CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Newark and Sherwood District Council
Audit & Accounts Committee Previous, Wednesday 21 April 2021 at 10.00am

Fraud Risk Assessment

Agreed Finance 2 papers

Audit & Accounts Committee Previous agreed this item on Wednesday 21 April 2021. Below is the council's own wording, with the papers it was decided on.

Item90

Resolved

AGREED (unanimously) that the Committee noted the content of the report.
Word for word from the decision Newark and Sherwood published for this meeting. Source: democracy.newark-sherwooddc.gov.uk

Follow this further

Built from Newark and Sherwood's papers

What the report saysPro

Report to Audit & Accounts Committee Previous

Purpose of report

1.1This report is to inform Members of the update of the Fraud Risk Register undertaken during February 2021.

2.0Background Information

2.1A fraud risk assessment was first undertaken in June 2014 and a fraud risk register produced and presented to the Committee.

2.2The fraud risks are reassessed periodically and the register updated. The amended Fraud Risk Register as at February 2021 is attached at Appendix A.

3.0Work Undertaken

3.1All of the existing risks have had an in depth review by the Business Manager – Financial Services and the risk owner. These were all considered as to whether there are new fraud types within the risk and whether the controls reflected the current environment.

3.2The risk scores were then reviewed to determine whether the impact or likelihood of any of the frauds occurring has changed since the last review.

3.4The final part of the exercise was to consider whether any further actions were appropriate which would lead to further controls being in place. These further actions are measureable and were given a timeframe for completion.

4.0Results

4.1Eighteen areas of the Council’s activities are considered to be at the risk of fraud, four of which have sub-categories within them. The type of risk is dependent on the service. Based on the existing controls, of those risks, seven are currently considered to be medium risk (amber) and fifteen are low risk (green).

4.2During the assessment process, it was felt that three of the risk scores needed to change from the assessment carried out during February 2020. The three that changed were:

NNDR Fraud – it was felt that the likelihood of fraud occurring in this area was heightened in the current environment, whilst the controls that we have in place mitigate the potential impact.

Economic and Third Sector Fraud – it was felt that the likelihood of this fraud occurring was heightened due to the current grant claim process for business grants. There have been a number of attempts of fraud which officers have found whilst administering the grants on behalf of Government, and hence the opportunity for fraud to occur is greater. Cyber Fraud – It was felt that whilst the impact is major on the organisation in terms of reputation and potential penalties, that the likelihood was possible, as the mitigations and controls that the ICT Business Unit have in place would reduce the likelihood of a successful attack.

4.3The further actions that have been implemented up to April 2021 which will help to mitigate fraud risks include:

Housing Benefit Fraud

 Verification of National Insurance number, proof of employment, residence, financial standing and dependents within the household

Procurement & Contract Fraud (Contracts)

 External Procurement Team independent to the Council assists with procurements  Electronic tender system used for receipt of tenders

Employment (Recruitment Fraud)

 IR35 assessment in place and regular reminders/refreshers sent to all managers on the engagement of agency workers and consultants

Electoral Fraud (Electoral Registration)

 Controls within Electoral software in order to flag unusual registration activity

Insurance Fraud

 External claim handlers have specialist software to identify fraudulent claims  Letter included within insurance pack when sent through to claimant detailing their responsibilities regarding fraudulent claims

Housing Fraud

 Participation in the National Fraud Initiative through supply and matching of application, tenancy and Right to Buy data  Tenancy Audit Programme provides an ongoing detection and prevention of tenancy fraud through, checking, verifying and updating records of tenants and occupants

Economic & Third Sector Fraud

 Use of NFI and Spotlight for pre and post payment checks for Business Grants  Verification of business on Business Rates system for Business Grants

4.4There are a number of new actions that need to be put in place: Housing Benefit Fraud:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Fraud Risk AssessmentReport 282 KB DownloadRead as text
PDF
Item 11a April NSDC: Fraud Risk Assessment FV 2021 Appendix AAppendix 776 KB Download

At this meeting

Whole meeting

Who was there

4 of 10 attended
MS
Councillor Mrs Sylvia MichaelChairman, present
MB
Councillor Mrs Betty BrooksCommittee Member, present
RC
Councillor Rob CroweCommittee Member, present
DC
Councillor Donna CumberlidgeCommittee Member, present
MM
Councillor Mrs Maureen DobsonCommittee Member, apologies
JR
John RobinsonCouncil Staff, expected
NW
Nick WilsonOfficer, expected
AS
Andrew SnapeOfficer, expected
HB
Helen BayneClerk, expected
AH
Amanda HuntOfficer, expected

On this subject at Newark and Sherwood

Search all
  1. Fraud Risk AssessmentThis decision
  2. Fraud Risk AssessmentAgreed
  3. Fraud Risk AssessmentAgreed
  4. Fraud Risk AssessmentAgreed
  5. Fraud Risk AssessmentAgreed
  6. Fraud Risk AssessmentAgreed

More from Newark and Sherwood Audit & Accounts Committee Previous

All decisions
MeetingDecisionOutcome
27 Apr 2022 Minutes of the meeting held on 2 February 2022AGREED that the Minutes of the meeting held on 2 February 2022 be approved as a correct record and signed by the Chai... Agreed Open
27 Apr 2022 Update on the Strategic Risk Management Process and RegisterAGREED (unanimously) that: a) the Committee noted the amendments to the Strategic Risk Register; and b) the Committee... Agreed Open
27 Apr 2022 Internal Audit Progress ReportAGREED (unanimously) that: a) the Committee considered the latest internal audit progress report; and b) the Committe... Agreed Open
27 Apr 2022 Combined Assurance ReportAGREED (unanimously) that the Committee considered the Combined Assurance report. Agreed Open
27 Apr 2022 Annual Internal Audit PlanAGREED (unanimously) that the Audit & Accounts Committee approved the Internal Audit Plan. Agreed Open