Middlesbrough Borough Council
Audit Committee, Thursday 16 April 2026 at 1.30pm

Programme and Project Management Framework - Annual Assurance Report

Agreed Finance 1 paper

AI summaryMiddlesbrough Audit Committee accepts assurance that programme and project management arrangements are adequate, despite only 76% of projects on track against a 90% target.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedCommittee noted PPM arrangements and agreed they are adequate
MoneyNo new direct financial implicationsSavings from closed Red projects to be found elsewhere
What happens nextRefresh of PPMF and project documentationPlanned for 2026/27 alongside Continuous Improvement model
Who it affectsCouncil programme and project portfolio40 projects in 2025/26 corporate portfolio

What was decided

The Committee noted the arrangements in place to manage programmes and projects within the Council. Report 2.1

The Committee considered the information provided offered sufficient assurance that appropriate arrangements are in place for programme and project management. Report 2.1

Why

The PMO provides strategic oversight of the Council's portfolio under the Programme and Project Management Framework, supported by standardised templates and periodic health checks. Report 3.2, 3.3, 3.4

Performance reporting shows 76% of corporately monitored projects were Green or Amber at the end of February 2026, below the 90% target. Report 3.9, P15

Eight of nine Red projects are transformation projects with financial savings; the Transformation Programme was ended by the Executive on 11 March 2026, and the Council is moving to a Continuous Improvement model. Report 3.10, 3.16

What happens next

The PMO will review legacy transformation projects in 2026/27, continuing some within the corporate portfolio and transitioning others to business-as-usual. Report 3.17

A refresh of the Programme and Project Management Framework and project documentation is planned for 2026/27, alongside a revised project categorisation scoring tool and a Centre of Excellence model. Report 3.18, 3.19, 3.20

Directorates must identify alternative savings proposals where Red projects with attached savings are closed. Report 3.11

Options considered

  • Chosen: Accept assurance from the report as adequate. The report provides a detailed overview of governance arrangements in place Report 4.1
  • Rejected: Request further information on programme and project governance. Not recommended because the report already gives a detailed overview of governance arrangements Report 4.1

Implications

  • Financial: Projects with financial savings that can no longer be achieved will be closed and Directorates will need to find alternative savings proposals. Report 3.11, P33
  • Risk: No new direct risk implications; the PPM framework already supports identification and management of programme and project risks aligned to the Council's corporate approach. Report P33
  • Equalities: No direct implications on human rights, equality or diversity; projects must complete an Equality Impact assessment as part of the business case before approval. Report P33
  • Legal: No new direct legal implications arising from the report. Report P33
  • Other: Some planned improvements were not delivered in 2025/26 due to capacity constraints within the PMO; PMO manager capacity has been increased to carry these forward in 2026. Report 3.14

Who and where

  • The Portfolio Management Office (PMO) Report 3.2, 3.14
  • Directorates delivering programmes and projects Report 3.7, 3.11
  • Programme and Project Managers and Sponsors Report 3.20

Timeline

  • End of February 2026: 76% of corporately monitored projects rated Green or Amber, below 90% target Report 3.9, P15
  • 11 March 2026: Executive approved ending the Transformation Programme in its current form and moving to Continuous Improvement Report 3.10, 3.16
  • Early 2026: PMO refreshed the Programme and Project Management Policy to reflect the new Continuous Improvement direction Report 3.15
  • 2026/27: Planned refresh of the PPMF, project documentation and categorisation scoring tool, and launch of a Centre of Excellence model Report 3.17, 3.18, 3.19, 3.20
  • April 2026: Revised performance and financial management policy due to be considered by Executive Report 3.17

Plain English for the jargon

  • PMO: Portfolio Management Office, the team providing strategic oversight of the Council's programme and project portfolio
  • PPMF: Programme and Project Management Framework, the Council's standardised approach to governance and management
  • RAG: Red, Amber, Green indicators used to rate how well a project is delivering against expectations
  • BAU: Business as usual, the routine running of services outside of formal project management
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item25/7

