Resolved
AGREED (unanimously) that the report be noted.
Economic Development Committee agreed this item on Wednesday 18 November 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
AGREED (unanimously) that the report be noted.
1.1To update Members on the negotiations with the ‘preferred bidder’ for Ollerton Hall.
2.0Background and Update
2.1Members will recall from the November 2019 update that following an open market process 3 no. compliant bids were submitted for the redevelopment of Ollerton Hall. A preferred bidder was identified (as was an under-bidder in the event that terms could not be agreed), with Officers being given authority to progress with finalising legal terms which secured the following:
The works being proposed by the preferred bidder being subject to the receipt of a planning permission and Listed Building Consent from the Council as Local Planning Authority [the preferred developer has also agreed to undertake public consultation as part of a pre-application process] That any planning and listed building consent applications include for an internal Schedule of Conservation Works (SCW) as defined by the Council That the works approved by the planning permission and listed building consent are implemented by the preferred bidder under a licence agreement, with the site effectively being ‘leased’ until practical completion, when the purchase transaction can take place with the preferred bidder for the agreed price That throughout the building process the Council employs a ‘Clerk of Works’ who will be responsible for the ongoing monitoring of the developers build programme (in terms of quality and timetable). That financial checks on the preferred bidder are concluded
2.2Since November 2019 there has been an understandable pause between the Council and preferred bidder in order to understand any impacts of the Covid-19 pandemic. Encouragingly the preferred bidder has reaffirmed their willingness to enter into contract terms with the Council for the terms and price previously agreed.
2.3The proposed legal documentation comprises an Agreement for Lease and a Lease.
2.4Upon signing, the Agreement to Lease will bind the preferred develop to the following:
To submit to the Council (as Landlord) proposed planning and listed building consent applications within 120 working days, and to in-turn submit these to the Council as Local Planning Authority within a further 20 days of confirmation that the Council agrees the content of the applications To notify the Council of any ‘unacceptable’ conditions within 10 days of receiving grants of planning permission and listed building consent. Unacceptable conditions in this case include that no S106 or CIL charge payments will be applicable. It must be noted that this will be a decision for the LPA to determine based on the planning submission of the preferred developer. This does not pre-determine the issue or bind the LPA. If the LPA determines that S106 contributions or CIL must be provided, the preferred developer will not be bound to purchase the building. A longstop date to secure planning permission. A requirement that the Council’s SCW are included in the approved Listed Building Consent. That when all of the above is met the preferred developer pays the Council its deposit, with the Lease then commencing.
2.5The Lease Secures:
A deposit A requirement to implement the scheme in accordance with the approved planning permissions and listed building consents (as may be amended by the LPA) A requirement for a Clerk of Works to be employed to monitor progress of construction on the site That the preferred developer can purchase the site for the agreed price upon practical completion and Council sign-off (via the Clerk of Works) of the scheme
2.6There remains some further work to conclude on mitigating financial risk in the early stages of implementing the development. Further information on this issue will be reported to the Committee as a late item if required, for forward consideration by the Policy & Finance Committee if required.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Ollerton Hall UpdateReport | 271 KB | DownloadRead as text |
Follow Economic Development Committee at Newark and Sherwood and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Nov 2021 | Minutes of Meeting Held on 8 September 2021AGREED that the Minutes of the meeting held on 8 September 2021 be agreed as a correct record and signed by the Chair... | Agreed | Open |
| 17 Nov 2021 | Forward Plan (December 2021 to November 2022)AGREED that the following items be added to the Economic Development Committee Forward Plan. · EV Charging Points Upd... | Agreed | Open |
| 17 Nov 2021 | Amended Structure for Planning DevelopmentAGREED (unanimously) that: (a) support be given for the amended structure and associated budget virements (increased ... | Agreed | Open |
| 17 Nov 2021 | Highways UpdateAGREED (unanimously) that: (a) the contents of the report be noted; (b) the Policy & Finance Committee be recommended... | Agreed | Open |
| 17 Nov 2021 | Funding Opportunities UpdateAGREED (unanimously) that: (a) the contents of the report be noted; and (b) Policy & Finance Committee be recommended... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.