AGREED (unanimously) that: (a) the Committee noted the current position and progress of the HRA new build development programme delivery and the financial performance thus far. (b) Members fedback their observations about the content and any further information that may be useful in future reports.
Word for word from the decision Newark and Sherwood published for this meeting.Source: democracy.newark-sherwooddc.gov.uk
1.1This report provides the Homes and Communities Committee with the up to date performance of the HRA new build development programme.
2.0Background Information
2.1Newark and Sherwood District Council approved a HRA new build programme to deliver an indicative 335 new additional housing units within the district to increase the Council’s housing stock. The programme commenced in the 2017/18 financial year and is due to complete in the 2022/23 financial year.
2.2A significant site being developed as part of the HRA new build development programme, will provide a 40-unit Extra Care Facility located on land in the Boughton area of the district. The construction of the Extra Care Facility started on site in October 2019 and is due for completion in July 2021. The development has a budget allocation of £8.937 million in August 2019 and secured £2,080,000 via Homes England Grant.
2.3The HRA Development Programme has to date provided 190 additional new council homes. This is the largest single contribution of affordable new build homes by any single provider within the district during this period.
2.4The 190 new council houses have been delivered as follows: 60 units Gladstone House 70 units phase 1 50 units phase 2 10 units phase 3
3.0Update on Progress
3.1In addition to the 190 new homes completed to date, the development programme has a further 70 homes currently under construction (Phase 3) due for completion during 2021 (inclusive of Boughton Extra Care site).
3.2There are also a further 54 potential houses currently being progressed through the planning process for start on sites during 2021, which will form part of Phase 4.
3.3The development programme has experienced delays both with onsite construction and with pre-construction works as a result of the Covid-19 pandemic which stopped construction on site for a period of 6 weeks during March and April 2020. Construction has also been delayed due to the availability of some materials, notably plaster and plaster board. Covid-19 safe working practices have also resulted in reduced trades, which has affected the site construction periods.
3.4The delays are being mitigated and managed out of the development programme by progressing multiple sites concurrently. Sites are also having works phased to ensure works progress with Covid safe working practices in place. Online arrangements are being utilised for progressing meetings, design workshops and briefings.
3.5The HRA new build development programme is utilising council owned land where possible for the delivery of the programme to ensure the existing HRA land is used to its full potential. Of the 190 homes completed to date, all have been built on existing council owned land.
3.6The existing HRA land bank has almost been exhausted in relation to viable development sites. To ensure the programme delivers the targeted 335 additional houses, additional land needed to be identified for acquisition.
3.7So far, the following sites have been identified as potential acquisitions and are currently being progressed:
Newark Old Fire Station The Crescent Bilsthorpe Dale Lane Blidworth Land off Kestrel Drive Rainworth Vicars Close Clipstone
The above sites have the potential to provide approximately 70 HRA properties. Negotiations are at the advanced stages on most of the identified sites.
3.8In terms of range, the HRA new build development programme is providing accommodation from one bed flats to three bed houses across the district.
Below shows areas where new homes have been completed or are currently under construction:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Homes & Communities Committee at Newark and Sherwood and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.