Investment into Housing to Reduce Temporary Accommodation Costs
ApprovedExecutive1 paper
AI summaryMiddlesbrough Executive approves using £3.6m of Section 106 affordable housing contributions to replace a Towns Fund grant, restoring the £6.141m housing pot and widening the options to secure properties for people at risk of homelessness.
Money£3.6mSection 106 to replace £3.6m Towns Fund grant
What happens next30 June 2026Deadline to secure first empty properties
Who it affectsPeople at risk of homelessnessIn Middlesbrough, including families and care leavers
What was decided
Use £3.6m of retained Affordable Housing Section 106 developer contributions to replace the Towns Fund grant and bring the funding pot back to £6.141m. Report P4
Approve a wider menu of options to secure properties, including direct purchase, a loan to The Ethical Housing Company, a social investment fund and third-party partnerships, to allow greater impact, flexibility and value for money than the original direct-purchase approach. Report P4, 4.4
Delegate the appointment of providers from within the approved menu to the Chief Officer for Regeneration, in consultation with the Chief Financial Officer and the Executive Member for Development. Report P4
Why
The Council faces rising costs from expensive temporary accommodation for people experiencing homelessness, and additional delivery options have been identified that spread risk and use partner expertise to deliver more properties for the same investment. Report 3.1, 4.2, 4.3
In November 2025, £3.6m of the original Towns Fund allocation was redirected to the Middlehaven development project, so Section 106 affordable housing contributions are being used to restore the £6.141m total. Report P4, 4.19, 4.20
Using Section 106 funds for refurbishing empty properties is consistent with the legal definitions governing how those contributions can be spent. Report 4.20
What happens next
The Head of Strategic Housing will use the allocated funds to secure the first empty properties by 30 June 2026. Report P65
Further reports will be brought to Executive to update on the balance of options used and the financial benefits achieved. Report 4.18
Decisions on each option will be taken using a cost and benefit analysis that balances value for money, risk and impact across the full funding package, and any tenant support contracts will still go through the Council's normal governance and legal processes. Report 4.16, 4.17
The money
£3.6m Section 106 affordable housing contributions replacing the Towns Fund grant Report P4
£6.141m Total funding pot restored for securing properties Report P4, 4.1
£4m Towns Fund grant originally allocated in December 2024 Report P2, 4.1
£2.141m Levelling Up Partnership grant originally allocated in December 2024 Report P2, 4.1
£1m Proposed additional loan facility to The Ethical Housing Company, at 5% interest Report 4.6, 4.7
£0.77m Remaining loan allocation to be made available to EHC under a second loan Report P15
£5m Proposed investment into the Resonance social investment fund Report 4.9, 4.10
£0.170m Forecast annual revenue return from the Resonance fund (around 3.5%) Report 4.10
£0.050m Possible annual return on the EHC investment, depending on drawdown Report 4.21
£0.017m Estimated annual reduction in temporary accommodation cost per fully utilised property Report 4.23
Options considered
Chosen: Wider menu of delivery options (direct purchase, EHC loan, Resonance fund, third-party partnerships). Spreads risk, uses partner expertise and offers flexibility and better value than direct purchase alone Report P4, 4.3, 4.4
Chosen: Up to £1m additional loan to The Ethical Housing Company at 5% interest. Could bring up to 25 additional empty properties back into use with Council nomination rights Report 4.6, 4.7
Chosen: £5m investment into the Resonance Evergreen social investment fund. Could acquire and refurbish around 40 empty properties, with forecast 3.5% annual return and nomination rights Report 4.9, 4.10
Chosen: Third-party partnerships and contracts, including leasing, acquisition via a third party and private rented sector access. Lower-risk, more flexible ways to secure properties where the market is changing or needs are specific Report 4.13, 4.14
Rejected: Do nothing. Forecast continued rises in temporary accommodation costs, churn in placements and repeat homelessness Report 6.2, 6.3, 6.4
Implications
Financial: The £3.6m S106 funds already sit within the Council's capital programme; any returns from the properties are intended to be reinvested in further homelessness prevention activity, and the Council will need to monitor whether the property portfolio ever triggers the requirement to operate a Housing Revenue Account. Report P57, 4.24, 4.25
Legal: All existing Section 106 planning agreements are subject to individual conditions and defrayal deadlines; failure to observe them could expose the Council to refund obligations to developers, and all loan, grant, investment and partner contracts must be reviewed by Legal Contracts and comply with procurement rules. Report P58, P60, P61, P62
Risk: Using a range of more flexible options rather than a single direct-purchase approach is intended to minimise the Council's risk. Report P58, 4.14
Equalities: Access to a safe home is identified as a basic human right; the proposal is expected to support the Public Sector Equality Duty, reduce poverty, aid community cohesion and provide more options for children, young people and care leavers. Report P63
Staffing: Finance and Procurement will review any options outside the EHC and Resonance investments to ensure value for money, grant and procurement compliance before engagement with providers. Report P57
Other: No climate change or environmental impact is identified, and no ward-member engagement has been carried out because the initiative is town-wide. Report 5.1, P63
Who and where
People at risk of homelessness in Middlesbrough, including families and individuals with complex needs Report 3.1, 4.2, P63
Children, young people and care leavers supported by the Authority Report P63
The Ethical Housing Company Middlesbrough Limited, as recipient of a proposed additional loan Report P13, 4.5, 4.6
Resonance, as the social investment fund provider Report 4.9
Middlesbrough Development Company, whose existing EHC loan is being assigned to the Council as part of MDC's closure Report 4.5
Developers who have paid Section 106 affordable housing contributions, whose defrayal deadlines must be observed Report P58, P60
Timeline
