AGREED (with 5 votes for and 2 against) that: (a) the Articles of Association (Appendix A) be noted; (b) the Shareholders Agreement (Exempt Appendix C) be noted; and (c) the inclusion of £3.3m to the Council’s Capital Programme, profiled over 2019/20 and 2020/21 be approved. Reason for Decision To keep Members informed of the progress of the redevelopment of the former Robin Hood Hotel and to establish the budget of £3.3m in the Council’s Capital Programme.
Word for word from the decision Newark and Sherwood published for this meeting.Source: democracy.newark-sherwooddc.gov.uk
1.1To inform Members of the joint venture agreement with MF Strawson Ltd for the redevelopment of the former Robin Hood Hotel.
1.2To include £3.3m in the Council’s capital programme, being one-half of the estimated development cost as agreed by Policy & Finance Committee at their meeting held on 29 November 2018.
2.0Background Information
2.1Members will recall that at the Policy & Finance Committee meeting on 20 September 2018 it was agreed in principle that the Council enter into a joint venture arrangement with MF Strawson Ltd. through the establishment of a special purpose vehicle for the redevelopment of the former Robin Hood Hotel.
2.2At the Policy & Finance Committee meeting held on 29 November 2018, Members considered further detailed information on the proposed joint venture agreement with MF Strawson Limited, and resolved that:
(a) the Deputy Chief Executive & Director – Resources, in consultation with the Chief Executive and Leader of the Council, be given delegated authority on behalf of the Council to negotiate detailed terms and to enter into joint venture arrangements with MF Strawson Ltd for the re-development of the former Robin Hood Hotel subject to planning permission having been issued and subject to the conditionality elements in the Agreement for Lease with Travelodge Hotels Ltd. first being satisfied or, if the joint venture company is set up in advance of this, that it will not be allowed to be active until these conditions are met ,and with the building costs in respect of the project being clarified as far as possible before a building contract is let by the joint venture company;
(b) the overall capital contribution by the Council towards the project be capped at £3.3million;
(c) the Deputy Chief Executive & Director - Resources be appointed as Director of the joint venture company; and
(d) the Deputy Chief Executive & Director – Resources, in consultation with the Chief Executive and Leader of the Council, be given delegated authority to deal with all ancillary and associated matters relating to the joint venture arrangements including the naming of the joint venture company.
2.3In accordance with the delegation, the Deputy Chief Executive & Director - Resources, after seeking legal advice from the Council’s Monitoring Officer and external firm of solicitors, and after consulting with the Chief Executive and Leader of the Council has: a) Formed the joint venture company, RHH Newark Limited, with Newark & Sherwood District Council and MF Strawson Limited being equal shareholders, with each holding 500 Ordinary Shares of £1 each.
b) Agreed the Articles of Association (Appendix A).
c) Received the Letter of Commitment from MF Strawson (Appendix B).
d) Agreed the Shareholders Agreement (Appendix C which is an exempt document at Item 16 on the agenda).
2.4The terms agreed are in accordance with those agreed by Members of the Policy & Finance Committee at the meeting of 29 November 2018. These terms, in summary, being:
1. Maximum Capital Contribution The Council and MF Strawson Ltd will enter into the redevelopment project with the capital commitment and risk being shared on an equal basis. The Council’s contribution will, however, be fixed at 50% of the total development cost which is, as stated above, estimated at £6.6m. The Council’s maximum capital commitment to the development costs will therefore be capped at £3.3m. The parties will need to consider whether the 50:50 arrangements will be changed in the event that costs exceed £6.6m and the Council is not willing to increase its overall contribution to the project.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Programme 2022/23 to 2025/26AGREED (unanimously) that the General Fund schemes set out at Appendix A to the report, and the Housing Services sche...
Newark Castle - Condition SurveyAGREED (unanimously) that: (a) the inclusion of this work in the 2022/23 Capital Programme for £570,000 be approved, ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.