PLANNING COMMITTEE – 26 MARCH 2019
Application No: 18/01477/FULM (MAJOR)
Proposal Erection of a Hydropower Electricity Generating Station, supported by energy storage and fish passage in the area of land adjacent to Cromwell Weir on the right bank of the River Trent near Collingham. The purpose of this development is to generate and store renewable electricity and provide improvement to upstream fish and eel passage and biodiversity on the River Trent.
Location: Land On The South Side Westfield Lane, Collingham, Nottinghamshire
Applicant: Barn Energy - [name removed]: 24th August 2018 Target Date: 23rd November 2018
Extension of time agreed in principle
This application is being presented to the Planning Committee as the adjoining ward member Cllr M Dobson has referred the application for consideration by Members. This request was made after the main agenda was published. However this application has been published as an additional item on the same day as the main agenda to ensure that a decision can be made before 31st March 2019. This will ensure that the applicant is able to take advantage of incentives currently being offered by OFGEM tariffs which expire on 31st March 2019 should Members be minded to approve the scheme.
The Site
The site is located on the eastern bank of the River Trent to the east of Cromwell and to the west of Collingham on an area of land between the river and the flood plain. The site is known as Cromwell Weir.
A dwelling associated with the lock alongside the weir is situated on the western river bank. A quarry owned and operated by Tarmac lies to the east of the site and there is a restored area of land which forms a RSPB wetland to the north of the site. The proposed site would cover approximately 0.6ha of land which predominantly includes a section of modified river bank on the eastern side of the weir. The site would be accessed from an existing access point serving the neighbouring Tarmac Quarry. The eastern bank of the river downstream of the weir is used by fishermen from local angling clubs.
Access is via the Tarmac Quarry entrance at the A1133 and two other vehicular access routes which are used by the two local angling clubs.
Given the proximity of the site to the River Trent the development land is designated as being within Flood Zones 2 & 3 in accordance with Environment Agency mapping. Public rights of way are situated on both eastern and western banks of the river; the western side terminates at the weir and the eastern side runs to the rear of the site along the boundary of the nature reserve to the north.
The site sits within the Langford and North Muskham parish wards with the boundary for the Collingham ward being approximately 0.5km further to the east. Relevant Planning History
17/01447/FUL – Full planning permission was granted in May 2018 for the erection of a Hydropower Electricity Generating Station, supported by energy storage and fish passage in the area of land adjacent to Cromwell Weir on the right bank of the River Trent near Collingham. The purpose of this development was to generate and store renewable electricity and provide improvement to upstream fish and eel passage and biodiversity on the River Trent.
This permission was challenged on that basis that no screening opinion had been undertaken under the EIA Regulations, no Habitat Regulation Assessment was undertaken under the relevant legislation and that the application had been wrongly determined under delegated powers. The Council submitted to judgment and the decision was quashed .
The Proposal
The development site would involve the removal of an existing engineered section of riverbank and installation of the turbines and associated infrastructure.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
EIA Screening Report: Collingham WeirAppendix 1 | 360 KB | Download |
PDF |
Collingham Weir Lepus HRA Appropriate AssesmentAppendix 2 | 1.1 MB | Download |
PDF |
Land on the South Side Westfield Lane, Collingham 18/01477/FULM (MAJOR)Report | 1.5 MB | DownloadRead as text |
Follow Planning Committee at Newark and Sherwood and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 May 2026 | Minutes of the meeting held on 9 April 2026AGREED that the minutes from the meeting held on 9 April 2026 were agreed as a correct record and signed by the Chair. | Agreed | Open |
| 7 May 2026 | Review of the Protocol for Planning Committee and the Planning Committee Scheme of Delegation to OfficersAGREED that: (a) no changes are currently required to the Protocol for Planning Committee or the Planning Scheme of D... | Agreed | Open |
| 7 May 2026 | Land to Rear of Mill Lane, Caunton (25/01952/FUL)AGREED Moved Councillor M Spoors and Seconded Councillor S Saddington (with 11 votes For and 2 votes Against) that co... | Agreed | Open |
| 7 May 2026 | Land to the East of Hockerton Road, Upton (26/00382/PIP)AGREED Moved Councillor K Melton and Seconded Councillor P Harris (with 7 votes For and 6 vote Against) that contrary... | Agreed | Open |
| 7 May 2026 | Land Adjacent Apple Cottage, Bilsthorpe Road, Eakring (26/00377/PIP)AGREED (with 10 votes For and 2 votes Against) that Permission in Principle be approved. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.