CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Middlesbrough Borough Council
Executive, Wednesday 8 April 2026 at 5.00pm

Performance and Financial Management Policy and Programme and Project Management Policy Review

Approved Executive 5 papers

AI summaryMiddlesbrough Executive approves new Performance and Financial Management Policy and Programme and Project Management Policy, with Directorate Business Plans to be developed during 2026/27.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedPerformance policy, PPM policy, Directorate Business Plans
MoneyNo sums in reportNo financial figures quoted
What happens nextImplementation during 2026/27First reporting from end of Quarter One 2026/27
Who it affectsAll council directorates and staffAligns activity to the Council Plan

What was decided

The Executive approved the Performance and Financial Management Policy, which combines performance, finance and risk in one process. Report 4.1, 4.2

The Executive approved the Programme and Project Management Policy, reviewed on a three-year cycle, to govern complex change activity. Report 4.9, 4.11

The Executive approved the Directorate Business Plan development plans set out in paragraphs 4.4 to 4.8, to be built during 2026/27. Report 4.4, 4.5, 4.6

Why

The policies embed a single, integrated view of performance, finance and risk to support delivery of the Council Plan and Best Value. Report 3.1, P5, P46

A clear golden thread is intended from the Council Plan, through Directorate Business Plans, to individual officer appraisals. Report 1.1, 4.7

The framework is needed to provide proportionate governance for complex, high risk or high cost change activity, while keeping low risk tasks as business as usual. Report 1.2, 4.12, 4.13, 4.14

What happens next

The Head of the Chief Executive's Department and the Section 151 Officer will reflect the new policy in an integrated outturn report from the end of Quarter One 2026/2027, with a deadline of 30 September 2026. Report P52

Directorate Business Plans will be developed during 2026/27 and refreshed yearly to align with the Council Plan refresh cycle. Report 4.4, 4.8

The supporting Programme and Project Management Framework will be updated during 2026/27 to align with the new policy. Report 4.11

Options considered

  • Rejected: Keep a separate approach to performance and financial budget management and reporting. Would reduce ability to identify trends earlier for correction or exploitation Report 6.1
  • Rejected: Keep current project thresholds and PPM governance arrangements. Would not align with the new performance and financial management approach or Best Value principles Report 6.2

Implications

  • Legal: Provides a framework to demonstrate ongoing compliance with the Best Value Duty. Report P46
  • Risk: Particularly relevant to risks SR01 (failure to maintain a balanced budget and MTFP) and SR09 (corporate governance fit for purpose), and positively affects all risks on the Strategic Risk Register. Report P46, P47, P48
  • Equalities: Impact assessments found positive impact: routine consideration of outcomes for people with protected characteristics, and structured equality impact consideration within projects. Report P48
  • Climate: Positive impact on climate and environmental objectives through consistent monitoring and reporting of relevant data. Report P50
  • Other: Supports the Council Plan commitment to put tackling poverty at the heart of everything the Council does, and delivery for children in care and care leavers. Report P50
  • Other: Reinforces existing UK GDPR and data protection requirements for performance and project data. Report P50

Who and where

  • All council directorates, who will develop new Directorate Business Plans during 2026/27 Report 4.4, 4.5
  • Council staff, through appraisal objectives linked to the Council Plan Report 1.1
  • Members of the Executive, who will see the impact of the policy in reporting from the end of Quarter One 2026/27 Report 4.8
  • Residents, via improved outcomes delivered through the Council Plan Report P5, P11

Timeline

  • 2026/27: New policy to be implemented and supporting performance and financial management cycle put in place Report 4.4
  • During 2026/27: Directorate Business Plans to be developed, then refreshed yearly Report 4.4
  • During 2026/27: Programme and Project Management Framework to be updated to align with the new policy Report 4.11
  • End of Quarter One 2026/2027: First reporting reflecting the new integrated policy expected Report 4.8, P52
  • 3 December 2025: Council Plan 2026-29 reported to Executive Report P54
  • 30 September 2026: Deadline for the integrated performance and financial outturn report Report P52

Plain English for the jargon

  • Golden thread: A clear line of alignment from the Council Plan, through Directorate Business Plans, to individual staff appraisals.
  • PPM: Programme and Project Management, covered by the proposed policy and its supporting Programme and Project Management Framework (PPMF).
  • Best Value Duty: The council's ongoing legal duty to make arrangements to secure continuous improvement in how it exercises its functions.
  • SMART: Specific, measurable, achievable, relevant and time-bound objectives, as set out in the policy principles.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item25/132

