Resolved
AGREED (unanimously) that: (a) the report and achievements made to date be noted; and (b) a further progress report be presented to the Committee in June 2020.
Economic Development Committee agreed this item on Wednesday 20 November 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
AGREED (unanimously) that: (a) the report and achievements made to date be noted; and (b) a further progress report be presented to the Committee in June 2020.
1.1The purpose of this report is to update Members on the progress made at the Newark Beacon.
2.0Background Information
2.1On 1 October 2018, the management of Newark Beacon was brought in-house and a five year Business Plan (2018 – 2023) was subsequently approved by the Economic Development Committee (21 November 2018)
3.0Update
Business Plan 3.1 The Business Plan set out a number of proposals and objectives over a five year timeline. There have been some delays within this 5 year programme, primarily due to the need to undertake essential works and staffing changes. However, the overall budgetary position remains positive compared to forecast.
Staffing Changes 3.2 As reported to Committee on 19 June 2019, currently both the Centre Manager and the Assistant Centre Manager are on 12 months maternity leave which commenced on March/April 2019. As a consequence, both a temporary Centre Manager and Assistant Centre Manager has been employed. A further member of staff is on a phased return to work following long term sick leave. Two new zero hours contract staff have been employed and have been trained to cover reception.
The forgoing has resulted in a considerable reduction in the use of agency staff to cover the management and operation of Newark Beacon and costs have reduced considerably.
Essential Works 3.3 Managing the Beacon over the last 12 months has enabled us to identify a range of essential works required to update and maintain the facility to the high standard of service offering we are striving for. We recognise the importance of providing this level of service in an attractive environment to retain existing businesses. Equally we are focussing on providing facilities that appeal to new organisations which may be attracted by new and innovative facilities. The following progress in respect of improvements to the Centre have been made: Scheme Status Cost (approx.)
New website completed & operational Complete Nil Fire Risk Assessment compliance Complete £2,000 Fire Alarm upgrade Complete £4,000 Telephone system upgrade Complete £4,000 Door Access System replacement Complete £4,000 Kitchen Equipment (Café) Complete £2,000 Kitchen Reorganisation/redecoration (improved Complete £4,000 storage) Redecoration (reception) Complete £1,200 Centre Signage replacement Complete £4,000 Shared Office/New Meeting Room (inc new Complete £20,000 Furniture & AV equipment) Conference facility upgrade inc. new AV Complete £4,000 equipment (NB this has replaced the option of the sliding wall and new AV previously reported at circa £20,000 Reception Upgrade Complete £2,000 Car Park Remarking Complete £1,000 Intruder Alarm upgrade Complete £1000 Communications Room upgrade Complete £2,000 Principal Toilet upgrade including Legionella In progress £20,000 compliance Carpet Replacement Awaiting quotation TBA Kitchenette refurbishment (2 ) To programme Approx. £2,000 Telephone switches To inspect and update TBA
4.0Performance to Date
4.1Rental Surplus The 2018/19 Outturn shows the following: Rental Income which includes rent, virtual and services charges was budgeted as £365,530. Actual achieved was £364,365 an unfavourable variance of £1,165.
4.2Auxiliary Surplus Auxiliary Income which includes catering, hot desking and hire charges was budgeted as £51,600. Actual achieved was £70,931 a favourable variance £19,331.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Newark Beacon UpdateReport | 273 KB | DownloadRead as text |
Follow Economic Development Committee at Newark and Sherwood and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Nov 2021 | Minutes of Meeting Held on 8 September 2021AGREED that the Minutes of the meeting held on 8 September 2021 be agreed as a correct record and signed by the Chair... | Agreed | Open |
| 17 Nov 2021 | Forward Plan (December 2021 to November 2022)AGREED that the following items be added to the Economic Development Committee Forward Plan. · EV Charging Points Upd... | Agreed | Open |
| 17 Nov 2021 | Amended Structure for Planning DevelopmentAGREED (unanimously) that: (a) support be given for the amended structure and associated budget virements (increased ... | Agreed | Open |
| 17 Nov 2021 | Highways UpdateAGREED (unanimously) that: (a) the contents of the report be noted; (b) the Policy & Finance Committee be recommended... | Agreed | Open |
| 17 Nov 2021 | Funding Opportunities UpdateAGREED (unanimously) that: (a) the contents of the report be noted; and (b) Policy & Finance Committee be recommended... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.