Homes England Compliance Audit Report 2020-21 - HRA 5 Year Development Programme
AgreedFinance2 papers
Audit & Accounts Committee Previous agreed this item on Wednesday 21 April 2021. Below is the council's own wording, with the papers it was decided on.
AGREED (unanimously) that the Committee noted the findings of the Compliance Audit having been accepted by the Council, and a response to Homes England has been sent outlining the steps taken to address the breaches and to ensure they do not re-occur.
Word for word from the decision Newark and Sherwood published for this meeting.Source: democracy.newark-sherwooddc.gov.uk
1.1To inform the Committee the outcome of the Homes England Audit 2020/21 for the Council’s 5 year Housing Revenue Account (HRA) Development Programme.
1.2To advise the Committee of the actions taken and enable the Council to sign of the Audit on Homes England’s Information Management System by the end of April 2021 following an extension agreed with Homes England to accommodate the timing of this Committee.
2.0Background Information
2.1In support of the Council’s 5 years HRA Development Programme a grant of £4,307,635 (years 1 and 2) was provided to the Council through the Homes England affordable housing grants programme. No grant has been claimed in relation to year 3 due to the deadlines for using Right to Buy “1-4-1” receipts.
2.2Grant was claimed in October 2019 for the Boughton Extra Care Scheme to the sum of £1,560,000 (start on site claim) and a further claim for £520,000 will be submitted upon reaching practical completion. As part of due diligence, Homes England have undertaken a routine audit of the delivery of the programme.
2.3It is part of the grant conditions that the outcome of the audits are reported to the Council’s Senior Leadership Team and relevant Committee.
2.4The Compliance Audit Programme provides assurance that organisations receiving grant have met with all Homes England’s requirements and funding conditions and that providers have properly exercised their responsibilities as set out in the Capital Funding Guide, contract and any other supplementary compliance audit criteria.
2.5The scope of the audit includes matters such as compliance with grant conditions, compliance in rent setting, contractor appointment and management and compliance in obtaining relevant planning and other approvals.
2.6Homes England use the audit findings to inform future investment decisions and to assure them that public funds have been used properly.
3.0Audit Findings
3.1Standardised checks (off-site) were made by Council appointed Independent Auditors (Beever and Struthers) on one of two potential scheme in the district that could have been chosen by Homes England: Westhorpe, Southwell. During the audit, the Independent Auditor checks the scheme for compliance using questions from Homes England’s published checklists. The Independent Auditor reviews the information contained on file and reports any findings against Homes England’s policy and procedures. 3.2 The Homes England Lead Auditor reviews the Independent Auditor findings and records any inconsistencies against their audit checklist that covers reconciliation of data as well as compliance with the capital funding guide. Breaches are used as the basis for awarding grades to the provider. The Compliance Audit Report awards Providers a red, amber or green grade based on the number and severity of breaches recorded.
3.3The Grading structure is such that:
Green Grade – the provider meets the requirements through identifying no high or medium breaches.
Amber Grade – one or more high or medium breaches but the authority has not misapplied public funds.
Red Grade – one or more high level breaches and there is a risk that the authority has misapplied public funds.
3.4Newark and Sherwood District Council’s Compliance Audit has concluded that the Council breached two elements of the audit checklist but that in breaching those checklist points, it did not misapply public funds and hence has been awarded an Amber Grade. The full Homes England Audit Findings are attached as Appendix A.
3.5The Council has taken the necessary steps to ensure the breaches the Audit highlighted have been addressed and a process review has taken place to resolve the issues and reduce the risk of future audit failure as detailed below:-
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Audit & Accounts Committee Previous at Newark and Sherwood and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.