December 2024: Executive approved £6.141m from Towns Fund and Levelling Up grants to purchase properties and reduce temporary accommodation use Report P2, 4.1
12 November 2025: Executive, within the Middlehaven Housing report, redirected £3.6m of the Towns Fund grant to the appointment of Capital and Centric as development partner Report P4, 4.19
21 January 2026: Executive approves the recommendations in this report
30 June 2026: Deadline to secure the first empty properties using the allocated funds Report P65
Plain English for the jargon
Temporary accommodation (TA): Short-term external housing arranged by the Council for people who are homeless or at risk of homelessness, which is expensive and in limited supply
Section 106 (S106) contributions: Developer contributions for affordable housing negotiated through planning agreements under the Town and Country Planning Act 1990, subject to specific conditions and spending deadlines
Towns Fund: Government grant funding originally allocated to Middlesbrough to support town centre and regeneration projects
Levelling Up Partnership grant: Government grant used alongside the Towns Fund to fund property acquisition for homelessness prevention
Resonance: A UK social impact investment company that would run an Evergreen Fund acquiring and refurbishing properties in Middlesbrough
The Ethical Housing Company Middlesbrough Limited (EHC): A local organisation that purchases and refurbishes empty properties, with an existing loan from Middlesbrough Development Company being assigned to the Council
Housing Revenue Account (HRA): A separate statutory account a council must operate if it holds a large portfolio of dwellings; the report says the proposed actions would not yet trigger this requirement
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item25/91
Resolved
ORDERED that Executive: 1. Approves the utilisation of £3.6m of retained Affordable Housing Section 106 developer contributions to replace the Towns Fund grant and bring the available resources back to the previously approved £6.141m; 2. Approves a revised menu of options to secure properties to alleviate the need for expensive temporary accommodation that would enable greater impact, flexibility and value for money than those previously proposed; and, 3. Delegates decisions relating to the appointment of the providers from within the menu of options to the Chief Officer with responsibility for Regeneration in consultation with the Chief Financial Officer, and the Executive Member with responsibility for Development. AGREED that Executive: 1. Notes the decision of Executive, in December 2024, to invest resources from the Towns Fund grant (£4m) and Levelling Up Partnership grant (£2.141m) to secure properties to alleviate the need for expensive temporary accommodation solutions. 2. Notes the subsequent decision of Executive, on 12 November 2025, within the Middlehaven Housing report to utilise £3.6m of the aforementioned Towns Fund grant for the appointment of Capital and Centric as the Council’s development partner.
Word for word from the decision Middlesbrough published for this meeting.Source: moderngov.middlesbrough.gov.uk
Report of: Director of Regeneration - Richard Horniman
Relevant Executive Executive Member for Development - Theo Furness Member:
Submitted to: Executive
Date: 21 January 2026
Title: Investment into Housing to Reduce Temporary Accommodation Costs
Report for: Decision
Status: Public
Council Plan A successful and ambitious town priority:
Key decision: Yes Why: Decision(s) will incur expenditure or savings above £250,000
Subject to call in? Yes Why: This is a non-urgent report
Proposed decision(s) It is recommended that Executive: a) notes the decision of Executive in December 2024 to invest resources from the Towns Fund grant (£4m) and Levelling Up Partnership grant (£2.141m) to secure properties to alleviate the need for expensive temporary accommodation solutions; b) notes the subsequent decision of Executive on 12 November 2025, within the Middlehaven Housing report to utilise £3.6m of the aforementioned Towns Fund grant for the appointment of Capital and Centric as the Council’s development partner; c) approves the utilisation of £3.6m of retained Affordable Housing Section 106 developer contributions to replace the Towns Fund grant and bring the available resources back to the previously approved £6.141m; d) approves a revised menu of options to secure properties to alleviate the need for expensive temporary accommodation that would enable greater impact, flexibility and value for money than those previously proposed; and, e) delegates decisions relating to the appointment of the providers from within the menu of options to the Chief Officer with responsibility for Regeneration in
May 2025 onwards 1 This document was classified as: OFFICIAL
consultation with the Chief Financial Officer, and the Executive Member with responsibility for Development.
Executive summary In December 2024 Executive approved the utilisation of £6.141 of external grant for the purchase of properties to ultimately reduce the need for the Council to put clients in expensive temporary accommodation. The report proposed that the Council would directly purchase around 65 properties. Since the report was approved, a number of different options for securing access to properties have been identified, that may offer a more cost effective route. This report proposes an additional ‘menu’ of different options that may be utilised, which includes a significant investment in a social impact fund. The recommendations are seeking approval to utilise this menu of options to provide the best possible mix of properties.
1. Purpose of this report and its contribution to the achievement of the Council Plan ambitions
1.1The report seeks Executive approval to utilise grant funding and Section 106 resources to secure properties to alleviate the need for expensive temporary accommodation (TA) solutions via a range of options as detailed within the report. This will contribute to the achievement of the Council Plan ambitions as detailed in the following table:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Place Strategy to Investment ProspectusORDERED that Executive: 1. Note the work undertaken by the Place Leaders Partnership to develop a Place Strategy for ...
Cremator Refurbishment ProgrammeORDERED that Executive: 1. Approve the inclusion of the Teesside Crematorium in the Council’s Capital Programme, and ...
Stainton Way Highway ImprovementsORDERED that Executive approve the Stainton Way Highway improvements scheme, considering the issues raised and propos...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.