Programme and Project Management Framework - Annual Assurance Report
AgreedFinance1 paper
AI summaryMiddlesbrough Audit Committee accepts assurance that programme and project management arrangements are adequate, despite only 76% of projects on track against a 90% target.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedCommittee noted PPM arrangements and agreed they are adequate
MoneyNo new direct financial implicationsSavings from closed Red projects to be found elsewhere
What happens nextRefresh of PPMF and project documentationPlanned for 2026/27 alongside Continuous Improvement model
Who it affectsCouncil programme and project portfolio40 projects in 2025/26 corporate portfolio
What was decided
The Committee noted the arrangements in place to manage programmes and projects within the Council. Report 2.1
The Committee considered the information provided offered sufficient assurance that appropriate arrangements are in place for programme and project management. Report 2.1
Why
The PMO provides strategic oversight of the Council's portfolio under the Programme and Project Management Framework, supported by standardised templates and periodic health checks. Report 3.2, 3.3, 3.4
Performance reporting shows 76% of corporately monitored projects were Green or Amber at the end of February 2026, below the 90% target. Report 3.9, P15
Eight of nine Red projects are transformation projects with financial savings; the Transformation Programme was ended by the Executive on 11 March 2026, and the Council is moving to a Continuous Improvement model. Report 3.10, 3.16
What happens next
The PMO will review legacy transformation projects in 2026/27, continuing some within the corporate portfolio and transitioning others to business-as-usual. Report 3.17
A refresh of the Programme and Project Management Framework and project documentation is planned for 2026/27, alongside a revised project categorisation scoring tool and a Centre of Excellence model. Report 3.18, 3.19, 3.20
Directorates must identify alternative savings proposals where Red projects with attached savings are closed. Report 3.11
Options considered
Chosen: Accept assurance from the report as adequate. The report provides a detailed overview of governance arrangements in place Report 4.1
Rejected: Request further information on programme and project governance. Not recommended because the report already gives a detailed overview of governance arrangements Report 4.1
Implications
Financial: Projects with financial savings that can no longer be achieved will be closed and Directorates will need to find alternative savings proposals. Report 3.11, P33
Risk: No new direct risk implications; the PPM framework already supports identification and management of programme and project risks aligned to the Council's corporate approach. Report P33
Equalities: No direct implications on human rights, equality or diversity; projects must complete an Equality Impact assessment as part of the business case before approval. Report P33
Legal: No new direct legal implications arising from the report. Report P33
Other: Some planned improvements were not delivered in 2025/26 due to capacity constraints within the PMO; PMO manager capacity has been increased to carry these forward in 2026. Report 3.14
Who and where
The Portfolio Management Office (PMO) Report 3.2, 3.14
Directorates delivering programmes and projects Report 3.7, 3.11
Programme and Project Managers and Sponsors Report 3.20
Timeline
End of February 2026: 76% of corporately monitored projects rated Green or Amber, below 90% target Report 3.9, P15
11 March 2026: Executive approved ending the Transformation Programme in its current form and moving to Continuous Improvement Report 3.10, 3.16
Early 2026: PMO refreshed the Programme and Project Management Policy to reflect the new Continuous Improvement direction Report 3.15
2026/27: Planned refresh of the PPMF, project documentation and categorisation scoring tool, and launch of a Centre of Excellence model Report 3.17, 3.18, 3.19, 3.20
April 2026: Revised performance and financial management policy due to be considered by Executive Report 3.17
Plain English for the jargon
PMO: Portfolio Management Office, the team providing strategic oversight of the Council's programme and project portfolio
PPMF: Programme and Project Management Framework, the Council's standardised approach to governance and management
RAG: Red, Amber, Green indicators used to rate how well a project is delivering against expectations
BAU: Business as usual, the routine running of services outside of formal project management
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item25/7
Resolved
AGREED that: 1. The arrangements in place to manage programmes and projects within the Council be noted. 2. The Committee considered that the information provided offered sufficient assurance that appropriate arrangements are in place in relation to programme and project management.
Word for word from the decision Middlesbrough published for this meeting.Source: moderngov.middlesbrough.gov.uk
• NOTES the arrangements in place to manage programmes and projects within the Council. • CONSIDERS whether the information provided has given the Committee sufficient assurance that the Council has appropriate arrangements in place in relation to programme and project management.
3. Background and relevant information
3.1The purpose of this report is to outline the Council’s Programme and Project Management (PPM) approach, summarise project performance for 2025/26, and set out planned PPM developments for 2026 and beyond, providing assurance that robust PPM arrangements are in place to support delivery of the Council Plan ambitions.
3.2The PMO has responsibility for the strategic oversight of the Council’s portfolio of programmes and projects that follow the corporate Programme and Project Management Framework (PPMF), which ensures a consistent approach to the governance and management of programmes and projects.
3.3The PPMF is supported by a set of standardised project templates and provides clear guidance for managing programmes and projects at every stage of their lifecycle, helping to further embed the framework and methodology across the Council.
3.4Compliance with the PPMF is assured through periodic project health checks, and performance is reported quarterly to the Executive within the performance outturn report.
3.5The Council maintained a portfolio of corporate and transformation programmes and projects in 2025/26 to support of achievement of the Council’s strategic priorities.
3.6During 2025/26 projects within the Transformation Portfolio were reviewed to ensure ongoing alignment with transformation themes. Some were incorporated into the Council’s overarching portfolio of corporate programmes and projects as a result, with progress against performance reported accordingly.
3.7Monthly Directorate and Corporate Performance Boards were in place in 2025/26 and included monitoring the performance of progress against the delivery of all This document was classified as: OFFICIAL
strategic programmes and projects, Executive actions and Council Plan workplan initiatives.
Performance of programmes and projects in 2025/26
3.8During 2025/6 there were 40 projects in the corporate portfolio at the point of reporting. Projects are categorised as either Level 1 (the most complex projects) or Level 2 (lighter-touch projects), and their performance is assessed and reported using Red, Amber, and Green (RAG) indicators that measure how well the project is delivering against expectations.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Outcome of the Review of Internal AuditAGREED that: 1. The findings of the review of the Council’s current internal audit arrangements be noted. 2. The prop...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.