Resolved

ORDERED that Executive: 1. Approved the Performance and Financial Management Policy; 2. Approved the Programme and Project Management Policy; and 3. Approved the Directorate Business Plan development plans as set out at paragraphs 4.4 to 4.8 of the report
Word for word from the decision Middlesbrough published for this meeting. Source: moderngov.middlesbrough.gov.uk

Follow this further

Built from Middlesbrough's papers

What the report saysPro

Report to Executive

Executive summary

The Council Plan is the organisation’s overarching business plan for the medium-term and sets the vision and priorities for the Council.

This report proposes agreement of a Performance and Financial Management Policy, which sets out how the Council will ensure that arrangements are in place to:

- Align directorate and workforce activities and performance focus with the Council Plan

May 2025 onwards report format 1 This document was classified as: OFFICIAL

- Provide a holistic view of performance, financial resources and risk to enable the Council to identify and address underperformance and risks and maximise its ability to deliver the Council Plan vision.

This report also seeks approval of planned development of Directorate Business Plans during 2026/27 which will include development and implementation of a template that will be used to capture the key business information of each Directorate and clearly set out their contributions to the Council Plan, key activities and functions to be delivered by them and the Key Performance Indicators that will be used to assess the impact of that activity.

There will be times when the Council still needs to take significant change activity, as part of its commitment to continuous improvement. Where this activity is likely to be particularly complex, innovative or carries significant risks and / or costs, the Council will put additional governance in place to deliver this. It will use the proposed Programme and Project Management Policy to do this. This report seeks approval of that policy.

1. Purpose of this report and its contribution to the achievement of the Council Plan priorities

1.1The purpose of this report is to ensure the Council puts in place the necessary arrangements to enable it to maximise delivery of the Council Plan within a proportionate and robust governance framework. It aims to ensure the Council Plan is fully embedded within the Council’s Performance Management arrangements, creating a clear ‘golden thread’ from the Council Plan, through Directorate Business Plans, wider plans, and other policies and strategies, down to the appraisal objectives of individual officers.

1.2Approval of the Programme and Project Management Policy will also support delivery of the Council Plan by providing a governance framework that will support delivery of time limited project activity that has been identified as necessary to improve outcomes and / or ensure ongoing compliance with legislative requirements and good practice.

Our Priorities Summary of how this report will support delivery the Council Plan A successful and The refreshed Council Plan sets out the outcomes that will be achieved ambitious town to deliver its vision. This report will ensure the Council has effective A healthy place arrangements in place to drive achievement of that vision. Safe and resilient communities Delivering best value

Recommendations

2.1That the Executive: • APPROVES the Performance and Financial Management Policy • APPROVES the Programme and Project Management Policy. • APPROVES the Directorate Business Plan development plans as set out at paragraphs 4.4 to 4.8.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Performance and Financial Management Policy 2026-9 /132Appendix 1 307 KB Download
PDF
Equality Impact Assessment Performance and Financial Management Policy /132Appendix 2 116 KB Download
PDF
Programme and Project Management Policy /132Appendix 3 229 KB Download
PDF
Equality Impact Assessment Programme and Project Management Policy /132Appendix 4 114 KB Download
PDF
Performance and Financial Management Policy and Programme and Project Management Policy ReviewReport 174 KB DownloadRead as text

At this meeting

Whole meeting

More from Middlesbrough Executive

All decisions
MeetingDecisionOutcome
2 Sep 2026 Final Report of the Overview and Scrutiny Board - The Council's Approach to PovertyORDERED that the Executive: 1. Note the report of the Overview and Scrutiny Board on The Council’s Approach to Povert... Noted Open
2 Sep 2026 Risk and Opportunity Management PolicyORDERED that Executive approve the 2026–2029. Approved Open
2 Sep 2026 Place Strategy to Investment ProspectusORDERED that Executive: 1. Note the work undertaken by the Place Leaders Partnership to develop a Place Strategy for ... Noted Open
2 Sep 2026 Cremator Refurbishment ProgrammeORDERED that Executive: 1. Approve the inclusion of the Teesside Crematorium in the Council’s Capital Programme, and ... Approved Open
2 Sep 2026 Stainton Way Highway ImprovementsORDERED that Executive approve the Stainton Way Highway improvements scheme, considering the issues raised and propos... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies