AI summaryMiddlesbrough Executive approves refreshed Council Plan 2026-29, ends the Transformation Programme in favour of a Continuous Improvement model, and backs development of a Place Strategy.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedCouncil Plan 2026-29 and related changes
MoneyNot stated
What happens nextNot stated
Who it affectsResidents, council directorates, partnersCustomer, Digital, Housing and Neighbourhoods workstreams
What was decided
Approved the refreshed Council Plan 2026-29, including minor amendments splitting digital and transport connectivity into separate outcomes. Report 2.1, 4.1, 4.2
Approved ending the Transformation Programme and moving to a Continuous Improvement model within business-as-usual operations. Report 2.1, 4.3, 4.4, 4.5
Endorsed the Place Leaders Partnership developing a Place Strategy for the town, with the Council joining that partnership. Report 2.1, 4.11, 4.12
Why
The Council is legally required under the Local Government Act 1999 to demonstrate Best Value and continuous improvement in how it works. Report 3.1
The Transformation Programme, set up in 2024, has met its financial objectives and standalone programme governance is no longer proportionate. Report 4.3, 4.4
Refreshing the Plan keeps the medium-term business plan aligned with the Council's vision and priorities, agreed by Executive in December 2025. Report 4.1, 4.2
What happens next
Publish the refreshed Council Plan on the Council's website and communicate it to staff by 31 March 2026. Report P43
Bring revised Performance Management and Programme and Project Management Policies to Executive by 30 April 2026. Report 4.8, 4.9, P43
Options considered
Rejected: Do not refresh the Council Plan or its measures of success. The Plan would not give a reliable blueprint against which to set supporting plans, strategies and policies. Report 6.1
Implications
Legal: Implementation supports the Council's statutory Duty of Best Value and continued delivery of statutory duties. Report 3.1, P40
Financial: Annual revenue and capital budgets are developed in parallel to align spending with the Plan's ambitions. Report P40
Risk: Delivering the outcomes would address key risks on the Council's Strategic Risk Register. Report P40
Equalities: Impact assessment found the Plan will have a positive impact on individuals and communities and takes an inclusive approach for all residents. Report P40
Other: Plan expected to have a positive impact on reducing poverty, making it central to the Council's work. Report P40
Climate: Plan expected to have a positive impact on climate and the environment through relevant priorities. Report P40
Other: Plan expected to have a positive impact on children and young people, including on educational attainment. Report P41
Staffing: Move from centralised transformation to local accountability within Directorates, supported by enabling functions. Report P12
Who and where
Middlesbrough residents, including vulnerable residents facing housing need Report P27, P28, P40
Council directorates taking on ownership of continuous improvement Report P12, 4.5
Public, private and voluntary sector partners in the Place Leaders Partnership Report 4.11, 4.12
Customers of the Council's customer-facing functions Report P20, P21
Neighbourhoods in the North, South, East and West of the town Report P30
Timeline
2024: Transformation Programme established in response to financial pressures. Report 4.3
December 2025: Executive agreed the outcomes for the Council Plan. Report 4.1, P45
31 March 2026: Publish refreshed Council Plan on website and to staff. Report P43
8 April 2026: Report to Executive on Pride in Place Programme delivery in Middlesbrough. Report P43
30 April 2026: Submit revised Performance Management Policy to Executive. Report P43
30 April 2026: Submit revised Programme and Project Management Policy to Executive. Report P43
Spring 2026: Place Leaders Partnership public consultation on emerging vision and priorities. Report 4.13
June 2026: Draft Digital Strategy to be presented to Executive for consideration. Report P27
Early Autumn 2026: Planned adoption of the Place Strategy by all partners in the partnership. Report 4.13
Plain English for the jargon
Best Value: Duty under the Local Government Act 1999 requiring councils to arrange continuous improvement in how they work.
Transformation Programme: Time-limited programme set up in 2024 to stabilise the Council, deliver savings and maintain statutory services.
Continuous Improvement: New operating model replacing the Transformation Programme, embedding improvement in everyday operations owned by Directorates.
Place Leaders Partnership: Multi-sector partnership of public, private and voluntary organisations set to develop a Place Strategy for Middlesbrough.