Resolved

AGREED that: 1. The arrangements in place to manage programmes and projects within the Council be noted. 2. The Committee considered that the information provided offered sufficient assurance that appropriate arrangements are in place in relation to programme and project management.
Word for word from the decision Middlesbrough published for this meeting. Source: moderngov.middlesbrough.gov.uk

Follow this further

Built from Middlesbrough's papers

What the report saysPro

Report to Audit Committee

Recommendations

2.1That the Committee:

• NOTES the arrangements in place to manage programmes and projects within the Council. • CONSIDERS whether the information provided has given the Committee sufficient assurance that the Council has appropriate arrangements in place in relation to programme and project management.

3. Background and relevant information

3.1The purpose of this report is to outline the Council’s Programme and Project Management (PPM) approach, summarise project performance for 2025/26, and set out planned PPM developments for 2026 and beyond, providing assurance that robust PPM arrangements are in place to support delivery of the Council Plan ambitions.

3.2The PMO has responsibility for the strategic oversight of the Council’s portfolio of programmes and projects that follow the corporate Programme and Project Management Framework (PPMF), which ensures a consistent approach to the governance and management of programmes and projects.

3.3The PPMF is supported by a set of standardised project templates and provides clear guidance for managing programmes and projects at every stage of their lifecycle, helping to further embed the framework and methodology across the Council.

3.4Compliance with the PPMF is assured through periodic project health checks, and performance is reported quarterly to the Executive within the performance outturn report.

3.5The Council maintained a portfolio of corporate and transformation programmes and projects in 2025/26 to support of achievement of the Council’s strategic priorities.

3.6During 2025/26 projects within the Transformation Portfolio were reviewed to ensure ongoing alignment with transformation themes. Some were incorporated into the Council’s overarching portfolio of corporate programmes and projects as a result, with progress against performance reported accordingly.

3.7Monthly Directorate and Corporate Performance Boards were in place in 2025/26 and included monitoring the performance of progress against the delivery of all This document was classified as: OFFICIAL

strategic programmes and projects, Executive actions and Council Plan workplan initiatives.

Performance of programmes and projects in 2025/26

3.8During 2025/6 there were 40 projects in the corporate portfolio at the point of reporting. Projects are categorised as either Level 1 (the most complex projects) or Level 2 (lighter-touch projects), and their performance is assessed and reported using Red, Amber, and Green (RAG) indicators that measure how well the project is delivering against expectations.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Programme and Project Management Framework: Annual Assurance ReportReport 132 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Middlesbrough

Search all
  1. Programme and Project Management Framework - Annual Assurance ReportThis decision
  2. Performance and Financial Management Policy and Programme and Project Management Policy ReviewApproved
  3. Programme and Project Management Framework AssuranceAgreed

More from Middlesbrough Audit Committee

All decisions
MeetingDecisionOutcome
25 Jun 2026 Management of Strategic Risk 17 - Funding for Key External Projects led by TVCA or MDCAGREED that: 1. The latest position regarding Strategic Risk 17 be noted. 2. The Committee considered that it had rec... Agreed Open
25 Jun 2026 Training Programme for Audit Committee MembersAGREED that: 1. The proposed Audit Committee Member training programme for 2026/27 be approved. 2. Attendance at iden... Agreed Open
25 Jun 2026 Head of Internal Audit Annual Report 2025/26AGREED that: 1. The report be noted. 2. The Corporate Director of Finance present a report to the September 2026 meet... Agreed Open
25 Jun 2026 Outcome of the Review of Internal AuditAGREED that: 1. The findings of the review of the Council’s current internal audit arrangements be noted. 2. The prop... Agreed Open
25 Jun 2026 Counter Fraud Annual ReportAGREED that: 1. The 2025/26 be noted. Agreed Open