsORDERED that Executive approve the Stainton Way Highway improvements scheme, considering the issues raised and propos... Approved Open