Neighbourhoods model: Locality-based working model agreed by Executive in April 2025, delivering place-based support alongside universal customer services.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item25/118
Resolved
ORDERED that Executive: 1. Approves the refreshed Council Plan which set out how the Council would measure success, following previous agreement of the outcomes in December 2025 by Executive. 2. approves further minor amendments to the outcomes agreed by executive in December 2025 to create separate outcomes for digital and transport connectivity and minor, non-material changes to sentence structure to enhance readability and did not change the nature of the agreed outcomes. 3. Approves the cessation of the Council’s transformation programme and transition into a continuous improvement model. 4. Approves the transition of the customer strategy and the Neighbourhoods model into business-as-usual delivery. 5. Approves the Council’s engagement in the place leader’s partnership, its membership on that partnership. 6. Endorses the planned development of a place strategy for the town, to be led by the place leader’s partnership.
Word for word from the decision Middlesbrough published for this meeting.Source: moderngov.middlesbrough.gov.uk
Relevant Executive The Elected Mayor of Middlesbrough, Chris Cooke Member:
Submitted to: Executive
Date: 11 March 2026
Title: Council Plan 2026-29
Report for: Decision
Status: Public
Council Plan Delivering Best Value priority:
Key decision: No Why: Decision does not reach the threshold to be a key decision
Subject to call in? Yes Why: Non-Urgent Report
Proposed decision(s) That Executive:
APPROVES the refreshed Council Plan which sets out how the Council will measure success, following previous agreement of the outcomes in December 2025 By Executive. APPROVES further minor amendments to the outcomes agreed by Executive in December 2025 to create separate outcomes for digital and transport connectivity and minor, non-material changes to sentence structure to enhance readability and do not change the nature of the agreed outcomes. APPROVES the cessation of the Council’s Transformation Programme and transition into a Continuous Improvement model. APPROVES the transition of the Customer Strategy and the Neighbourhoods Model into business-as-usual delivery. APPROVES the Council’s engagement in the Place Leaders Partnership, its membership on that Partnership. ENDORSES the planned development of a Place Strategy for the Town, to be led by the Place Leaders Partnership.
Executive summary This document was classified as: OFFICIAL
This report seeks Executive approval of the refreshed Council Plan, setting out the refreshed Outcomes that were agreed by Executive in December 2025, alongside the indicators that will measure the impact of that activity, as set out in the refreshed Council Plan appended to this report at Appendix 1.
The Council Plan is the organisation’s overarching business plan for the medium-term and is typically refreshed on an annual basis. This refresh follows a review of performance in the previous year and consideration of an outcome-driven approach to demonstrate progress and impact, which was agreed as the direction of travel at Executive in December 2025.
The Council Plan is part of the Council’s Policy Framework and so requires the approval of Full Council, as set out in the Constitution. The Council’s Budget and Policy Framework Procedure Rules provide for the Executive to draw up firm proposals on the Strategic Plan for submission to Full Council. Full Council approved the Council Plan for the period 2024-27 on 28 February 2024, which was structured around the following vision and priorities:
The vision for Middlesbrough is a thriving, healthier, safer and more ambitious place where people want to live, work, invest, and visit. We will support our residents to live fulfilling lives, to ensure that our communities thrive, with the four priorities remaining, as follows:
A Successful and Ambitious Town: Maximising economic growth, employment, and prosperity, in an inclusive and environmentally sustainable way. A Healthy Place: Helping our residents to live longer and healthier lives, improving life chances and opportunities to thrive. Safe and Resilient Communities: Creating a safer environment where residents can live more independent lives. Delivering Best Value: Changing how we operate, to deliver affordable and cost- effective outcomes for residents and businesses.
The vision and priorities will remain; this report seeks to refresh the underpinning activity to deliver the vision. The activity set to deliver the Council Plan will be embedded within Directorate Plans to ensure effective delivery. The Directorate Plans will form a key part of the Council’s approach to performance management and continuous improvement.
The report also sets out the planned development of a Place Strategy by the Place Leaders Partnership and proposes that Executive endorses the Council working with the partnership to develop that Strategy.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Place Strategy to Investment ProspectusORDERED that Executive: 1. Note the work undertaken by the Place Leaders Partnership to develop a Place Strategy for ...
Cremator Refurbishment ProgrammeORDERED that Executive: 1. Approve the inclusion of the Teesside Crematorium in the Council’s Capital Programme, and ...
Stainton Way Highway ImprovementsORDERED that Executive approve the Stainton Way Highway improvements scheme, considering the issues raised and propos...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.