AGREED (unanimously) that: (a) the General Fund projected favourable outturn variance of £0.123m be noted; (b) the variations to the Capital Programme at Appendix B, totalling £0.073m, be approved; and (c) the Capital Programme projected outturn and financing of £32.482m be noted. Reason for Decision To advise Members of the projected outturn monitored against service budgets for the period ending 31 March 2019, as at 30 September 2018.
Word for word from the decision Newark and Sherwood published for this meeting.Source: democracy.newark-sherwooddc.gov.uk
1.1This report compares the Revised Budgets for the period ending 31 March 2019 with the Projected Outturn forecast for the period, based on meetings with Financial Services staff and the appropriate Business Manager. These are based on four months’ performance information on the Council’s revenue and capital budgets, including:-
General Fund Revenue Capital Programme
1.2To inform Committee of the individual contributions to, and withdrawals from, Usable Reserves.
2.0Background Information
2.1The Council’s Constitution states that the Section 151 Officer shall present to the Policy & Finance Committee, at least twice in each financial year, budgetary control statements showing performance against the approved estimates of revenue expenditure and income. The appropriate Chief Officer will report on any major variances from planned budget performance.
2.2Where it appears that the amount included under any head of the approved budget is likely to be exceeded or the budgeted amount of income under any head is unlikely to be reached then Business Managers are required to find savings elsewhere in their budget. In circumstances where savings cannot be identified it will be necessary to consult with the Section 151 Officer and ultimately take a report to the Policy & Finance Committee.
3.0Proposals
Overview of General Fund Revenue Projected Outturn for 2018/19
3.1The accounts show a projected favourable variance against the revised budget of £0.168m on Service budgets, with an overall favourable variance of £0.123m as shown in the table below:
Original Revised Projected Variance Budget Budget Outturn £'m £’m £'m £'m Economic Development 1.412 1.914 1.665 -0.249 Homes & Communities 2.903 3.257 3.235 -0.022 Leisure & Environment 4.331 4.567 4.440 -0.127 Policy & Finance 4.044 4.145 4.375 0.230 Net Cost of Services 12.690 13.883 13.715 -0.168 Other Operating Expenditure 0.000 1.752 1.836 0.084 Finance & Investment Inc & Exp 0.000 -0.369 -0.369 0.000 Taxation & Non Specific Grant Inc -12.370 -14.645 -14.684 -0.039 Net Cost of Council Expenditure 0.320 0.621 0.498 -0.123 Transfer to/-from Usable Reserves 1.925 0.996 0.996 0.000 Transfer to/-from Unusable Reserves -2.245 -1.617 -1.617 0.000 Transfer to/-from General Reserves 0.000 0.000 -0.123 -0.123
3.2As can be seen from the table above there are variances projected in service areas and other budgets. Looking at the underlying trends, the detailed variances by Committee can be further summarised and these are shown at Appendix A.
3.3The level of underspending on Service Budgets managed by the Business Managers is £0.168m and represents 1.21% of the total service budgets. The breakdown below of variances by type of income/expenditure (CIPFA classification), shows where outturn is projecting to be favourable or unfavourable, when compared to the revised budget figure.
Employees £0.044m Premises £0.056m Transport (£0.166m) Supplies (£0.214m) Income £0.266m Rent Allowances/HB (£0.154m)
Total (£0.168m)
3.4Non-Service expenditure is expected to be overspent against the revised budget by £0.045m. This is due to the corporate savings target of £0.084m, which the Council’s Commercial Project Team are looking to achieve. Any savings made are highlighted within the appropriate Committee area. The other £0.038m is additional grant income from Rural Services Delivery Grant which was not budgeted for.
3.5There has been a positive variation of £0.216m from the outturn projected at 31 July 2018 for Service budgets. At that time, the outturn was an adverse projection to budget of £0.048m. As discussed above, this is now a favourable variance to budget of £0.168m. The primary reasons for this are:-
Savings identified in the timing of payments to the Development Company: £0.093m Garden waste income and waste collection payments to NCC: £0.088m Cashless income from Newark car parks increase: £0.037m
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Programme 2022/23 to 2025/26AGREED (unanimously) that the General Fund schemes set out at Appendix A to the report, and the Housing Services sche...
Newark Castle - Condition SurveyAGREED (unanimously) that: (a) the inclusion of this work in the 2022/23 Capital Programme for £570,000 be approved, ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.