Resolved
AGREED (unanimously) that outline planning approval be granted subject to the conditions appended at Appendix 3 to the report and the signing of a S106 agreement to secure the contributions in Appendix 4 to the report.
Planning Committee agreed this item on Tuesday 6 October 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
AGREED (unanimously) that outline planning approval be granted subject to the conditions appended at Appendix 3 to the report and the signing of a S106 agreement to secure the contributions in Appendix 4 to the report.
Members will recall that this application has been presented on three occasions in the past as detailed below. At the outset it should be stated that on all occasions Members have resolved to approve the application subject to conditions and the sealing of the Section 106 agreement. The decision is yet to be issued due to discussions in relation to the S106 and the purpose of the current report is to present to Members the latest position offered by the applicant.
This report now forms the fourth report which has been presented to Members for this application. The first was on 13th September 2016 with an Officer recommendation of approval. The second, was on 24th July 2018 where Officers outlined the original viability case presented by the applicant as well as outlining the changes which had occurred between 13 September 2016 and 24 July 2018 in respect of Section 106 negotiations and other changes in material planning considerations. The third and most recent occasion was on 5 th February 2019 where Officers presented a ‘sense check’ of their recommendation in the context of the revised NPPF.
The latest position, and the reason for this report, is that the applicant has provided (by email dated 8th July 2020) updated financial appraisals as discussed in further detail below. The focus of the current report will be on the updated viability position and any other material changes since the application was last presented on 5th February 2019. The intention is for this report to be read as an ‘update report’ in combination with the full assessment presented in February 2019. For ease of reference, the previous committee report has been included as Appendix 1. Viability Case
The previous negotiated position which Members resolved to support in February 2019 was that the proposal will deliver 13% affordable housing (234 units) broken down as follows:
Rent Intermediate Total 1 bed 24 - 24 2 bed 80 72 152 3 bed 14 40 54 4 bed 4 - 4 Total 122 112 234
Delivery was agreed on the basis of the following trigger points:
Affordable Housing Scheme to be submitted prior to the commencement of development of each phase Construct Affordable Housing in compliance with the approved scheme (each phase will include Affordable units) No occupation of more than 60% of the individual completed properties constructed on the site within any phase until at least 45% of the Intermediate Housing within any phase has been completed and transferred to an Affordable Housing Provider No occupation of more than 90% of the individual completed properties within any phase until the remaining 55% of the Intermediate Housing within any phase has been completed and transferred to an Affordable Housing Provider
Furthermore, the drafting of the Section 106 includes a requirement for the applicant to provide an appraisal review after 33% occupation (594 dwellings) and 66% occupation (1,188 dwellings).
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
10a Appendix 1: 16-00506-OUTM: Committee Report presented on February 5th 2019Appendix | 2.3 MB | Download |
PDF |
10b Appendix 2: 16-00506-OUTM: Independent Viability Consultant ResponseAppendix | 346 KB | Download |
PDF |
10c Appendix 3: 16-00506-OUTM: Conditions and InformativesAppendix | 486 KB | Download |
PDF |
10d Appendix 4: 16-00506-OUTM: Developer ContributionsAppendix | 309 KB | Download |
PDF |
Land at Fernwood South, Nottinghamshire (16/00506/OUTM)Report | 786 KB | DownloadRead as text |
Follow Planning Committee at Newark and Sherwood and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 May 2026 | Minutes of the meeting held on 9 April 2026AGREED that the minutes from the meeting held on 9 April 2026 were agreed as a correct record and signed by the Chair. | Agreed | Open |
| 7 May 2026 | Review of the Protocol for Planning Committee and the Planning Committee Scheme of Delegation to OfficersAGREED that: (a) no changes are currently required to the Protocol for Planning Committee or the Planning Scheme of D... | Agreed | Open |
| 7 May 2026 | Land to Rear of Mill Lane, Caunton (25/01952/FUL)AGREED Moved Councillor M Spoors and Seconded Councillor S Saddington (with 11 votes For and 2 votes Against) that co... | Agreed | Open |
| 7 May 2026 | Land to the East of Hockerton Road, Upton (26/00382/PIP)AGREED Moved Councillor K Melton and Seconded Councillor P Harris (with 7 votes For and 6 vote Against) that contrary... | Agreed | Open |
| 7 May 2026 | Land Adjacent Apple Cottage, Bilsthorpe Road, Eakring (26/00377/PIP)AGREED (with 10 votes For and 2 votes Against) that Permission in Principle be approved. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.