CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Newark and Sherwood District Council
Cabinet, Tuesday 12 July 2022 at 6.00pm

Development of the former Robin Hood Hotel, Newark

Agreed Executive 1 paper

Cabinet agreed this item on Tuesday 12 July 2022. Below is the council's own wording, with the papers it was decided on.

Item16

Resolved

AGREED 1. To establish a reduced, revised capital budget for landlord incentives of £167,000 (from £275,000); 2. To note the successful delivery of the 66 room Travelodge Hotel and reputable tenants for the 3 commercial units; 3. To note that the Council’s actual loan value required for the development of the whole demise was £3.146m, against the capital loan budget of £3.300m, therefore a capital borrowing requirement reduction of £0.154m; 4. To note the final financial position of the development of the former Robin Hood Hotel and the positive contribution from the development, to the Council’s general fund of £163,930; 5. To note the ongoing positive estimated revenue return per year to the Council that the letting of the 3 commercial units will generate; and 6. To approve the revision of the current capital budget by a reduction of £108,000 from £275,000 to £167,000 for landlord incentives, in respect of the 3 commercial units.
Word for word from the decision Newark and Sherwood published for this meeting. Source: democracy.newark-sherwooddc.gov.uk

Follow this further

Built from Newark and Sherwood's papers

What the report saysPro

Report to Cabinet

Report to: Cabinet Meeting - 12 July 2022

Portfolio Holders: Councillor David Lloyd, Strategy, Performance & Finance and Councillor Rhona Holloway, Economic Development & Visitors

Director Lead: Sanjiv Kohli, Deputy Chief Executive and Director - Resources

Lead Officer: Nick Wilson, Business Manager, Financial Services, Ext. 5317

Report Summary Open Report Type of Report Non-Key decision

Report Title Development of the Former Robin Hood Hotel, Newark

To update Cabinet on the final development and lease(s) position of the Purpose of Report Joint Venture, for the development of the former Robin Hood Hotel on Beaumond Cross, with final completion dates and financial performance.

To establish a reduced, revised capital budget for landlord incentives of £167,000 (from £275,000).

To note the successful delivery of the 66 room Travelodge Hotel and reputable tenants for the 3 commercial units.

To note that the Council’s actual loan value required for the development of the whole demise was £3.146m, against the capital loan budget of £3.300m, therefore a capital borrowing requirement reduction of £0.154m. Recommendations To note the final financial position of the development of the former Robin Hood Hotel and the positive contribution from the development, to the Council’s general fund of £163,930.

To note the ongoing positive estimated revenue return per year to the Council that the letting of the 3 commercial units will generate.

To approve the revision of the current capital budget by a reduction of £108,000 from £275,000 to £167,000 for landlord incentives, in respect of the 3 commercial units. 1.0 Background

At the meeting of the Policy & Finance Committee on 21 January 2021, a financial update report was considered by Members where it was agreed that a further report would be brought to Members setting out the final financial position once the various legal arrangements – Sale to Knights Frank Investment Llp (KFIM), Head Lease with KFIM and Sub Leases for Travelodge and the 3 commercial units - had been completed

2.0Proposal/Options Considered and Reasons for Recommendation

Final Position

2.1Construction and Practical Completion

It was reported at the January 2021 meeting that the anticipated practical completion date of the building would be 8 March 2021. The final completion date was slightly delayed due to COVID and legal completion took place on 18 March 2021. The sale of the whole demise to Knights Frank Investment Management Llp (KFIM) was completed on 13 April 2021.

2.2Financial Performance Summary

The financial performance of RHH Ltd’s delivery of the development project and the Council’s 50% share is summarised in the tables below:

Table 1 –Development Receipt RHH Ltd NSDC Joint 50% Sales Value Venture 7,000,000 Share 3,500,000 Less: Rent free – 6m to Travel Lodge(TL) (152,625) (76,313) Less Sales/Lease legal costs (110,851) (55,425) Net Sale Proceeds 6,736,524 3,368,262 Table 2 – Development Costs RHH Ltd Joint NSDC Venture 50% Total development costs 6,667,990 Share 3,333,995 Less: Reduction in land value (equal to 6m rent free to (152,625) (76,313) TL) development costs Net 6,515,365 3,257,683 Table 3 – Development Profit RHH Ltd Joint NSDC 50% Venture Share Net Development Profit 221,159 110,580 Corporation Tax (42,020) (21,010) Net Profit after Tax 179,139 89,570

The Council’s s151 Officer was the Council’s representative on the Board of RHH Ltd. By the close management of the delivery of the development of the former Robin Hood site, RHH Ltd have returned additional monies of £89,570 over and above the funding requirement of £3.146million, against the original capital loan budget of £3.3million, that the Council had loaned to the joint venture. In addition, the total interest earned by the Council on the amount loaned to RHH Ltd for the development costs through to completion of the development is £74,360.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Development of the former Robin Hood Hotel, NewarkReport 366 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 19 attended
DL
Councillor David LloydChairman, present
KG
Councillor Keith GirlingCommittee Member, apologies
MR
Councillor Mrs Rhona HollowayCommittee Member, present
RJ
Councillor Roger JacksonCommittee Member, present
PP
Councillor Paul PeacockCommittee Member, present
TW
Councillor Timothy WendelsCommittee Member, present
HB
Helen BayneSecretary, expected
HB
Helen BrandhamSecretary, expected
NH
Nigel HillSecretary, expected
SB
Sue BearmanOfficer, expected
MF
Matt FinchOfficer, expected
DK
Deborah K JohnsonOfficer, expected

All 19 on the meeting page

On this subject at Newark and Sherwood

Search all
  1. Development of the former Robin Hood Hotel, NewarkThis decision
  2. Phase 6a/7 Thoresby Vale, Development, Former Thoresby Colliery, Ollerton Road, Edwinstowe, NG21 9PS - 24/00289/OUTM (MAJOR AND EIA DEVELOPMENT)Agreed

More from Newark and Sherwood Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 Budget Performance Report Quarter 1That Cabinet: (a) note the General Fund projected unfavourable outturn variance of £0.665m; (b) note the Housing Reve... Noted Open
15 Sep 2026 Community Plan Performance Report Quarter 1That Cabinet: a) review the Community Plan Performance Report attached as Appendix 1; b) review the compliance report... Decided Open
15 Sep 2026 Housing Compliance Assurance Report Quarter 1That Cabinet note: a) the exceptions to performance of the housing service compliance functions; b) interim arrangeme... Decided Open
15 Sep 2026 Annual Review of Exempt ItemsThat Cabinet note the report, with any items being released into the public domain if considered no longer being exempt. Noted Open
15 Sep 2026 Progress Towards Net ZeroThat Cabinet: a) notes the Council's 2025/26 corporate emissions position and progress towards the Net Zero 2035 targ... Decided Open