AGREED (unanimously) that contrary to Officer recommendation planning permission be refused on the grounds of access, traffic and safety. In accordance with paragraph 12.5 of the Planning Protocol, as the motion was against officer recommendation, a recorded vote was taken. Councillor Vote R. Blaney For L. Brazier Absent M. Brock For M. Brown Absent L. Dales For M. Dobson For L. Goff For R. Holloway For J. Lee For P. Rainbow For M. Skinner For T. Smith For I. Walker For K. Walker For Y. Woodhead For
Word for word from the decision Newark and Sherwood published for this meeting.Source: democracy.newark-sherwooddc.gov.uk
Proposal: Application for variation of conditions 02, 03, 04 and 05 of planning permission 16/01369/FUL to allow the new access junction to be constructed wholly within highway land or that owned by the applicant (Retrospective)
Location: Springfield Bungalow Nottingham Road Southwell NG25 0QW
Applicant: 23.04.2019
Registered: 9th April 2019 Target Date: 4th June 2019
Extension of time agreed in principle
UPDATE REPORT
This application was deferred by Members at June 4th Planning Committee in order to seek clarification of the specific issues of the acceptability of the kerb radii to the site, the gradient of the footpath (achieving 1:12), the cross fall of the footpath (achieving 1:40), and confirmation that the visibility splay measured on site by NCC highways was appropriate.
The Proposal
As Members will recall that this application seeks solely to revise conditions 2 (relating to approved plans) and 3 (drainage and surface water relating to the access into the site [nb. This is where the new access crosses the threshold into the site from the public highway not the internal access road, which remains in the location originally approved and is covered by planning permission 15/01295/FULM]), 4 (longitudinal and cross sectional gradients, street lighting, drainage and outfall proposals, construction specification, provision of utilities services, and any proposed structural works) and 5 (visibility splays) attached to the planning permission ref. 16/01369/FUL for the creation of an access at Hallougton Road.
The access has implemented but has been redesigned and constructed (by the applicant using Via as contractors) to ensure that that works have wholly taken place within the undisputed boundary of the public highway. As such the development is not in accordance with the access plans approved under this permission.
Thus the current application seeks retrospective planning permission to change the conditions in order to regularise the situation.
It is proposed to amend the conditions as follows:-
Original conditions
Condition 2 relates to the approved plan ‘The development hereby permitted shall be carried out in accordance with the following approved plan:-
12/1889/750
unless otherwise agreed in writing by the local planning authority through the approval of a non-material amendment to the permission.’
Condition 3
‘No development shall be commenced until details of drainage and surface water disposal have been submitted to and approved in writing by the local planning authority. The development shall be carried out thereafter in accordance with the approved details unless otherwise agreed in writing by the local planning authority.
Condition 4
‘No part of the development hereby permitted shall take place until details of the new access road have been submitted to and approved in writing by the Local Planning Authority including longitudinal and cross sectional gradients, street lighting, drainage and outfall proposals, construction specification, provision of utilities services, and any proposed structural works. The development shall be implemented in accordance with these details to the satisfaction of the Local Planning Authority.’
Condition 5
‘No part of the development hereby permitted shall be brought into use until the visibility splays of 2.4m x 43m shown on drawing no. 12/1889/750 are provided. The area within the visibility splays referred to in this condition shall thereafter be kept free of all obstructions, structures or erections exceeding 0.25 metres in height unless otherwise agreed with the Highway Authority.’
Proposed Amendments
Condition 02 01
The development hereby permitted shall be retained in accordance with the following approved plan:-
• HALL-BSP-ZZ-XX-DR-C-100 Rev P6 deposited 7th April 2019 (Notwithstanding gradients) and (ref. 37049-BSP-ZZ-XX-DR-C-101 Rev P3)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.