Resolved
AGREED that the progress being made with both the 5 year Housing Revenue Account Development Programme and Extra Care Scheme in Boughton be noted.
Homes & Communities Committee agreed this item on Monday 20 January 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
AGREED that the progress being made with both the 5 year Housing Revenue Account Development Programme and Extra Care Scheme in Boughton be noted.
1.1This report provides the Committee with an update on the progress being made with the 5 year Housing Revenue Account (HRA) Development Programme and the Extra Care Scheme in Boughton.
2.0Background Information
2.1The delivery of additional affordable homes across the district continues to be a strategic priority for the Council with an objective of the Community Plan being to; ‘Accelerate the supply of new homes including associated facilities.’
2.2There is an ongoing requirement to develop a mixed provision of affordable homes to meet the requirements of younger people, families with young children and older people across the district’s urban and rural communities.
2.3Set against this the Policy & Finance Committee, at its meeting on 30 June 2016, approved that the Council and Newark & Sherwood Homes (NSH) work in partnership to deliver a 5 year (HRA) development programme to provide an indicative 335 new affordable units across the district, with the Homes & Communities Committee charged with monitoring the delivery of the programme.
2.4To date, in addition to the 60 units delivered at Gladstone House, Newark (an extra care scheme), the first two phases of the development programme have delivered 120 new council homes.
2.5To inform the development programme the council has a robust evidence base of housing need, with the last ‘Newark and Sherwood Housing Market and Needs Assessment’ published in 2014. A new Assessment has now been commissioned, in accordance with the Committee’s decision at its meeting on 10th June 2019, and is due to be completed by June.
2.6The 2014 assessment indicated a total net affordable housing need of 677 units per annum and after deducting the annual supply of housing, the shortfall for the following 5 years was 221 homes per annum.
2.7The Council owns 5,460 units (31 March 2019), with 35 homes being sold through the Right to Buy in 2018/19.
2.8There are currently 3825 applicants on the Council’s housing register, which includes transfer applicants. 3.0 Progress – Housing Revenue Account (HRA) Development Programme
3.1Robert Woodhead Ltd are the construction delivery partner for the 5 year HRA development programme following a detailed and successful procurement exercise based upon both price and quality.
3.2NSH are project managing the programme on behalf of the Council and review meetings are held between officers of the Council and Company to monitor delivery of the programme.
3.3The Company adhere to a service specification covering the project management roles and responsibilities set by the Council. The fee charged by the Company is based on per unit delivery, rather than a percentage of the overall programme and reflective of a competitive market rate. The Committee will acknowledge that this relationship will cease once the housing management function comes back to the Council.
Phase One: Completed 3.4 Phase one of the development programme delivered 70 units across 26 sites, all of which reached completion by the end of March 2019 and let to applicants on the Housing Register. The 12-month defect period inspections are currently in progress (50% completed) and minimal remedial works have been required.
Phase Two: Site Progression 3.5 Construction activity continues with phase two that will provide 50 units over 12 sites and current delivery is within the scheduled programme and to budget. The first 7 sites have been handed over and now going through the allocation process. The table below provides the Committee with the key details of phase two delivery:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Housing Revenue Account: Development Programme UpdateReport | 561 KB | DownloadRead as text |
Follow Homes & Communities Committee at Newark and Sherwood and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Jan 2022 | Minutes of meeting held on 22 November 2021AGREED (unanimously) that the Minutes of the meeting held on 22 November 2021 be approved as a correct record and sig... | Agreed | Open |
| 24 Jan 2022 | Update on Antisocial Behaviour and Interventions and EnforcementAGREED (unanimously) that the Committee noted the data relating to Anti-Social Behaviour and the range of activities,... | Agreed | Open |
| 24 Jan 2022 | Housing Ombudsman Complaint Handling - Self AssessmentAGREED (unanimously) that: a) Members noted the progress and continued compliance against the self-assessment. b) Mem... | Agreed | Open |
| 24 Jan 2022 | Reasonable Adjustment Policy for Customers ReportAGREED (unanimously) that Members of the Committee supported the Reasonable Adjustment for Customers Policy and recom... | Agreed | Open |
| 24 Jan 2022 | Dealing with Unreasonable Behaviour and Vexatious Complaints PolicyAGREED (unanimously) that Members of the Committee supported the revised Dealing with Unreasonable Behaviour and Vexa... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.