Resolved
AGREED (unanimously) that the report be noted with a further update report being presented to Committee in January 2019.
Economic Development Committee agreed this item on Wednesday 21 November 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
AGREED (unanimously) that the report be noted with a further update report being presented to Committee in January 2019.
1.1This report is to update Members on the current Capital Scheme approved by Policy & Finance on 5 April 2018. The total capital expenditure proposed is £250k.
2.0Background Information
2.1The report to Policy & Finance Committee advised Members that Sherwood Forest Art & Craft Centre was opened in 1998 and was in need of significant updating.
2.2This had become a priority following the decision to relocate the new Visitor Centre to a site immediately adjacent to the Art & Craft Centre which would bring an anticipated increase in footfall of visitors directly passing the entrance to SFACC of 455,000. This was on top of the existing 60,000 visitors (approx.) to the Centre
2.2The new Sherwood Forest Visitor Centre has now been completed and is open to the public and there has been a substantial increase in customers to Sherwood Forest Art & Craft Centre.
3.0Proposals
3.1The capital scheme was envisaged to cover three main aspects as set out below:
3.1.1 Conversion of a former storage building at Forest Corner to provide a “gateway” building for the forest. Planning consent had already been granted but a number of minor amendments have been proposed which will allow the property to be used as either one large unit or two smaller ones. The necessary Environmental Surveys have been carried out and a European Protected Species Licence approved. Minor preparation works started in October with substantive work starting in November 2018.
3.1.2 New public toilets and provision of additional storage for the tenants - design drawings are at an advanced stage and a planning application is expected to be submitted by the end of November.
3.1.3 Realignment of rear entrance and creation of additional studio space - provisional design drawings have been completed and a number of amendments have been proposed. It is hoped that these will also be ready to submit for Planning Consent alongside those for the new toilets/storage.
4.1There are only positive implications for taking forward the refurbishment of the Sherwood Forest Art and Craft Centre. The building is DDA compliant and provides opportunities for local businesses to showcase crafts and skills. 5.0 Financial Implications (18-19/9187)
5.1A capital budget of £250,000 for the scheme was included in the Capital Programme for 2018/19 and is due be financed by existing Capital Receipts.
6.0Comments of Director(s)
6.1Policy & Finance Committee, at the meeting on 5 April 2018 approved a budget of £250.000 to carry out the improvements and refurbishment of the Sherwood Forest Art and Craft Centre. The financial calculations included in the Business Case considered by that Committee, based on the latest market rents achieved indicated that the Council would receive an approximate 7% return on its investment. This position has not changed and the work, as stated in this report, is now under way.
That the report be noted and a further report be provided in January 2019
In order to keep Members appraised of the progress of the scheme
Nil
For further information please contact Julie Reader-Sullivan on Ext 5258
Sanjiv Kohli Deputy Chief Executive/Director - Resources
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Progress Update on Edwinstowe Craft CentreReport | 250 KB | DownloadRead as text |
Follow Economic Development Committee at Newark and Sherwood and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Nov 2021 | Minutes of Meeting Held on 8 September 2021AGREED that the Minutes of the meeting held on 8 September 2021 be agreed as a correct record and signed by the Chair... | Agreed | Open |
| 17 Nov 2021 | Forward Plan (December 2021 to November 2022)AGREED that the following items be added to the Economic Development Committee Forward Plan. · EV Charging Points Upd... | Agreed | Open |
| 17 Nov 2021 | Amended Structure for Planning DevelopmentAGREED (unanimously) that: (a) support be given for the amended structure and associated budget virements (increased ... | Agreed | Open |
| 17 Nov 2021 | Highways UpdateAGREED (unanimously) that: (a) the contents of the report be noted; (b) the Policy & Finance Committee be recommended... | Agreed | Open |
| 17 Nov 2021 | Funding Opportunities UpdateAGREED (unanimously) that: (a) the contents of the report be noted; and (b) Policy & Finance Committee be recommended... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.