AGREED (unanimously) that additional capital expenditure for £250,000 for the refurbishment of the Sherwood Forest Art & Craft Centre, be approved for inclusion in the Council’s Capital Programme. Reason for Decision The refurbishment allows for the upgrade of the Centre in order to enhance the visitor experience.
Word for word from the decision Newark and Sherwood published for this meeting.Source: democracy.newark-sherwooddc.gov.uk
1.1This paper seeks to provide Members with a proposal, as outlined and discussed in the March 2018 Economic Development Committee meeting relating to the refurbishment of the Sherwood Forest Art and Craft Centre. The total capital expenditure proposed is £250,000.
2.0Background Information
2.1Sherwood Forest Art & Craft Centre was opened in 1998 and is now in need of refurbishment.
2.2The relocation of Sherwood Forest Visitor Centre to a site immediately adjacent to SFACC provides a unique opportunity to undertake this refurbishment. The SFACC is ideally located to benefit in terms of increased footfall opportunities which will result in approximately 455,000 passing the entrance of SFACC every year.
2.3The financial calculations in the following Business Case are based on the latest market rents achieved at SFACC and indicate that the Council would receive an approximate 7% return on its investment. There may also be the opportunity to increase the rents of the existing studios by between 5% and 7% - whilst this is speculative nonetheless given the dramatic increase in footfall it may prove to be a feasible option..
3.0Proposals
3.1Details of the proposal are set out in the report to the Economic Development Committee meeting held on 28 March 2018 which is attached as an appendix to the report.
Equalities implications
4.1There are only positive implications for taking forward the refurbishment of the Sherwood Forest Art and Craft Centre.
5.0Impact on Budget/Policy Framework
5.1A capital budget of £250,000 will need to be included in the Capital Programme for 2018/19 which will be funded from the capital reserve or a revenue contribution to capital from the change management reserve. 6.0 Comments of Director – Resources and S151 Officer
6.1The decision on how to finance this scheme will be taken in conjunction with the rest of the Council’s capital programme. The revenue cost of borrowing is approximately £60,000 per annum per £1million of borrowing based on current PWLB rates. The revenue cost of the capital spend of £200,000 is therefore £15,000 which, if borrowed, will be funded in 2018/19 from general fund balance and included in the base budget for future years.
Recommendation
That additional capital expenditure for £250,000 for the refurbishment of the Sherwood Forest Art & Craft Centre, be approved for inclusion in the Council’s Capital Programme.
Reason for recommendation
The Centre is in need of refurbishment and as the Centre opened in 1998, the refurbishment allows for the upgrade of the Centre in order to enhance the visitor experience.
Background papers
Nil
For further information please contact Julie Reader-Sullivan on Ext 5258
Sanjiv Kohli Deputy Chief Executive Director - Resources and s151 Officer APPENDIX
ECONOMIC DEVELOPMENT COMMITTEE AGENDA ITEM NO. 10 28 MARCH 2018
REFURBISHMENT OF SHERWOOD FOREST ART & CRAFT CENTRE AND ASSOCIATED BUILDING
1.1This report provides an opportunity to invest capital for the refurbishment of the Sherwood Forest Art & Craft Centre (SFACC).
2.0Background Information
2.1Sherwood Forest Art & Craft Centre was opened in 1998 and is now in need of refurbishment.
2.2The relocation of Sherwood Forest Visitor Centre to a site immediately adjacent to SFACC provides a unique opportunity to undertake this refurbishment. The SFACC is ideally located to benefit in terms of increased footfall opportunities which will result in approximately 455,000 passing the entrance of SFACC every year.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Programme 2022/23 to 2025/26AGREED (unanimously) that the General Fund schemes set out at Appendix A to the report, and the Housing Services sche...
Newark Castle - Condition SurveyAGREED (unanimously) that: (a) the inclusion of this work in the 2022/23 Capital Programme for £570,000 be approved, ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.